Chapter 3: - Lighting up Locomotives
Place a piece of wood along each side and a couple of
pieces across these two. Light a piece of used oily waste
and place it at the centre of the firebox, over this, place small
pieces of wood in a crisscross manner.
When these pieces of wood ignite, add other and heavier
pieces of wood until the fire is well under way. Now close
the firehole, using a blind door.
When placing long lengths of wood into the firebox, care
must be taken to ensure that the brick arch is not struck and
damaged.
To avoid stress to boilers when lighting up, steam should be
allowed to rise gradually to a pressure of 100p.s.i. so that the
firebox, tubes, and boiler plates are allowed to expand
equally, thus preventing leakages. A minimum of four hours
is to be allowed from the time the fire is lit until the time that
the full pressure is achieved.
After steam has been raised and light use of the blower can
be used to prevent smoke escaping from the firehole, the
gauge glasses and their protectors are to be thoroughly
cleaned. Steam and water cocks on the gauge glass
columns are to be closed before cleaning and re-opened
upon completion of cleaning.
3.5
LIGHT-UP CHECK LIST
Light-up Crews and Drivers are to carry out checks and
inspections as detailed on the checklist titled “STEAM
LOCOMOTIVE LIGHT UP AND PREPARATION FOR
TRAFFIC”.
Refer to FIGURE 4 in Annex A.
3.6
ENGINE EQUIPMENT
The engine is checked to ensure that it is equipped with a
pinch bar, long and short pricker, rocking bar, if applicable,
plus a fire shovel, fire bucket and a coupling on each draw
hook. The sand box/s are to be examined to ensure that
they have sufficient dry sand.
3.7
FILLING OF HYDROSTATIC LUBRICATOR
The hydrostatic lubricator must be filled with the cylinder oil
provided. When filling, the steam supply valve is checked to
ensure that it is shut.