Dubai Building Code (2021) - page 18

 

  Index      Manuals     Dubai Building Code (2021)

 

Search            copyright infringement  

 

   

 

   

 

Content      ..     16      17      18      19     ..

 

 

 

Dubai Building Code (2021) - page 18

 

 

Dubai Building Code

Part G: Incoming utilities

G 81

G.7.3 

Substation location and access

The substation room/RMU room shall be directly 

located on the RTA/public road or sikka.
Where the substation/RMU room is located on a sikka, 

the sikka should have a minimum clear width of 6.1 m. 

However, if the proposed RMU room location is less 

than 12 m away from the main road then the sikka can 

be used with a minimum clear width of 3 m.
Access shall be provided for DEWA staff and vehicles 

from the plot limits to the substation and RMU rooms 

(if setback is allocated in the affection plan by the 

competent authority). The access shall be directly open 

to sky and available 24/7.
In a split room/basement room arrangement, the 

transformer room may be located on an internal 

driveway having a clear (3 m wide x 3 m high) and 

direct access from the RTA road.

G.7.4 

Requirements for provision of attic 

slabs above substations and LV electrical 

rooms

Wet facilities shall not normally be located above 

the substation/RMU room/LV electrical room. 

Occasionally, in exceptional unavoidable cases, this 

is permitted at the discretion of DEWA, and in these 

cases the following requirements shall be met.

a)  A reinforced concrete attic slab shall be provided 

above the entire substation/RMU room/LV 

electrical room.

b) 

The entire attic slab and floor slab above, including 

the vertical sides above the attic slab, shall be 

waterproofed using an approved system.

c)  The Consultant shall take full responsibility for 

supervision of the waterproofing works, during 

execution and testing of waterproofing.

d)  All pipes, joints, trap, etc. running in wet areas 

shall be enclosed in an approved waterproofing 

membrane.

e) 

The void between the floor and attic slab shall 

have a clear height of not less than 600 mm. The 

void above the attic slab shall be accessed via an 

opening of 1,200 mm × 600 mm, fitted with an 

aluminium louvered door. The void shall not be used 

for any other purpose and shall have a permanent 

lighting arrangement. A drain pipe shall be provided 

for the attic slab to drain out any water leakage 

through the floor slab. Tiles are not compulsory 

above the attic slab.

f) 

The Consultant shall forward complete floor plans 

to DEWA. The plans shall show the location of 

the wet area and the substation/RMU room/

LV electrical room. The extent of the attic slab 

shall be clearly marked in the plans. Typical cross 

sections through the wet area, substation/RMU 

room/LV electrical room and attic slab shall be 

shown in the drawings, including the waterproofing 

arrangement/systems/materials.

The following checklist shall be followed for attic slab 

construction:
1)  reinforced concrete attic slab above entire 

substation/ring main unit/LV;

2)  clear depth (void) of 600 mm between attic slab 

and floor slab;

3)  aluminium louvered access door of  

1,200 mm × 600 mm to above clear depth (void) 

from outside substation;

4) 

waterproofing of attic slab, floor slab above attic 

slab and vertical side walls;

5)  drain pipe of 40 mm diameter projecting out of 

the attic slab;

6) 

waterproofing of all pipe joints, traps, etc. running 

in wet areas;

7)  lighting inside the void space;
8)  drawings showing the above details attached;
9)  guarantee letter;
10)   no high pressure and vertical pipes passing in the 

void area;

11)   PVC tray provided with a 1:100 slope towards the 

drain pipe.

Dubai Building Code

Part G: Incoming utilities

G 82

G.7.5 

Substation types and areas

G.7.5.1 

Single room substation (RMU and transformer in same room on 

ground floor)

The dimensions for a single room substation where the RMU and transformer are in 

the same room on the ground floor shall conform to Table G.23 and Figure G.39 to 

Figure G.41.

Transformer topologies

Area required 

(m

2

)

Minimum width 

of room (m)

1 × 1,000/1,500 kVA

33 

4.57 

2 × 1,000/1,500 kVA

55 

6.1 

Additional transformer

Additional 25 

Four or more transformers (including necessary equipment)

10

Table G.23  Dimensions of single room substation

Figure G.39  Typical 1 × 1,000 kVA/1,500 kVA substation arrangement (m) (for reference only, not for 

construction)

Key

01: 150 mm øPVC at Trench Level  

02: Transformer Base 

03: RMU

04: RTU  

05: Louvered windows 3.0 m (w) x 2.15 m (h), installed 0.6 m AFFL, 

 

to be constructed to same detail as louvered doors 

06: 0.60 m opening at channel base level 

Dubai Building Code

Part G: Incoming utilities

G 83

Key

01: 150 mm øPVC at trench level 

02: Transformer base

03: RMU

04: RTU

02

01

02

01

03

04

0.40

0.60

3.00

6.00

0.20

0.75

0.40

0.45

0.85

0.45

0.92

0.92

0.30

0.60

0.77

1.00

0.77

0.90

0.20
0.40

0.85

0.45

2.10

0.80

1.30

0.90

0.92

0.67

0.92 0.60

1.00

0.77

0.77

0.90

6.00

9.00

2.98

2.98

3.05

Figure G.40  Typical 2 × 1,000/1,500 kVA substation arrangement (m) (for reference only, 

not for construction)

Dubai Building Code

Part G: Incoming utilities

G 84

Figure G.41 

Typical substation arrangement allowing for additional transformers (m) (for reference only, not for construction)

05

06

02

01

02

01

04

03

9.0

6.00

4.15

1.65

0.40

0.60

0.20

0.75

0.40

0.45

0.85

0.45

0.92

0.92

0.30

0.60

0.77

1.00

0.77

0.90

0.20

0.40

0.85

0.45

2.10

0.80

1.30

0.90

0.92

0.67

0.92

0.60

1.00

0.77

0.77

0.90

Key

01: 150mm øPVC at Trench Level 

02: Transformer base

03: RMU

04: RTU

05: 25 m

2

 for extra transformer

06: 10 m

2

 for extra transformer

Dubai Building Code

Part G: Incoming utilities

G 85

G.7.5.2 

Split room substation (RMU and transformer in separate rooms on 

 

 

ground floor)

The dimensions for a split room substation where the RMU and transformer are in 

separate rooms on the ground floor shall conform to Table G.24, Figure G.42, 

 

Figure G.43, Table G.25 and Figure G.44.

Transformer topologies

Area required 

(m

2

)

Minimum width 

of room (m) 

towards door side

For one RMU set controlling two transformers

9

3

Additional RMU set

7

3

Four or more transformers (including necessary equipment)

10

5

Table G.24 

Dimensions of RMU room, ground floor

Figure G.42  Typical ground floor RMU room spatial arrangements for one 

RMU (m) (for reference only, not for construction) 

Figure G.43  Typical ground floor RMU room spatial arrangements for multiple RMUs (m) (for reference only, not for construction) 

Key

01: RMU

02: RTU

03: 9 m

2

Key

01: RMU

02: RTU

03: 9 m

2

04: 7 m

2

 for extra RMU

05: 10 m

2

 for four and above transformers

03

01

02

3.0

2.0

3.0

0.40

0.60

1.36

1.55

1.00

0.20

0.28

0.28

2.44

1.03

0.60

04

03

05

02

01

3.0

3.0

2.33

3.33

0.40

0.60

1.36

1.55

1.00

1.03

0.60

Dubai Building Code

Part G: Incoming utilities

G 86

Transformer topologies (ground floor)

Area required 

(m

2

)

Minimum width 

of room (m)

1 × 1,000/1,500 kVA

21

4.57

Extra area required for an additional transformer

21

For 2 × 1,000/1,500 kVA transformers 

42

6.1

Table G.25 

Dimensions of transformer room, ground floor

02

01

04

03

4.20

3.05

0.20

0.20

5.00

3.05

5.00

0.20
0.40

0.45

0.92

0.92

1.70

0.60

0.77

0.77

1.28

0.90

Figure G.44  Typical ground floor transformer room spatial arrangements (m) (for reference only, not for construction)

Key

01: 150 mm øPVC at trench level 

02: Transformer base

03: Trench

04: 21 m

2

 for extra transformer

Dubai Building Code

Part G: Incoming utilities

G 87

G.7.5.3 

Basement substation (RMU room in ground floor and transformer 

 

 

room at basement level)

The dimensions for a basement substation where the RMU room is on the ground 

floor shall conform to Table G.26, Table G.27, Figure G.43 and Figure G.44.

RMU room, ground floor

Area required 

(m

2

)

Minimum width 

of room (m) 

towards door side

One RMU set controlling two transformers

9

3

Additional RMU set

7

Four or more transformers (including necessary equipment)

10

5

Transformer topologies (basement level)

Area required 

(m

2

)

Minimum width 

of room (m)

1 × 1,000/1,500 kVA

21

4.57

Extra area required for an additional transformer

21

For 2 × 1,000/1,500 kVA transformers

42

6.1 

Table G.26 

Dimensions of RMU room, ground floor and basement substation

Table G.27  Dimensions of transformer room, basement substation

Dubai Building Code

Part G: Incoming utilities

G 88

Parameter

Requirement

Equipment

1 × 1,000/1,500 kVA transformer and 1 × RMU

Dimensions

6.1 m × 6.1 m

Additional requirements

Substation space shall be located along RTA/public road or sikka. 

LV room shall be adjacent to the substation room.

 

Soakaway shall be 3.66 m (minimum) away from the substation.

G.7.5.4 

Open to sky dedicated substation with private panel

The dimensions of an open to sky dedicated substation with private panel shall 

conform to Table G.28 and Figure G.45.

Table G.28  Open to sky, dedicated substation parameters

Figure G.45 

Typical open to sky dedicated substation spatial arrangement (m) (for reference only, 

not for construction)

05

02

01

03

06

04

07

6.10

6.10

0.92

0.92

0.60

0.77

0.77

1.53

1.53

0.90

0.60

0.40

0.30

1.03

0.40

0.20

0.40

0.85

0.45

0.60

0.60

0.30

Key

01: 150 mm øPVC at trench level 

02: Transformer base

03: RTU

04: RMU

05: Open to sky

06: Compound wall shall not be 

more than 2.1 m

07: RTA road/sikka

Dubai Building Code

Part G: Incoming utilities

G 89

G.7.5.5 

Open to sky pocket substation

The dimensions of an open to sky pocket substation 

shall conform to Table G.29, Figure G.46 and 

 

Figure G.47.

Equipment

Dimensions (m)

1 × 1,000 kVA

4.57 × 3.66

2 × 1,000 kVA

6.1 × 6.1

Table G.29  Open to sky, dedicated substation parameters

The substation shall be directly located along the RTA/

public road or sikka. The side of the substation with 

the dimension 4.57 m or 6.1 m should be facing the 

RTA/public road/service road.
The substation shall be suitable for releasing supply 

through individual feeders, each of 400 A (maximum 

rating).
The height of the compound wall around the 

substation foundation (on three sides) shall be not 

more than 2,100 mm.
Any soakaway shall be a minimum of 3.66 m from the 

substation.

03

04

05

01

02

3.04

0.38

0.30

1.40

0.60

0.20

0.30

0.30

4.57

2.44

0.30

3.66

Figure G.46  Typical 1 × 1,000 kVA pocket substation spatial arrangement (m) (for reference only, not for construction)

Key

01: Pocket substation base

02: Trench

03: Earth pits

04: Open to sky

05: RTA road/sikka

Dubai Building Code

Part G: Incoming utilities

G 90

01

02

03

03

04

05

6.10

6.10

0.30

0.30

0.30

1.06

1.06

0.60

0.60

1.58

0.53

0.40

2.74

0.60

2.36

1.60

0.53

1.66

Key

01: Pocket substation No.1 

02: Pocket substation No.2 

03: Trench 

04: Compound wall less than 2.1m 

05: RTA road/sikka  

Figure G.47  Typical 2 × 1,000 kVA pocket substation spatial arrangement (m) (for reference only, not for construction) 

Dubai Building Code

Part G: Incoming utilities

G 91

G.7.5.6 

DEWA control room requirements for direct 11 kV supply

The dimensions of a DEWA control room shall conform to Table G.30, Figure G.48 

and Figure G.49.

11 kV feeder Area (m

2

)

Dimension 

(m)

Area for 

every 

additional 

feeder (m

2

)

Additional requirements

Two feeders

29.16 

5.4 × 5.4

Regular type of RMU room made of 

block work and RCC slab.

Two feeders

37.2 

6.1 × 6.1

37.2

Open to sky with FGRP kiosk (to be 

supplied by DEWA). 

Height of the wall around the 

substation foundation (on three sides) 

not more than 2.1 m.

Table G.30  DEWA control room requirements, 11 kV supply

Figure G.48 

Typical dedicated 11 kV/RMU room (enclosed) (m) (for reference only, not for construction) 

Key

01: RTU

02: Trench

03: DB

04: 8 m

2

 for extra RMU

04

01

02

02

03

5.40

0.90

0.30

0.45

0.85

3.05

0.60

0.42

1.18

1.18

0.60

3.03

3.03

0.42

5.40

1.50

Dubai Building Code

Part G: Incoming utilities

G 92

Figure G.49 

Typical dedicated 11 kV/RMU enclosure (open air) (m) (for reference only, not for construction) 

Key

01: RTU

02: Trench

03: DB

04: Compound wall less than 2.1m

01

02

02

03

04

0.45

0.45

3.70

0.45

0.45

0.45

0.30

0.30

0.45

0.45

0.30

3.00

0.75

0.85

3.00

0.75

0.85

6.10

Dubai Building Code

Part G: Incoming utilities

G 93

G.7.6 

Substation ventilation and fire 

 

 

safety provisions

G.7.6.1 

General

Substations shall have adequate ventilation 

using natural louvers, mechanical ventilation or a 

combination of both, depending upon how many sides 

of the transformer room have direct access to an 

exterior wall.

Substations shall be 2 h fire rated to conform to Table 

1.9, Ch. 1 of UAE FLSC 

[Ref. G.1]

. Exterior walls do not 

need to be fire rated unless there is a risk of exterior 

fire spread and the wall is fire rated in accordance with 

Ch. 1 of UAE FLSC 

[Ref. G.1]

.

G.7.6.2 

Natural ventilation via two exterior walls

Substations at ground floor shall be naturally 

ventilated. A minimum of two sides shall be ventilated 

using aluminium louvered doors and fixed aluminium 

louvers.

Fixed aluminium louver window(s) should be at 

 

600 mm above the outside ground level.
Aluminium louvered doors shall be of the following 

sizes:
a) 

transformer rooms: 3.05 m wide × 2.75 m high;

b) 

RMU rooms: 2.4 m or 3.05 m wide × 2.75 m high.

NOTE: Door details are shown in Figure G.50 and 

Figure G.51.

Substations shall be 2 h fire rated to conform to Table 

1.9, Ch. 1 of UAE FLSC 

[Ref. G.1]

. Exterior walls do not 

need to be fire rated unless there is a risk of exterior 

fire spread and the wall is fire rated in accordance with 

Ch. 1 of UAE FLSC 

[Ref. G.1]

.

At least one exit door with door swing in the direction 

of egress shall be provided. If the door is in a 2 h fire 

rated fire rated wall, then the door shall be 90 min fire 

rated. Equipment access doors maybe sufficient to 

meet this requirement.
Walls enclosing covered parking ramps at the  

exit/access of the basement are interior walls. Louvers 

shall not be permitted in these walls unless they are 

protected in accordance with G.7.6.3.

G.7.6.3 

Forced ventilation with no exterior walls

RMU rooms shall be at the ground floor. RMU rooms 

shall be 2 h fire rated to conform to Table 1.9, Ch. 1 of 

UAE FLSC 

[Ref. G.1]

. Exterior walls do not need to be 

fire rated unless there is a risk of exterior fire spread 

and the wall is fire rated in accordance with Ch. 1 of 

UAE FLSC 

[Ref. G.1]

.

Independent mechanical ventilation shall be provided 

to transformer rooms with no exterior walls (e.g. in a 

basement). All equipment shall be accessed from the 

landlord side. 

The mechanical ventilation shall be sized to 

maintain the ambient temperature in the substation 

at maximum of 55 °C based on an outside air 

temperature of 48 °C. Supporting calculations shall be 

provided to justify the proposed exhaust and supply 

rates. 

Typical details are shown in Figure G.52.
Louvers shall be provided on two sides of the room as 

a back-up to the mechanical ventilation system.
The total grill area shall be not less than 14.9 m

2

 for 

1,000 kVA transformer and not less than 18.6 m

2

 for 

1,500 kVA transformer.

Transformer rooms shall be 2 h fire rated to conform 

to Table 1.9, Ch. 1 of UAE FLSC 

[Ref. G.1]

Louvers shall be protected by automatic 2 h fire rated 

shutters or 2 h fire rated curtains on the landlord side 

of the louvers (see Figure G.53). 
Two combined fire and smoke detectors shall be 

provided on the landlord side of the louvers. They 

shall be located on the slab soffit within the vicinity 

of the louver in accordance with the dimensional 

requirements of Table 8.1 (item 25, door release 

service), Ch. 8 of UAE FLSC 

[Ref. G.1]

.

Dubai Building Code

Part G: Incoming utilities

G 94

Upon activation of both combined fire and smoke 

detectors, the fire rated shutters or fire rated curtains 

shall automatically close and the mechanical ventilation 

to the transformer room shall automatically stop.

The fire rated shutters or fire rated curtains shall have 

an automatic override switch on the landlord side.

At least one fire rated (90 min) exit door, with door 

swing in the direction of egress, shall be provided.
Equipment access doors may include louvers, but they 

shall be protected by automatic fire rated shutters or 

fire rated curtains on the landlord side of the louvers. 

The fire curtains/shutters will close in a fire and block 

the equipment doors therefore an alternative exit shall 

be provided and the equipment doors shall not be 

marked as an exit. 

Figure G.50 

Details of substation louvers

N

N

L

J

K

M

I

O

O

O

P

P

I

M

K

L

J

Dubai Building Code

Part G: Incoming utilities

G 95

Figure G.51 

Details of substation doors

Key

01: 3.05 m, or 2.44 m if located where it opens onto 

a sikka/road, or as per plan

02: Slot

A: Central mullion

B: 40 mm × 20 mm bracing aluminium box

C: Heavy duty hinges

D: Heavy duty aluminium drop with locking hook

E: Heavy duty brass tower bolt (750 mm) 

F: Heavy duty brass tower bolt (300 mm) 

G: Handles

H: Rawl bolt

a) Elevation

b) Door plan

c) Details of additional locking arrangement

Dubai Building Code

Part G: Incoming utilities

G 96

Figure G.52  Forced ventilation of transformer room in basement

4 x 1,000 kVA

Dubai Building Code

Part G: Incoming utilities

G 97

Figure G.53  Plan and section view of a basement transformer room with fire rated shutter/curtains over the louvers (m)

Key

01: 150 mm øPVC duct at trench level 

02: Transformer base 

03: Combined heat/smoke detector 

04: 2 h fire/smoke curtain on landlords side to protect louver opening 

05: Louvered door 

06: 90 min fire rated door  

02

01

04

04

05

06

AA

03

03

03

AA

AA

3.05

5.00

4.20

0.20
0.40

0.85

0.45

1.70

0.45

0.20

0.98

0.92

0.92

0.60

0.77

0.77

1.28

0.90

5.00

Dubai Building Code

Part G: Incoming utilities

G 98

G.7.7 

Transporting equipment to basement transformer rooms

Transporting transformers between the public road and the transformer room is the 

customer’s responsibility. The requirements set out in Table G.31 shall be followed.

Element of transport route

Requirements 

Ramp

Straight, with a minimum width of 3 m. Sloped curves and speed 

breakers (humps) are not permitted. A minimum clear height of  

3 m shall be maintained between the public road and the transformer 

room. The slope of the ramp shall be maintained at a maximum of 

1:10 (10%).

Slab cut-out opening

The cut-out size shall be 3 m × 3 m and adjacent to the main 

 

RTA/public roadside.
The area below the cut-out at basement level shall be designated as 

a loading/unloading bay.

The area above the cut-out shall be open to sky. If there is a floor 

above then a minimum clear height of 7 m shall be maintained. 

Substation 

type

Cable arrangement 

General 

substation 

The cable trench inside a substation shall have a clear depth of 950 mm from the 

substation FFL, as indicated in Figure G.54.
Cable route/arrangement from plot limit to the substation (if setback confirmed in 

affection plan issued by competent authority) shall be through cable trench with 

removable slab as shown in Figure G.55, or cable tray at high level basement.

The cable route/arrangement from RMU room to transformer room for split/

basement substations shall be through cable trench with removable slab as shown in 

Figure G.53, or cable tray at high level basement.
If cables are passing through a traffic movement area, concrete encased ducts with 

manholes at both ends shall be provided. Spare provision for ducts shall be provided 

in accordance with DEWA requirements. Cable ducts shall have an internal diameter 

of 150 mm.

NOTE: Cut-out at 950 mm depth from outside level (towards road/sikka) should 

be provided for HV cable entry. Typical arrangements are shown in Figure G.54 and 

Figure G.55.

Basement 

or split 

substation 

For basement/split substation, the transformer room cable trench depth shall be 

 

500 mm below finished floor, subject to DEWA approval.
For cable tray arrangement, a clear depth of 950 mm shall be provided from the 

substation FFL up to the bed of the tray, with minimum clear depth of 450 mm 

between bottom of the slab and the bed of the tray.
Cable installation/maintenance space of minimum 1.2 m shall be provided on at least 

one side of cable tray arrangement.
The cable tray shall pass through public/open area and not through any closed  

area/room (there shall be no services, pipes, etc. below the cable tray).

NOTE: Cable route from RMU to transformer room should be straight (without 

turns/bends). Where unavoidable, a minimum bending radius of R = 950 mm might 

be accepted.

Table G.31 

Transformer transportation requirements – main road to transformer room

Table G.32  Substation cable arrangement

G.7.8 

Substation cable arrangement

Cable arrangements are subject to DEWA approval and shall conform to Table G.32.

Dubai Building Code

Part G: Incoming utilities

G 99

Figure G.54 

Typical substation cable trench setting out details

Figure G.55 

Cable lying arrangement in concrete trench

300

950

150

150

300

650

Key

01: Wall

02: Chequered plate

03: Channel

04: Opening

05: Slope

06: Pre-cast concrete

Key

01: Pre-cast concrete kerb

02: Cover heavy duty

03: 200 mm thick block work

04: Cables

05: 0.08 m diameter drain in floor at 2 m c/c

06: 30 N/mm

2

 pre-cast concrete

07: Polythene sheet

08: Compacted earth

09: Channel width – variable according to number of cables

Dubai Building Code

Part G: Incoming utilities

G 100

G.7.9 

Direct 11 kV supply for super high- 

 

rise towers above 200 m

G.7.9.1 

Intake arrangement

The point of supply to a super high-rise tower is the 

supply intake of MV switchgear, which is located 

adjacent to the DEWA metering/control room. The 

switchgear shall be provided with a circuit breaker, with 

E/F and O/C protection.

The customer is responsible for all equipment beyond 

the point of supply. DEWA does not supply, operate or 

maintain any equipment installed above ground level.
All equipment procured by the customer shall have 

dual ratio (6.6/11 kV) unless it is clearly stated to be 

11 kV.
All equipment shall conform to the relevant 

international standards (IEC standards).

Total transformer losses shall not exceed 1.5% of 

rated capacity.
Only cast resin transformers shall be installed in 

residential/commercial buildings.

Technical justification shall be submitted for availing 

direct 11 kV supply to the super high-rise building 

for locating transformers above ground level(s). This 

depends on the height of the building, size of load, type 

of load, etc. When buildings exceed 200 m then DEWA 

may accept direct 11 kV supply.  The designer shall 

consult with DEWA to confirm.

MV switchgear is suitable for termination of maximum 

cable size of 3 × 300 mm

2

 XLPE/PVC/SWA/PE 

aluminium/copper cable with heat shrinkable type 

cable terminations.
Termination at a private MV switchgear incomer shall 

be installed by the consumer. Terminations at a DEWA 

RMU shall be installed by DEWA.

G.7.9.2 

Protection requirements

Suitable protection and interlocking shall be provided 

to ensure that a private substation does not have a 

negative impact on the DEWA system.

The private substation shall be configured such that 

its protection operates before the DEWA protection 

during a fault.
Mechanical and electrical interlocks shall be provided 

so that the incomers are not paralleled. In substations 

with multiple switchboards, the interlock shall extend 

to all of the switchboards.
Incomer protection relays shall conform to IEC 60255. 

NOTE 1: Compliance is supported by type test 

certificates and guaranteed routine manufacturer’s 

works test certificates. Only certificates confirming 

that relays have passed the type tests need to be 

submitted to DEWA.

The overcurrent relay shall operate correctly for fault 

currents up to 31.5 kA.
Instrument transformers shall conform to IEC 61869. 

NOTE 2: Compliance is supported by type test 

certificates and guaranteed routine manufacturer’s 

works test certificates. Only certificates confirming 

that current transformers (CT) have passed the type 

tests need to be submitted to DEWA.

The incoming current transformer shall be 

dimensioned such that the protection scheme operates 

effectively for a fault current of 31.5 kA.
Reverse power protection shall be provided to enable 

in-feeds to faults within the DEWA 11 kV network to 

be cleared within 3 s.

Dubai Building Code

Part G: Incoming utilities

G 101

G.8 

Liquefied petroleum gas (LPG)

G.8.1 

General

LPG installations shall comply with Ch. 11 of UAE FLSC 

[Ref. G.1]

. LPG main 

distribution pipes serving multiple floors of a building shall be contained within a 

dedicated 2 h fire rated shaft.

Dubai Building Code

Part G: Incoming utilities

G 102

G.9  Water

DEWA specification

Sample drawing 

number

Sample drawing 

title

Domestic water 

meter installation 

in meter room - 

guidelines

PEW-STD-

AMI-003 

Water meters in 

meter room

Bulk meter 

installation 

in chamber - 

guidelines 

PEW-STD-

AMI-004 

Bulk water meters 

in chamber (for bulk 

meters 50 mm and 

greater diameter 

connection)

Bulk meter 

installation 

in chamber - 

guidelines

PEW-STD-

AMI-005 

50 mm diameter 

bulk water meter 

installation in 

chamber  

(2 in meter with 

LDPE connection)

G.9.1 

Water metering 

A DEWA main meter shall be installed to measure 

and record the water demand and consumption of a 

building. 
Each individual tenancy in a building shall have a sub-

meter installed which is connected to the building main 

meter.  
Additional requirements for sub-metering are detailed 

in 

H.5.2.6

Where a building management system or central 

control and monitoring system is installed, metering 

shall be integrated into the system to allow real time 

profiling and management of water demand and 

consumption.

G.9.2 

Design and installation of water  

 meters

The design and installation of DEWA water 

meters, including smart metering communications 

requirements, shall follow the specifications and 

sample drawings in the DEWA Circulars and 

Regulations 

[Ref. G.8]

 and as listed in Table G.33.

Table G.33 

DEWA specifications and sample drawings for design and 

installation of water meters

Dubai Building Code

Part G: Incoming utilities

G 103

G.10  District cooling

G.10.1  General

This section identifies the coordination requirements 

and common technical requirements related to district 

cooling installations and their connection to building 

cooling systems. 

G.10.2  Coordination with district cooling  

 Providers

Depending on the location of the development, the 

Customer shall contact the relevant district cooling 

Provider to obtain the latest district cooling technical 

design guidelines 

[Ref. G.9]

.

Coordination shall start in the concept design phase 

and continue as necessary in later design stages. The 

scope of work shall be agreed as part of the service 

agreement between the two parties.

NOTE: district cooling Providers in Dubai include (but 

are not limited to) those listed in 

[Ref. G.9]

.

The building design parameters shall conform to 

the district cooling Provider’s specific technical and 

interface requirements 

[Ref. G.9]

. The following 

parameters shall be determined as a minimum:
a)  cooling capacity requirements;
b)  pipe connection size;
c)  supply/return chilled water temperature on the 

primary and secondary sides;

d)  maximum allowable system pressure; and
e)  design water velocities/pressure drop.

G.10.3  Common technical requirements

The following common technical requirements shall be 

met for all developments featuring district cooling. 

NOTE 1: The list is provided to assist Customers but 

does not replace requirements from the district cooling 

Providers. 

a)  The energy transfer station (ETS) shall 

accommodate the district cooling Provider’s heat 

exchangers (HEXs), and all associated equipment 

for the primary and secondary sides of the HEXs. 

The chilled water system configuration shall be 

determined by the Customer and coordinated with 

the district cooling Provider.

NOTE 2:  Figure G.56 and Figure G.57 show 

examples of installed ETS pipework and pumps.

b)  The secondary side shall include all equipment 

for supplying chilled water to the premises. 

The pipework installation shall conform to the 

requirements identified in 

H.4.13

.

c) 

The location, configuration and space dimension 

for the ETS and valve chamber (VC) shall be agreed 

taking into account the route and availability of the 

main district cooling pipes. Space planning for the 

ETS, including accessibility of the ETS plant, shall 

be included in the design at the concept design 

phase.

d)  The structural Engineer shall design the supporting 

structure to withstand the loading imposed by 

equipment in the ETS and along the equipment 

access route.

e)  The ETS shall be provided with electric power, 

lighting, communication, potable water, drainage, 

ventilation and cooling in accordance with 

Part G

 

and 

Part H

f)  The district cooling facility, including but not limited 

to the ETS, cooling towers and other mechanical 

and electrical plant rooms, shall conform to the fire 

safety requirements of Ch. 14 of the  

UAE FLSC 

[Ref. G.1]

.

g)  In accordance with the service agreement, the 

district cooling Provider or Customer shall provide 

heat exchanger (HEXs) and primary side chilled 

water installation (including all piping from the 

underground) to the VC, and to and inside the ETS.

h)  The district cooling Provider shall design the VC in 

coordination with relevant authorities and based 

on the premises load demand. VC civil construction 

shall be carried out by the Customer or district 

cooling Provider in accordance with the service 

agreement. 

i)  A smart energy metering system shall be provided 

in accordance with 

H.4.14

 as part of the primary 

chiller water system.

j)  The Customer shall provide the secondary side 

chilled water piping systems pumps, cooling coils, 

and control valves and electrical equipment.

k)  The secondary chilled water circuit design shall 

align with the supply stated by the district 

cooling Provider, and shall return chilled water 

temperatures.

Dubai Building Code

Part G: Incoming utilities

G 104

l)  The chilled water distribution system and control 

system on the secondary side shall be designed as a 

variable flow chilled water system. It shall use two-

way control type valves, e.g. pressure  independent 

control valves.

m) The secondary side system shall incorporate a 

bypass to avoid chilled water stagnation. The 

minimum pump flow shall correspond to a 

maximum chilled water flow of 5% of the full 

design flow. 

n)  The chilled water pumping system installed in the 

secondary side in the ETS shall allow the chilled 

water flow to vary between 5% and 100% of the 

full design flow. The chilled water pumping design 

and arrangement shall account for redundancy 

and part load conditions (during winter/night-time 

operation).

o) 

Secondary system pipework shall be flushed, 

cleaned and provided with chemical dosing to 

provide corrosion protection, and to enable the 

minimum required water condition parameters 

of the district cooling Provider to be achieved. 

Flushing shall be carried out using a bypass to avoid 

a flow of contaminated water through the HEXs. 

p)  A water sample shall be analysed by a district 

cooling Provider-approved testing laboratory, to 

verify conformity to the specified water quality 

parameters. Analysis results shall be submitted to 

the district cooling Provider before any water flow 

is allowed through the HEXs.

q)  The secondary side chilled water distribution 

system shall be accurately flow-balanced in order 

to achieve the specified temperature difference. 

This work shall be performed in accordance with 

balancing principles for variable flow systems.

r)  The pumps shall be provided with variable 

frequency drives (VFDs). The pump VFDs shall 

be specified with the necessary communication 

protocol to allow the district cooling Provider to 

monitor the status of the VFDs.

s)  Differential pressure transmitters shall meet the 

following minimum requirements.
1)  They shall be of industrial grade, and suitable 

for the environment in which they are installed.

2)  They shall provide a DC output of 4 mA to 20 

mA with a maximum loop resistance of 1,000 Ω. 

3)  They shall be linear in function, with differential 

pressure, and capable of isolation from the pipes 

that they monitor.

t) 

The specific products to be used for pumps, 

VFDs, and differential pressure and temperature 

transmitters utilized on the secondary circuits shall 

be agreed and confirmed with the district cooling 

Provider.

u)  An industrial grade programme logic controller 

(PLC)/human machine interface (HMI) controller 

with open protocol capability shall be provided 

in the ETS. The ETS PLC shall be integrated with 

other control systems in the district cooling plant 

and associated building. Single mode fibre-optic 

connectivity shall be included with district cooling 

plant and ETS integration. Sleeves for fibre-optic 

shall be included along with a chilled water pipe and 

both shall be extended up to the ETS PLC control 

panel.

v) 

The chilled water pipes and fibre-optics to the VC/

interface point shall be routed in accordance with 

the service agreement. The ETS room shall be 

located as close as possible to the plot VC and plot 

limit.

NOTE 3: The district cooling Provider might choose 

to review the design of the secondary side chilled 

water distribution and air handling equipment, to 

give confidence that the allowable chilled water 

temperature difference is likely to be achieved.

Dubai Building Code

Part G: Incoming utilities

G 105

Figure G.56 

Examples of ETS pipework

Figure G.57 

Examples of ETS pumps

Dubai Building Code

Part G: Incoming utilities

G 106

G.11  Telecommunications

G.11.1  Design and installation of 

telecommunications infrastructure

G.11.1.1  General requirements

This section provides the requirements for the design 

of all telecommunications (telecom) infrastructure 

installations within any development including new 

build, “greenfield”, redevelopment, “brownfield”, and 

additions, alterations, renovations or refurbishments to 

existing buildings, in Dubai.
These requirements are based on version two of the 

Telecommunication Regulatory Authority (TRA), In-

Building Telecommunication Network – Specification 

Manual Guidelines for FTTx in new 

 

Buildings 

[Ref. G.10]

. If the TRA is updated to give 

more stringent requirements, these shall be used in 

preference to the DBC.

This section specifies the minimum requirements 

to provide a baseline infrastructure. There is no 

restriction to extending the baseline, provided that 

the design meets the requirements in this section and 

does not prevent competition, e.g. by using proprietary 

standards. 
All telecom infrastructure shall enable each user/

tenant freedom of choice between telecommunication 

service providers (SPs). 

The requirements cover all of the following aspects of 

infrastructure:
a)  civil infrastructure and entry ducts;
b) 

fibre concentration point (FCP) space(s) per 

development or plot;

c)  meet-me-room (MMR) space(s) per development 

or plot;

d)  telecom rooms;
e)  indoor mobile service and rooftop rooms;
f)  building pathways;
g)  OSP cables;
h)  ISP cables.

Passive optical fibre infrastructure shall be provided to 

support deployment of FTTx. 

Copper access networks shall not be used for SP 

services.
All buildings shall be equipped with physical 

infrastructure capable of supporting multiple high-

speed SP networks which can be easily accessed by 

the SP. The Developer shall assume a minimum of 

two active SPs in the region, but may future-proof the 

infrastructure by incorporating provision to support a 

possible third SP.

New installations shall be based upon a minimum of 

category 6 balanced twisted pair cabling as specified in 

ISO 11801 1. Designers may future-proof designs by 

providing category 6 A cabling, which supports higher 

data rates and provides support for newer power-

over-ethernet (PoE) standards that are typically used 

for video surveillance camera and wireless local area 

network access points. Where category 6 A is specified, 

unshielded twisted pair (UTP) or shielded twisted pair 

(STP) may be utilized.
Category 6 cabling (structured cabling system) shall as 

a minimum conform to the requirements specified in 

G.11.4.10.7.
Cabling within the tenant space (e.g. multi-tenanted 

commercial/retail building, home, unit, flat, apartment, 

single family home or similar) for onward distribution 

of services beyond the tenant equipment is not in the 

scope of these requirements.
The requirements of this section do not replace 

a detailed specification, act as instruction for 

untrained persons, or provide for every specific design 

circumstance. For situations beyond the scope of these 

requirements, the TRA shall be consulted to obtain 

further clarity and guidance.

Dubai Building Code

Part G: Incoming utilities

G 107

Special buildings or development areas (e.g. hospitals, 

shopping malls, stadiums, data centres, public 

buildings) will need further enhanced requirements. 

Individual agreements shall be bespoke and beyond 

that of the minimum requirements established in this 

section.
Installations where special telecom requirements might 

exist shall be referred to a registered Dubai SP at the 

preliminary design stage to incorporate any specific 

requirements above that of this section.

G.11.1.2  Telecoms service

To support the deployment of SP optical broadband 

networks and services, the Developer shall design and 

install in-building elements of telecom infrastructure 

up to and within single and multi-tenant premises 

(to include single or multiple buildings, villa complex, 

warehouses, etc.).
Standardized telecom infrastructure shall be provided 

for FTTx, to enable seamless interworking of all 

network parts. All designed infrastructure shall support 

ethernet and GPON.
To optimize investments, SPs shall share essential 

infrastructure elements including telecom rooms, 

ducts, cable pathways and cabling.

Dubai Building Code

Part G: Incoming utilities

G 108

G.11.1.3  Reference architecture

The general schematics in Figure G.58 and 

 

Figure G.59 shall be used as the basis for infrastructure 

design. Adaptations which enhance the resilience or 

performance of telecom infrastructure are permitted, 

if agreed by consultation with all stakeholders. Any 

such adaptations shall meet the requirements of this 

section. 

NOTE: The reference architecture shown in  

Figure G.58 allows the end user to change SPs. 

 

It also allows service to be provided by multiple SPs  

in parallel if required.

Figure G.58 

Reference architecture

Key

01: Property boundary

02: External cabling (OSP)

03: In building cabling (ISP)

04: Equipment patch cord

05: Tenant/unit cabling

06: Service provider 1

07: Service provider 2

08: SP feeder cabling

09: SP distribution cabling

10:  MMC/MMR

11: MTR

12: FTR

13: Consolidation cabinet

14: Building 1 boundary

15: Building n boundary

Dubai Building Code

Part G: Incoming utilities

G 109

Key

01: FTR-7th floor mini ODF (splicing point)

02: FTR-6th floor

03: FTR-5th floor 

04: FTR-4th floor mini ODF (splicing point)

05: FTR-3rd floor

06: FTR-2nd floor

07: FTR-1st floor mini ODF (splicing point)

08: Multicore indoor fibre cables

09: 4 core SM drop fibre cables from each unit to 

mini ODF (splicing point) in FTR

10: du PoP-A and B

11: Etisalat PoP-A and B

12: MMC/MMR

13: MTR with splitters

14: SP feeder cabling

15: SP distribution cabling

Figure G.59 

Schematic diagram for typical building connectivity

Dubai Building Code

Part G: Incoming utilities

G 110

The design shall include:
i)  shared SP infrastructure;
ii)  performance requirements which achieve system 

resilience;

iii)  a roles and responsibilities matrix (see G.11.2);
iv)  safeguards for future adjacent developments and 

OSP extensions to these, clearly identified as such 

on the design drawings;

v)  provision or cessation of service to enable 

each tenant to adopt either SP without on-site 

intervention;

vi)  a choice of SP; 
vii)  provisions for a minimum of two SPs;

NOTE 1: The design may include an option to 

enhance this provision to support a future third 

SP.

viii) 

a minimum of four optical fibre cores per premise, 

for a two-SP design, enabling the possibility for 

either SP to provide an ethernet-based service;

ix) 

SP OLTs/fibre switches connected directly to the 

dedicated fibre cores allocated to them;

NOTE 2: Large developments can have local SP 

OLTs where high tenant numbers are expected.

x)  an MTR for a minimum of two SPs; 
xi)  rack space and SP cabling allowances in the MTR 

for two SPs;

xii) 

dedicated end-to-end FTTx network with full-

service delivery control for each SP;

xiii)  the required splitters for GPON architecture 

inside the MTR for each of the two SPs (SPs shall 

provide their own feeder fibre connecting the OLT 

to the splitter);

xiv) 

in-building cabling with multicore optical fibre 

cable; 

xv) 

at least one dedicated fibre from each SP OLT 

to each home, commercial/retail unit or other 

building;

xvi)  within each tenant space, a consolidation cabinet 

configured to house a minimum of two ONTs in 

parallel.

The infrastructure design shall avoid single points of 

failure. The design shall enable physical diversity and 

redundancy in feeder and distribution cabling, and in 

site-wide distributor cabling. For example, a site with 

multiple buildings shall have more than one MMC and 

FCP.

The design shall include all the following elements of 

reference architecture:
a)  duct infrastructure from SP stubs/development 

boundary to MMC;

b)  development MMC;
c)  campus duct from MMC to BEPs, including 

handholes, turning chambers and pulling chambers 

as required;

d)  BEPs to accommodate SP and campus telecom 

cabling;

e) 

FCPs;

f)  telecom rooms; and
g)  in-building cabling.
h)  Design standards shall be applied by building type:

1)  residential, designed in accordance with ISO/

IEC 11801-1, ISO/IEC 11801-4 and ISO/IEC 

11801-6;

2)  commercial, designed in accordance with ISO/

IEC 11801-1, ISO/IEC 11801-2 and ISO/IEC 

11801-6;

3)  industrial, designed in accordance with ISO/

IEC 11801-1, ISO/IEC 11801-2 and ISO/IEC 

11801-3 and ISO/IEC 11801-6.

Dubai Building Code

Part G: Incoming utilities

G 111

No. Item description

Masterplan 

Developer  

(site wide)

Building Owner 

(individual 

buildings)

Service 

providers  

(SP)

1

Lead-in ducts, including connections 

to entry manholes outside building 

boundaries.

P

2

Installation of manholes and ducts 

outside the building/boundaries 

(including cover).

P

3

Entry boxes inside the building/complex 

of villas boundaries (including the 

cover).

P

4

Supply and installation of 4-core SM 

fibre terminal box with duplex LC/APC 

adaptors and pigtail and two SC/APC 

adaptors.

P

5

Fibre optic cable supply, pulling/ 

blowing, termination and testing from 

the MTR to FTR and drop fibre cables 

supply, pulling, termination and testing 

from the FTR to consolidation cabinet 

(except shell and core offices, which are 

under the tenant scope).

P

6

Fibre optic cables supply, pulling, 

termination and testing from the MTR 

to FTR and drop fibre cables supply, 

pulling, termination and testing from 

the FTR to consolidation cabinet.

P

7

Supply and installation of mini optical 

distribution frame (ODF) splice cabinet 

at splice point location.

P

G.11.2  Responsibility matrix

Developers shall comply with the design and supply requirements of the responsibility matrix in Table G.34.

No. Item description

Masterplan 

Developer  

(site wide)

Building Owner 

(individual 

buildings)

Service 

providers  

(SP)

8

Splicing and labelling multicore fibre 

cables with 4-core drop cables using 

wall-mounted mini ODF.

P

9

Horizontal cabling inside the unit/ 

apartment/office/retail (except shell 

and core offices, which are under the 

tenant scope).

P

10

FTTx components such as the fibre 

cables, 42U 800 mm × 800 mm free 

standing racks, ODF, high density fibre 

patch panel, low-density fibre patch 

panel, patch-free splitters, mini ODF for 

splice point, mini ODF for shell and core, 

4-port fibre terminal box (with 

 

LC/APC and SC/APC pigtails and 

adaptors), GPON splitters, open rack for 

splitters and fibre patch cords.

P

11

Fibre optic splitter supply and 

installation (from the approved lists 

of suppliers/vendors of both du and 

Etisalat).

P

12

Supply of fibre patch cords and pre-

patching the fibre patch cords between 

splitter downlink ports to building fibre 

patch panels (ISP) and between splitter 

uplink ports to OSP fibre patch panels.

P

Table G.34  Responsibility matrix

Dubai Building Code

Part G: Incoming utilities

G 112

No. Item description

Masterplan 

Developer  

(site wide)

Building Owner 

(individual 

buildings)

Service 

providers  

(SP)

13

Supply of pigtail cords and splicing of 

patch-free splitter downlink cores with 

the pigtail cords and terminating pigtail 

cords in the fibre patch panels (ISP), 

splicing the patch-free splitter uplink 

cores with feeder cable (for Etisalat).

P

14

Consolidation cabinet supply and 

installation (including accessories and 

related elements).

P

15

Supply and installation of vertical and 

horizontal cable trays, cable pathways, 

ducts and microducts.

P

16

Telecom rooms/spaces and related 

electrical, mechanical and civil 

requirements.

P

17

Plot of 10 m × 10 m for each MMR.

P

18

Construction of MMR.

P

19

Commissioning of MMR.

P

20

Fibre optic cables supply, pulling, 

termination and testing from the MTR 

to each MSR and the rooftop room.

P

21

Supply and installation of fibre optic 

components for IBS connectivity (GSM)

P

22

SP identification labels (GAID and EID), 

supply and placement in the building 

unit.

P

Table G.34  Responsibility matrix (continued)

 

 

 

 

 

 

 

Content      ..     16      17      18      19     ..