STANDARDISED INFORMATION FOR EMPOWERED SUB-COMMITTEE (ESC) OF CIL BOARD FOR CHURI-BENTI UG PROJECT, CCL (0.81MTY)

 

  Index      Manuals 

 

Search            copyright infringement  

    

 

   

 

   

 

 

 

 

 

STANDARDISED INFORMATION FOR EMPOWERED SUB-COMMITTEE (ESC) OF CIL BOARD FOR CHURI-BENTI UG PROJECT, CCL (0.81MTY)

 

 

PROJECT REPORT ON
PRODUCTION AUGMENTATION BY
CONTINUOUS MINER
AT
CHURI-BENTI UG PROJECT, CCL (0.81MTY)
May 2007
Regional Institute - III
Central Mine Planning & Design Institute Ltd.
(A Subsidiary of Coal India Ltd)
Gondwana Place, Kanke Road, Ranchi - 834 008
STANDARDISED INFORMATION
FOR
EMPOWERED SUB-COMMITTEE (ESC)
OF
CIL BOARD
FOR
CHURI-BENTI UG PROJECT, CCL (0.81MTY)
May 2007
Central Coalfields Limited
(A Subsidiary of Coal India Ltd)
Darbhanga House, Ranchi - 834 001
CHAPTER - I
INTRODUCTION
1.1
BACKGROUND OF THE PROJECT REPORT
Churi UG is an existing project under the administrative control of North
Karanpura Area of Central Coalfields Limited. The mine has been taken over at the
time of nationalization. Prior to nationalization, it belonged to M/s United Karanpura
Collieries Ltd. Before nationalization, Lower Bachra seam has been worked in distant
past through Incline No. 2, 3, 4 & 5 in patches, which are presently abandoned. The
existence of water, fire etc cannot be ruled out in these abandoned workings. At the
time of nationalization, Churi old mine was under operation. The first Feasibility
Report for the project was undertaken in 1979 to work Upper and Lower Bachra
seams. After approval of the report, the mine development continued in Upper
Bachra & Lower Bachra seams.
Major area under Churi UG project has been developed and is standing on
pillars. Further investment is required in the mine for sustaining the existing
production as well as for production augmentation.
Mass Production Technology with Continuous Miner has been introduced in
few mines of the Coal India Limited. In view of encouraging results in SECL and
WCL, CCL management has also proposed for introduction of similar technology in
UG mines of CCL. Churi UG has been identified as a potential mine for introduction
of Continuous Miner Technology.
Churi-Benti UG project (developed mining area in Churi block & part of virgin
area in Benti block annexed to Churi UG mine) has been identified for introduction of
mass production technology. It is proposed to augment the coal production as well
as liquidate standing pillars at Churi UG. This report has been prepared to assess
the technological and financial implications of the introduction of Continuous Miner
Technology (based on equipment specifications as implemented in other CIL mines)
and to form a guideline for the process of the technological transfer. Recently,
agreement for supply of Continuous Miner package has been signed between ECL
and M/s JOY MINING for Jhanjra Project. The cost and specification of Continuous
Miner package considered for this report is same as that of Jhanjra Project.
1.2
PREVIOUS REVIEW OF THE PROJECT
The Project Report for Churi UG Project (Re-organization) was approved in
Feb’1982 by Government of India for a rated capacity of 0.84MTY with a capital
investment of 16.77 crores. The Churi project could not be completed and the
production remained far below the targeted production of 0.84 MTY. Recently, the
Derating-cum completion (foreclosure) report was prepared and has been approved
by the CCL Board in the 333rd meeting on 9.9.2006 for a capacity of 0.16MTY. It has
been forwarded to GOI for competent sanction of foreclosure. The RCE of Churi
project has also been approved by CCL Board in Dec’06 and forwarded to GOI for its
consideration.
Job No: 3507127
I/1
Mean while, for improvement in production from the existing project, various
reviews of the project have been taken up (prior to de-rating cum completion report)
and the reports have been submitted. A chronology of various reports is as under:
RPR (0.60MTY)
:
Jan’91 (Approved by CCL
Board in July’93 but not
approved by CIL Board due to
low IRR
RPR (0.33MTY)
:
Dec’98
Augmentation Report (0.45 MTY) :
Dec’2005
RPR (0.84 MTY)
:
March’2006
De-rating Cum Completion Report: July ‘2006
(Approved By CCL Board
In 333rd meeting in sept’06
And sent to govt of India
For its approval
And RCE of Churi UG project:
Approved by CCL Board in
Dec’2006 and sent to GOI for
approval
1.2
EXPLORATION STATUS
The area within the proposed mine boundary is about 7.69 sq. km. The
present mining area of the project falls under Churi & Benti (part) blocks, about 5.89
sq. km in Churi block & 1.8sq. km in Benti block. Detailed exploration has been
carried out in both the blocks. Total number of boreholes within the proposed
boundary is about 79BHs. The boreholes density works out to 10.26BHs/sq. km.
However, additional boreholes have been proposed for purpose of detailed analysis
of seams/bands and confirmation of seam/band thickness, wherever gap in
geological input exists.
CHURI BLOCK
A total of 56 boreholes have been drilled within mine boundary, including 3
non-coring boreholes. The borehole density works out to 9.50boreholes per square
km. The detailed exploration of Churi blocks revealed two major workable seams, i.e.
Upper Bachra seam (UBS) & Lower Bachra seam (LBS). Upper Bachra seam (UBS)
is not well developed in the north-western part of the block along Damodar river. In
the block, Lower Bachra seam has been interpreted as single geological
seam/horizon. However, the seam structure indicates multiple dirt bands, especially
in LBS. The average grade as per geological report is grade’ C’ but the grade
realization for the project is grade ‘B’ (LF).
Job No: 3507127
I/2
BENTI BLOCK
The total area within mine boundary in Benti block is about 1.80 sq. km. A
total of 23 boreholes exist within the area. The borehole density works out to
12.7boreholes per square km. In Benti Block only Lower Bachra seam is workable.
The lower Bachra seam has splitted in two parts namely BLB (Bottom Lower Bachra)
and Top Lower Bachra. The parting between BLB & TLB varies from 0.30-5.10m in
the block area within mine boundary. Top lower Bachra is again splitted into two
parts namely Upper Section of Top Lower Bachra and Lower section of Top lower
Bachra. Out of these three section, only two section BLB (Bottom Lower Bachra) &
Upper Section of Top Lower Bachra (UTLB) is workable.
TLB has been interpreted as combined Top Lower Bachra (CTLB) in part of
the mining area while in some part has been interpreted as split seam-section, i.e
Upper section of Top Lower Bachra (UTLB) and Lower section of Top Lower Bachra
(LTLB). The parting between UTLB & LTLB varies from 0.30- 2.07m. However, major
part of the mining area is having parting of around 1.0m or less. CTLB occurs as
thick seam with grade of coal D-E. In split seam-section, UTLB has workable seam
thickness, with thinning of seam to unworkable thickness on eastern and northern
side and grade of coal D-F. The LTLB shows workability in patches with grade of
coal B-D. In major part of the mining area, the parting between BLB and UTLB/CTLB
is generally around 1.0m or less. The BLB generally has workable thickness with
grade of coal varying from A-E.
In Benti block, UBS has been developed partly along Damodar river (common
boundary between Churi & Benti blocks). However, the seam is generally
unworkable.
1.3
CHRONOLOGY OF MINING ACTIVITIES
The first Feasibility Report for the project was undertaken in 1979 to work
Upper and Lower Bachra seams in Churi Re-organization (CRO). Subsequently,
Inclines 6 & 7 were driven up to Lower Bachra seam. Since then, B&P development
continued in UBS & LBS. Later, LHDs were introduced in the Churi UG project for
B&P development. After exhaustion of development reserves in LBS, additional area
in adjoining Benti block (sector-A) was annexed to the Churi UG project to continue
with B&P development. Presently, one B&P district with LHDs (5Nos.) is in operation
in Bottom Lower Bachra (BLB) seam/section in mining area under Benti block and
one manual B&P district in Upper Bachra seam in CRO. In Benti block, only initial
trunk roadway development has been done. The coal production during 2005-06
from Churi UG project has been 0.16Mt. Out of this, 0.10 Mt from LHDs panel and
0.06 Mt from manual B&P panel.
1.4
NECESSITY OF RECASTING PROJECT REPORT
Most of the property in Churi Block is developed and standing on pillars.
DGMS is also imposing restrictions on giving permission for further development.
Depillaring of these developed pillars is essential. Recent experiences in SECL and
WCL have shown that depillaring with Continuous Miner (CM) is suitable to achieve
higher production.
Job No: 3507127
I/3
CCL management has desired for introduction of Mass Production
Technology (MPT) to achieve higher rate of production from a mine / project. Churi
UG mine has been identified for deployment of Continuous Miner. The area, which is
free from overlying developed seams or unworkable overlying seams in Churi block,
i.e western section of CRO (Churi Re-organization), few panels of eastern section of
CRO (E12 & E13) and virgin area in Benti block, having thickness >3.0m has been
considered for deployment of Continuous Miner (similar to introduced in Chirimiri &
Tandsi UG mines of SECL & WCL respectively). There is change in technology
proposed for the mine and significant investment is required for production
augmentation as well as sustaining the production. Hence, it is required to recast the
report.
Scope of the report: The purpose of the report is to augment the existing
production by deploying Continuous Miner which may enhance the production,
economics and profitability of the project. The scope of this report is limited mainly to
depillaring of western section of CRO, few panels of eastern section of CRO (E12 &
E13) and development & depillaring in Benti block by Continuous Miner.
1.5
JUSTIFICATION OF PRESENT REPORT
The present status of the mine suggests the following:
 The entire property in Churi block is almost developed and standing on pillars
while mining area in Benti block is almost virgin.
 The development reserve for CM in mining area under Benti block has limited
mine life.
 The development and depillaring reserves for CM in the proposed area is for
about 9 years.
 The liquidation of standing pillars is essential. Depillaring cannot be
undertaken, as surface land is not acquired.
 Additional investment on acquisition of land is required for sustaining
production.
 In the present scenario, the mine is incurring losses @ of about Rs. 266/T,
which is likely to increase further with increase in various cost elements.
 Further investment is required for enhancement of production and/or
introduction of new technology.
 It is desired for production augmentation by adopting new technology on risk-
gain sharing basis.
 Investment is required for man-riding system due to long and arduous
traveling distance.
 Improved ventilation is required for ventilating distant panels.
 Additional capital is required for mine development and P & M.
 Better productivity and performance of Continuous Miner suggests feasibility
of enhanced production by way of introduction of mechanization at working
places.
 Integrated planning for coal & material transport, ventilation and pumping.
Job No: 3507127
I/4
1.6
RISK / DIFFICULTIES & CONSTRAINTS IN MINING
The difficulties / constraints and risk associated are :
 The seams lie at relatively low depth of cover thereby likely poses difficulty in
caving and strata control.
 Presence of Damodar and Saphi rivers on surface - a potential source of
danger
 Surface subsidence likely to significantly damage surface land.
 Coal to be left in UG to protect state highway on surface.
 Relatively low parting between seams
 Developed galleries are roof bolted.
 Crossing of Damodar River.
 Shifting of surface features like road, power trestles, Villages, company/
private quarters etc.
 Other constraints as mentioned in the Chapter-IX
1.7
PROJECT OBJECTIVES & TARGET BENEFICIARIES
The objective of the present report is to augment the coal production from the
mine keeping in view overall demand of better quality coal and better / improved
performance of the mine and higher capacity utilization of the existing resources.
The coal produced from the mine would be included in the basket linkages.
1.8
SALIENT FEATURE OF PRESENT REPORT
The objective of the present report/project is two-fold:
 Production augmentation
 Introduction of modern technology in CCL mines on risk-gain sharing basis.
The present report envisages introduction of Continuous Miner in CCL mines. Churi -
Benti UG project has been identified for introduction of Mass Production Technology.
The basic criteria / requirement as identified are as follows:
(a)
Technology:
Transfer of technical know-how for mechanization of face workings with
introduction of Continuous Miner in underground mining systems to ensure an
average daily production of 1700 -2000TPD from one district / panel.
(b) Production Guarantee on risk-gain sharing basis
Production will be guaranteed for a period of 5 years. The guaranteed
production level will be decided mutually. The mutually agreed production will
be on risk-gain sharing basis, i.e. linked to the production level and cost of
equipment. The contract agreement should include transportation of face coal
up to surface bunker or as agreed mutually.
(c)
Supply of Equipment & Maintenance
As a step for introduction of the technology, the supplier would provide
comprehensive maintenance of the equipment and operational guarantee for
five years at mutually agreed rate of production.
(d) Transfer of Technical know-how
After completion of term of five years the supplier would hand over the
detailed drawings of the equipment and ensure easy availability of the spares.
Maintain office in India to ensure supply of spares.
Job No: 3507127
I/5
(e)
Site Investigation & Scientific Studies
For deployment of continuous miner
Method of development
Method of extraction
Feasibility of mining with CM in contiguous part and other area in Churi UG
(f)
Mine / District Layout
Development & Extraction layout for the mine over a period of 9-10 years and
the proposed panel to match new technology.
(g)
Equipment / Machinery
Detailed requirement of equipment for introduction of the technology.
(h) Infrastructure Requirement
Modifications needed in the existing infrastructure like, transport, ventilation,
electrical layout, workshop, stores, coal handling, etc.
(i)
Manpower
Daily requirement of manpower in the district with their job description.
(j)
Implementation Schedule
Implementation schedule with schedule of transfer of technological know-how,
training of personnel, etc.
Job No: 3507127
I/6
CHAPTER -II
MARKETABILITY & LINKAGE
2.1
Demand & Availability
The demand and availability of Central Coalfields Limited during Xth & XIth
plan period are as under:
Sl
Demand (MT)
End User
No.
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
1
Existing TPS
31.43
31.43
31.43
31.43
31.43
31.43
31.43
2
X Plan TPs
2.19
7.11
13.07
14.53
14.53
14.53
14.53
3
XI Plan TPS
0.00
0.00
1.45
4.47
12.81
19.48
22.49
Total Power Utility
33.62
38.54
45.95
50.43
58.77
65.44
66.45
4
Captive Power
2.77
2.77
2.77
1.35
1.35
1.35
1.35
5
Steel
5.50
6.00
6.1
6.20
6.30
6.40
6.50
6
Cement
0.18
0.18
0.18
0.18
0.18
0.18
0.18
7
Sponge Iron
0.92
0.92
0.92
0.92
0.92
0.92
0.92
8
Other sectors
6.84
6.78
6.73
6.68
5.63
6.58
6.53
Total Demand
49.83
55.19
62.65
55.76
74.15
80.87
83.93
Production
40.40
42.00
47.50
52.50
57.80
61.70
367.00
Gap
-9.43
-13.19
-15.15
-13.26
-16.35
-19.17
-16.93
Source: Consolidated coal availability report of CCL, March 2006
The above table reflects that even after achievement of projected additional
production from Churi UG project, there would be enormous gap in coal
availability in CCL. The Augmentation report will help to reduce this gap with
consistent supply of superior grade of coal.
2.2
Linkage
At present coal from Churi U/G project is mainly being sent to various sponge
iron plants. The additional production will be included in basket linkages.
Job No: 3507127
II/1
CHAPTER - III
PROJECT SITE INFORMATION
3.1
LOCATION
Churi-Benti U/G project is located in the South-central part of North Karanpura
coalfield between the latitudes 23o41'05" and 23o42'04" and the longitudes
85o03' and 85o04'20" covering an area of about 7.68 sq.kms. in Chatra district
of Jharkhand state. It is covered by topo sheet Nos. 73E/2 and 73A/14 (Scale
1"=1 mile) of Survey of India. Saphi River forms the south-eastern boundary
and arbitrary line beyond Fault F11A and along the fault plane of F11A of
Benti Block forms the western boundary of the project. Ray Bachra colliery
and Ashok OCP of Piparwar area is situated to the North / North-east and
Manki colliery (now exhausted) to the south/south- west of Churi project as
shown in the Location Plan (Plate-I). It has two units.
3.2
COMMUNICATION
Churi-Benti UG project is situated at a distance of 8 km on fair weather road
connecting Khalari and Ray railway stations on the Gomoh-Dehri-on-Sone
loop line of the East Central Railway. An all weathered 25 km long road links
Khalari with Bijupara village on the state highway connecting Ranchi and
Daltonganj.The P.W.D. road connecting Khalari and Barkagaon in Hazaribagh
district also passes through the Churi block. CCL Hq. at Ranchi is situated at
a distance of about 73km from Churi UG project.
3.3
TOPOGRAPHY, DRAINAGE AND HYDROLOGY
The topography of the area except in the western part is gently undulating and
sloping towards Saphi and Damodar rivers. The area as per borehole records
and colliery records lies between RL 404.50m and RL 476.80m above Mean
Sea Level. In the western part of the block, adjoining Manki mine, the terrain
is hilly, as few spurs of the Belangi Hill (RL 529.74m) traverse the block.
The average annual rainfall of the area is around 1500mm, most of the
precipitation of which is during the monsoon season with some winter rains.
Damodar and Saphi rivers control the drainage of the area. Water has been
found in some drilled boreholes but there has been no evidence of any water
under positive piezometric head in any of the boreholes drilled in the block.
However, seepage of water has been recorded in the workings of the Lower
Bachra seam through the floor of the seam in Incline No. 2A. A highly porous
and permeable coarse-grained sandstone and conglomerate layer forming the
floor of the Lower Bachra seam appears to be under water pressure and is
being recharged in the outcrop region by the Saphi River.
The High Flood Level of Saphi River as recorded close to the incline mouth by
the colliery authorities in 1976 and supplied to the Exploration Division is
420.95m above the M.S.L. Part of developed working of Churi UG in W7 ,
W8,and W9 panels falls below HFL. One seasonal nala is also passing over
Job No: 3507127
III/1
the panels of W8 , W9,and W10. While working below it safety care should be
taken.
Incline No.1 in the Lower Bachra seam was driven from the area falling under
high flood level of Saphi River. It has since been sealed and six numbers of
check dams between 2nd and 3rd levels have been constructed as protective
measures. Records of the H.F.L. on Damodar river (413.12-416.16m) have
been taken from the adjoining Hesalong block.
Job No: 3507127
III/2
CHAPTER - IV
GEOLOGY AND DEPOSIT APPRAISAL
4.1
Background
The summarized geological assessment has been prepared from the
following geological reports:
a)
Geological Report on Churi Block, 1977
b)
Supplementary Note on Geology of North-Western part of Churi
Colliery, May 1985.
c)
Geological Report for Benti Block, March 1992.
The approved Feasibility Report of 0.84 MTY was prepared on the basis
of Geological Report on Churi Block, 1977.
4.2
Exploration Status
a)
Churi Block: The exploration in Churi Block was initiated in 1975
and concluded in Jan, 1976. A total of 15 Boreholes (NNKC
1,2,3,6,11,15,
24-32) were drilled along with 5 boreholes (CBH
1,3,4,5 and CHPR) by colliery authorities. In 1983-85, additional 13
boreholes (NNKC 33-36, 40-48) were undertaken in virgin North-
Western part. The data of these 13 boreholes were utilized for
updating the stratum contours of Lower Bachra seam for the virgin
north-western patch of Churi Block. 3 more non-coring boreholes
(NNKC 37,38,39) were also drilled for dewatering and sinking
electrical cables.
In June 1990, 6 (six) boreholes were drilled for proving of structure
and determining the physico-mechanical properties. Subsequently,
CCL drilled 4 (four) boreholes in the eastern part to confirm
continuity of Lower Bachra seam. In 2001-02, 10 (ten) no of bore
holes were drilled by CMPDI for updating of seam plans.
Job No: 3507127
IV/1
Table 4.1: Details of Boreholes
Agency
Period/
Series
No.
of
Meterage
Year
Boreholes
(m)
Before
CBH/CHPR
5
-
Nationalisation
CMPDI
75-76
NNKC
15
1332
CMPDI
8385
NNKC
13
1236.60
CMPDI
83-85
NNKC
3(Non-
280.75
coring)
CMPDI
1990
NNKC
6
579.20
CCL
-
CCPS
4
365.15
CMPDI
2001-02
CMCPS
10
918.00
56
4711.70
The total area of the block is about 5.89 Km2 and the borehole
density is 9.5 boreholes/km2.
b)
Benti Block: A total of 101 boreholes were drilled over on area of
8.55 km2 in Benti Block. Out of the total boreholes, 93 boreholes
were coring and remaining 8 boreholes were partly coring/non-
coring. The borehole density works out to 11.81 bore hole per
square kilometer. The borehole density for the area proposed to be
mined in Benti block (Sector-A) through Churi is
12.7
boreholes/km2.
4.3
Geology and Structure of Project Area
4.3.1 The general geological sequence of the North Karanpura Coalfield is as
follows:
Job No: 3507127
IV/2
Table 4.2: Sequence of Geological Formation
Upper Gondwana
Mahadeva Formation
Triassic
Panchet Formation
Lower Gondwana
Raniganj
Formation
Permian
Barren
Measure
Formation
Damuda Sub-group
Barakar formation
Karharbari formation
Permo
Talcher formation
Carboniferous
----------------------------------- Unconformity----------------------------------
Gneisses and schists
Pre-cambrian
Of the above, only Karharbari and Barakar formations contain economical
coal seams.
4.3.2 Geological Succession of Churi Block
On the basis of available surface and sub-surface data, following
succession has been established for Churi Block.
Table 4.3: Geological succession in Churi Block
Formation
Broad Lithology
Thickness (m)
Recent
Soil and sub-soil
0.23 (CBH-3) to
12.20 (NNKC-3)
Barakar
Conglomerate,
30.03 (NNKC-27)
sandstone,
alternate
to 84.61 (NNKC-31)
bands of sand stone &
shale, grey shale, fire
clay etc.
Karharbari
Sandstone, fire clay,
20.22 (NNKC-15)
grey
shale,
to 47.42 (NNKC-27)
conglomerate
Upper Bachra seam
0.13 (NNKC-35)
Job No: 3507127
IV/3
to 4.84 CCPS-10)
Parting
of
0.49 (CCPS-10)
conglomerate,
to 20.27 (CCPS-4)
sandstone, alternating
bands of sandstone &
shale, sandy shale,
grey
shale
&
carbonaceous shale
Lower Bachra seam
1.71 (NNKC-32)
to 11.24 (NNKC-48)
Sandstone & shale
Not drilled
Talcher
Khakhi
green
sandstone, shale &
boulder bed
The Karharbari formation contains two major coal horizons i.e. Upper
Bachra seam and Lower Bachra seam.
4.3.3 Geological Structure
Churi Block: The area presently under consideration in Churi Block lies
between faults F17 & F10. Fault F17 exists in the north-eastern part of the
block where as fault F10 exists in the southern and south-western part of
the block . The throw of fault F17 is about 50m towards north-west in the
northern part which gradually decreases to around 5m near borehole No.
CHPR-57 located on the left bank of Saphi river. The throw of fault F10
varies from 15-25m and the throw is towards north-east. The area
between these two faults is characterized by simple geological structure.
There are three more faults (F11A, F12, F13) in addition to above two
faults which trend almost NW-SE with north-easterly throw of 5 to 13m.
There are four minor slips also F11B, F11, F15 and F18) whose throw
varies from 2 to 5m (Ref. Stratum contour plans).
Of the above faults, F11, F11A, F11B, F12 and F15 have been
encountered in the mine workings while F18 was responsible for omission
of Upper Bachra Seam in NNKC-24. Fault F15 encountered in the mine
Job No: 3507127
IV/4
workings was also responsible for omission of Upper Bachra seam in
NNKC-19.
Table 4.4: Details of Faults in Churi Block
Sl.
Fault
Trend
Direction
Amount of throw
Remarks/Evidence
No.
No.
of throw
(m)
1
F10
NW-SE
NE
7-15m throw
Omission of Lower Bachra seam in
diminishing in SE
CBM-6; also encountered in workings of
direction
south central part.
2
F11
NW-SE
SW
0-10m dies out in
Encountered in the workings of Lower &
the west
Upper Bachra seam in the south Central
part and seen in the Saphi river.
3
F11a
NW-SE
N-E
5m
Based on stratum contours.
4
F11b
E-W
South
2m
Based on stratum contours
5
F12
NW-SE
NE
5m
Encountered in UG workings.
6
F12A
NE-SW
SE
0 to 3m, dies out in
Omission of Upper Bachra seam in
the north
CCPS-3.
7
F13
NW-SE
NE
8 to 10m
Based on aerial photographs & stratum
contours.
8
F15
East-
South
3m
Upper Bachra seam omitted in borehole
West
NNKC-19. Minor slips in the workings of
Churi Colliery.
9
F17
NW-SE
NE
5-50m Reduces
Based on aerial photographs and floor
eastward
contours
10
F18
E-W
S
0-4m
Omission of Upper Bachra Seam in
NNKC-28.
The strike within the block is roughly NE-SW in the major part of the area
which gradually swings to almost north-south in the eastern part. The
strike between fault F13 and F17 in the north-eastern part has further taken
swing to almost NNW-SSE. The local swings in strike is mainly due to
rolls. The dip of the strata generally varies between 20 & 30 (1 in 20 to 1 in
40) in the major part of the property. However, in the southern part of the
area, gradient gradually increases locally as could be seen from the
stratum contour plans.
Job No: 3507127
IV/5
The seam belong to Karharbari formation, which is known to contain
seams with erratic behaviors, therefore, the confidence level of geological
interpretation is comparatively low.
Benti Block: In the Benti Block, only Karharbari formation is coal bearing
having Bachra seam normally in 2 to 4 splits. The Benti block is a part of
the northern limb of Karkatta- Piparwar plunging anticline. The strike in the
northern and south central part is roughly N-S with westerly dip, which
swings to NW-SE in the northeastern corner of the block. The N-S strike of
the northern part swings to almost NE-SW strike before becoming E-W in
the north-western part of the block. The strike again swings to more or
less NE-SW strike in the western part. In sector-‘A’, the strike varies from
N-S to NW-SE and dip ranges from 1 degree to 3 degree (1 in 60 to 1 in
20) due SW to west. In Benti Block, 18 faults have been established.
Table 4.5: Sequence of coal seams & partings in Benti Block
Formation
Seam/Parting
Sector ‘A’ of Benti Block
Thickness range (m)
Minimum
Maximum
Karharbari
Strata between
47.50
62.35
Barakar & Upper
Bachra/Top
Lower Bachra
Upper
Bachra
0.53
0.96
seam
Parting
0.50
1.61
Lower section of
0.40
2.0
Top
Lower
Bachra
Combined Top
3.0
5.10
Lower Bachra
Parting
0.3
3.0
Job No: 3507127
IV/6
Bottom
Lower
2.12
4.25
Bachra
4.4
Coal Seams
In the Churi Block, two seams namely Upper Bachra and Lower Bachra
have been encountered.
4.4.1
Upper Bachra Seam
It varies in thickness from 0.13 m (NNKC-35) to 4.84 m (CCPS-10) and is
mostly devoid of any dirt bands. Generally, it is 2 to 3 m in thickness in
major part of area. The seam thickness decreases to less than 1.2m in the
south-western part (NNKC- 26,28, 33, 35, 40, 48) and in the northern part
of the property (NNKC-
43,
44,
49). The immediate roof of UBS is
generally grey shale, sandy shale, conglomerate, medium to coarse
grained sands ton, carbonaceous shale etc. The immediate flor is
predominantly carbonaceous shale and grey shale.
4.4.2
Lower Bachra Seam
It is the bottom most seam having thickness from 1.71m to 11.24m
(NNKC-48) and occurs 0.68m to 20.27m (CCPS-4) below Upper Bachra
seam. The Iso-parting indicates that the parting gradually increases from
3m in the middle of the property to about 18m in the south-eastern region.
In the north-western part, parting varies from 1 to 3m. The thickness
normally varies from 3-5m, which gradually increases to 9m in the western
part near Damodar river.
It has been observed from the seam structure plans that there is generally
a persistent dirt band of carbonaceous shale/grey shale occurring about 2
to 2.5m below the roof. The bottom section of the seam is generally clean
and better in quality than the upper section which is commonly inter
banded and often contains thick shaly coal horizons.
The immediate roof of LBS is carbonaceous shale, grey shale, fine to
medium grained sandstone. Floor is generally grey shale, intercalation of
shale and sandstone, carbonaceous shale, sandy shale and at times by
Job No: 3507127
IV/7
medium to coarse grained sandstone. The summarized range of Analytical
parameters for LBS & UBS is given in Table: 4.6.
Table 4.6: Analytical Parameters for LBS & UBS
Seam
Particula
On 60% RH & 400C
UHV
Grade
Of
M%
Ash%
VM%
(Kcal/kg)
Analysis
Upper
Ex-band
6.4-8.5
17.8-27.6
25.6-27.7
4210-
C-D
Bachra
5420
In-band
5.4-8.0
17.8-30.3
23.2-27.7
3685-
C-E
5420
Lower
Ex-band
7.6-9.4
10.9-25.5
24.1-26.5
4330-
A-D
Bachra
6225
In-band
6.3-9.0
15.9-31.0
21.5-27.3
3640-
B-E
5865
Clean
Clean
7.6-9.2
9.0-14.2
23.9-25.3
5755-
A-B
bottom
coal
6610
section
4.4.3 In the Benti Block: Upper and Lower Bachra seams occur.
Upper Bachra Seam:
It occurs in a small patch in sector-A along the eastern block boundary.
This has completely pinched out near the boundary of Benti and Churi
mine. This seam has not been considered in this Report due to low
thickness (<1m). The grade of coal varies from ‘D’ to ‘F’.
Lower Bachra Seam:
The Lower Bachra seam in Benti Block splits into two parts.
a)
Top Lower Bachra seam(TLB), and
b)
Bottom Lower Bachra seam(BLB)
The Top Lower Bachra seam (2 to 5m thick) has again splitted into two
distinct sections designated as:
i)
Upper Section of Top Lower Bachra (UTLB)
ii)
Lower section of Top Lower Bachra ( LTLB)
Job No: 3507127
IV/8
However, both the above upper and lower sections have merged together
in small isolated patches in Sector ‘A’ and designated as combined Top
Lower Bachra( CTLB).
The Bottom Lower Bachra seam has thickness range of 0.24 to 4.18m and
is persistent throughout the property.
4.4.4
Upper section of Top Lower Bachra seam
It is persistent throughout the property as well as in sector-A, except near
the western block boundary where it has pinched out completely.
Thickness : It varies generally from 1.5 - 3.5m.
Dirt Bands: It is normally less than
0.30m in thickness and are
carbonaceous shale in nature.
Roof & floor:The immediate roof is represented by medium to coarse
grained sandstone, carbonaceous shale, grey shale and
conglomerates. The floor is marked by carbonaceous shale,
sandy shale, grey shale, medium shale to coarse grained
sandstone and alternate bands of shale and sandstone.
Quality:
The UHV and grade (In Band) varies from 3105 K.cal/kg (‘F’)
in NNKA-394 to 4955 K.cal/kg (‘C’) in NNKA-65. The overall
grade of coal is ‘D’.
4.4.5
Lower Section of Top Lower Bachra seam
This section is overlain by Upper section of Top Lower Bachra seam after
a parting of 0.50m to 11.33m and pinches out completely in the western
part of the block.
Thickness: It is genrally 1.2 to 2m in the proposed area.
Dirt Bands: The seam is mostly free from dirt bands. It has been found in
only 3 bore holes and is generally less than 0.38m in
thickness.
Roof & Floor:
The immediate roof is represented by carbonaceous
shale, sandy shale, medium to coarse grained sandstone
and alternate bands of shale and sandstone. The floor is
Job No: 3507127
IV/9
normally sandy shale, alternate bands of shale and
sandstone, medium grained sandstone and gray wackes.
Quality:
The UHV and grade (In band) ranges from 4070 K.cal/kg
(‘E’) in NNKA-394 and 5725 K.cal/kg (‘B’) in NNKA-65. The
overall grade is ‘D’.
4.4.6
Combined Top Lower Bachra Seam
The Upper and Lower sections of Top Lower Bachra seam have merged
together in three narrow isolated patches in the sector.
Thickness: The thickness of the combined Top Lower Bachra seam
varies from 1.10m (NNKA-372) to 5.10m (KP-1). The combined seam is
geerally around 4.0m in thickness in the north-eastern patch in Sector-A.
Dirt Bands: The thickness of the dirt bands is less than 0.19m. The dirt
bands have been found in 4 boreholes out of the 15 boreholes.
Roof & Floor:
Immediate roof is generally represented by
carbonaceous shale and coarse to very coarse-grained sandstone. The
floor is marked by the sandy shale, carbonaceous shale and greywacke.
Quality:
The UHV/grade varies from 3285 K.cal/kg (‘F’) in NNKA-375
to 4275 K.cal/kg (‘D’) in NNKA-66. The overall grade is ‘D’ in the Sector’A’.
4.4.7
Bottom Lower Bachra seam
It is the Lower most split of the main Bachra seam.
Thickness: The thickness of Bottom Lower Bachra seam varies from 2
to 4m.
Dirt Bands: The dirt bands are generally carbonaceous shale and grey in
nature. Its thickness is less than 0.30m except in one boreholes.
Roof & Floor:
The immediate roof is coarse to very coarse grianed
sandstone, carbonaceous shale, grey shale and sandy shale. Floor is
represented mostly by sandy shale, alternate bands of shale and
sandstone and carbonaceous shale followed by shale, grey wackes and
coarse to very coarse grained sandstone.
Quality:
The overall grade is ‘B’.
4.5
Geological Reserve
Job No: 3507127
IV/10
Churi Block:The estimated net-in-situ geological reserves in Upper &
Lower Bachra seams is about 36.29 MT.
Benti Block (Sector-‘A’):
The estimated net-in-situ geological reserves in Upper section of
Top Lower Bachra seam and Bottom Lower Bachra seam are 4.171 MT
and 8.697 MT respectively.
The detailed break-up of extractable reserve in Churi-Benti blocks is as
under:
Seam / Section
Churi block
Benti block
Total
Dev.
Dep.
Dev.
Dep.
A. Continuous Miner
Lower Bachra seam (LBS)
0.224
2.979
---
---
3.203
Bottom Lower seam (BLB)
---
---
0.464
0.547
1.011
Sub-Total
0.224
2.979
0.464
0.547
4.214
B. Heightening District
Lower Bachra seam (LBS)
0.915
---
---
0.915
Sub-Total
0.915
---
---
0.915
C. Bord & Pillar
Upper Bachra seam (UBS)
0.755
2.928
---
---
3.683
Lower Bachra seam (LBS)
0.242
5.037
---
---
5.279
Bottom Lower Bachra (BLB)
---
---
0.521
0.748
1.269
Upper section of Top Lower
---
---
0.418
0.430
0.848
Bachra (UTLB)
Sub-Total
0.997
7.965
0.939
1.178
11.079
Job No: 3507127
IV/11
CHAPTER - V
PRESENT STATUS OF MINE
5.1
GENERAL
Churi U/G Project is a nationalized project in the North Karanpura Area of
Central Coalfields Limited. At the time of nationalization, Churi old mine was
under operation. Manual development was in progress in LBS & UBS. After
nationalization, a feasibility report for Churi Underground (Re-organization)
was prepared and approved in Feb’82 for a rated capacity of 0.84 MTY with
capital investment of 16.77 Crores. The feasibility report was a combination of
the two mines (Existing and Proposed) with certain common arrangement for
transport, Ventilation and Pumping.
5.2
PRESENT DEVELOPMENT OF THE PROPERTY
The entire property of Churi Block has been developed in stages:
(a)
Churi old (Manual section):
This development is prior to
nationalization of the mine. Both Upper Bachra Seam (UBS) and Lower
Bachra Seam (LBS) have been approached through Incline Nos. 3A, 4A and
1A, 2A respectively and fully developed by Bord & Pillar method of mining
with manual loading. Almost entire property in Churi old mine is standing on
pillars and is available for depillaring. Presently return airway of CRO is
through this Churi old section.
(b)
Churi Underground (Re-organization): The remaining area of Churi
Block is approached through Incline No 6 & Incline no-7as envisaged in the
approved feasibility report (0.84 MTY). The proposed method of mining for
Upper Bachra seam were re-treating Long wall caving with solid blasting &
Manual loading onto AFC and friction prop as support for Thickness 1.2 - 2.0
m and Manual Bord and Pillar for Thickness 2.0m to 4.0m. Whereas for Lower
Bachra seam, the proposed methods were Blasting gallery method with
Jumbo drill and remote controlled LHD for Thickness 4.5m-6.0m & Manual
Bord & Pillar for Thickness 3m-4.5m.
Presently, almost entire area of Lower Bachra is developed by conventional
Bord and Pillar method with LHD and Upper Bachra seam is developed
manually. The development reserve of CRO is near to exhaustion. Almost
Job No.:3507127
V/1
entire property is developed and standing on pillar and is available for
depillaring.
Benti Section: Part of the Benti Block (Sector-A) is annexed to the Churi
Block. This annexed part has been approached by driving 3 nos. of drivages
headings from W-6 panel in the western section of CRO. Presently, Bottom
section of Lower Bachra seam is being developed by Bord & Pillar method
with LHDs (5 nos.). The annexed part to Churi project is beyond the scope of
the approved feasibility report.
Before nationalization, few patches of the Churi Block are also worked
in lower Bachra seam through incline no. 2,3,4 & 5, which is presently
abandoned. The existence of water, fire etc cannot be ruled out in these
abandoned workings.
5.1
PRESENT INFRASTRUCTURE
Churi underground project is an ongoing project. Most of the infrastructure
likes approach road, service buildings and residential buildings for the mine is
already exists. The Churi-Benti Project shall utilize the existing infrastructure.
Various mine development activities like incline drivages (6 & 7 Nos.); Airshaft
and surface coal handling arrangement (5 x 125 Te) have already been
completed.
5.1.1
Existing Underground Coal Transport
The existing UG coal evacuation system in Churi UG project is through a
series of 1000 / 800 mm belt conveyors, which includes trunk conveyors (TB1
to TB4) covering entire length of trunk roadways in Incl. No.7and gate belt
conveyors. Coal from the working face is loaded either manually or by LHDs
on to chain conveyors and Chain conveyors fed it to gate belt conveyors. The
gate belt conveyors feed coal on to trunk belt conveyors, which in turn carries
coal up to surface bunkers. This existing transport system is also for workings
in Benti section.
5.1.2
Existing Men & Material Transport
A direct haulage of 65 KW rating is installed on surface for transport of
material from surface along the Incline no.6 to underground. Thereafter,
endless rope haulages are used to haul the material trollies to the out bye of
the existing panels. Within the panel, endless haulage is also used to supply
material to in bye faces of the panels .
Job No.:3507127
V/2
5.1.3
Surface Coal Transport
Coal evacuated from UG is stored on surface in 5 overhead steel hoppers of
125 Te capacities, which directly loads either on to consumer’s truck or side
dumps on to surface, in case emergency arises.
5.2
PRESENT STATUS & METHOD OF MINING
LBS: Bord and Pillar with LHD (Development almost completed)
UBS: Manual Bord and Pillar (Development is in Progress)
BLB: Bord and Pillar with LHD (Development is in Progress)
Major part of the area is standing on pillars and manual development is being
carried out in upper Bachra seam in the eastern side of the Churi Re-
organization (CRO) and development with LHD is in progress in Bottom
Lower Bachra seam/ Section in Benti Block. .
5.3
EXISTING VENTILATION ARRANGEMENT
At present, exhaust system of ventilation is being followed for ventilating the
workings of mine. Presently, Churi UG mine is an operating mine with two
incline entries (Inc. 6 & 7) on the rise side working as main intake airways and
an air shaft serves as main return airway with a main mechanical ventilator
(PV200 make) installed in the air shaft. The present air discharge through the
main fan is about 50.0m3/s at an operating fan pressure of about 58mm of
WG.
Two standby fans exist, one a Model AF-80 fan in the fan drift parallel to the
existing fan drift and other a Model PV-160 fan in 1A incline. Only the main
fan PV200 make is in operation.
5.4
EXISTING POWER SUPPLY ARRANGEMENT
The existing Churi Reorganization sub-station (2x1MVA, 11/3.3KV) receives
power at 11 KV from old KDH 33/11 KV substation via Dakra sub-station. Out
of these two 1 MVA transformers, one transformer caters the loads of surface
and some underground loads. The other transformer feeds power to different
underground equipment through 3.3 KV overhead lines. which is being tapped
by cables passing through boreholes to underground substation & different
load points.
Job No.:3507127
V/3
5.5
SERVICE & RESIDENTIAL BUILDINGS
The major service buildings like Pit office, cap lamp room, sub-station,
workshop, store, service magazine, Haulage room etc. already exist at Churi
UG Project. However, the existing sub-station, workshop, store need further
strengthening and additional construction of water reservoir, shed etc. on
surface.
The break-up of existing residential buildings at Churi is as under:
Type of Quarters
Existing no of Quarters
MQ(LCH)
910
A
90
B
48
C
7
D
3
Barrack
52
Total
1110
5.6
WATER SUPPLY
The present water supply is from Damodar River, which is fed directly for
consumption. Saphi River is another source of water for water supply to the
colony after treatment. Present system of water supply and sewerage is
sufficient to fulfill the potable and industrial water demand.
5.7
EXISTING MANPOWER
The existing manpower deployed at Churi UG is 905 ( as on 1.1.07). The
details of the existing manpower are as under:
Sl.
Particulars
Existing Manpower
No.
1
Piece Rated Workers
177
2
Daily Rated Workers
576
3
Monthly Paid Staff
130
4
Executives
22
TOTAL
905
5.8
LAND ACQUISITION STATUS
Job No.:3507127
V/4
Non-forest land (24 Ha) has been acquired for colony construction. Major part
of the mining area is under forestland, which is yet to be acquired. Total land
for mining is yet to be acquired.
5.9
PAST PERFORMANCE
(a) Production
Year
86-
87-
88-
89-
90-
91-
92-
93-
94-
95-
87
88
89
90
91
92
93
94
95
96
Prod (MT)
0.156
0.150
0.205
0.228
0.214
0.230
0.240
0.246
0.204
0.226
Year
96-
97-
98-
99-
00-
01-
02-
03-
04-
05-
97
98
99
00
01
02
03
04
05
06
Prod (MT)
0.236
0.229
0.244
0.233
0.210
0.172
0.175
0.185
0.168
0.161
(b)
Other Existing Parameters of the project
 Selling price/Te
:
Rs. 1441.00
 Cost price/Te
:
Rs. 1707.00
 Profit/loss
:
(-) Rs.266.00
 Manpower (as on 31.3.06) :
945
 O.M.S
:
0.66
 Production
:
0.162 MT
Job No.:3507127
V/5
CHAPTER - VI
SALIENT FEATURES OF APPROVED PR
6.1
GENERAL
The Feasibility Report of Churi UG for a rated capacity of 0.84 MTY was
approved by Govt. of India in Feb 1982 for a capital investment of Rs. 16.77
Crs.
The method of work proposed and production envisaged is as follows:
(a)
Upper Bachra seam
 Retreating Long wall caving with solid blasting & Manual loading
onto AFC and friction prop as support for Thickness 1.2 - 2.0 m
 Manual Bord and Pillar (Thickness 2.0m to 4.0m)
(b)
Lower Bachra Seam
 Blasting gallery method with Jumbo drill and LHD (Thickness 4.5m-
6.0m)
 Manual Bord & Pillar (Thickness 3m-4.5m)
( c ) Production Envisaged
* Upper Bachra
:
0.135 MTY (Long wall Panel )
0.150 MTY (B & P Panel)
Sub-total
:
0.285 MTY
* Lower Bachra
:
0.42 MTY (2- Blasting gallery panels)
0.15 MTY ( B & P panel )
Sub-total
:
0.57 MTY
Total
:
0.855 MTY ( Approved for 0.84 MTY)
6.2
SUMMARISED DATA
Sl.No.
Technical/Financial
As per Approved Feasibility
Parameters
Report (0.84 MTY)
1
Name of the Report
Feasibility Report for Churi
Underground
Project
(Re-
organization)
2
Target Capacity (MTY)
0.84
3
Seams considered
Upper Bachra seam (UBS)
Job No.:3507127
V/6
Lower Bachra Seam (LBS)
4
Thickness of Seam
UBS:
0.13 - 4.42 m
LBS:
1.71 - 11.24 m
5
Seam gradient
1 in 20 ( 2 Deg. to 3 Deg.)
6
Av. grade
‘C’
7
Extractable Reserve (MT)
21
8
Manpower
1858
9
O.M.S. (Te)
1.651
10
Life (Yrs.)
28
11
Target Years
1983-84
13
SPT (Rs./Te)
Rs. 63.26
14
CPT (Rs./Te)
At 100% target production
Rs.59.92
At 85% target production
Rs. 68.81
15
Profit/Loss (Rs./Te)
At 100% target production
Rs. 3.34
At 85% target production
(-) Rs. 5.55
16
Internal Rate of Return (%)
At 100% of target production
7.2 %
At 85% of target production
1.4 %
6.3
SALIENT FEATURES OF DE-RATING-CUM-COMPLETION REPORT
The Derating- cum- completion Report of Churi UG was approved in the 333rd
Board meeting of CCL on 9.9.2006 at a production level of 0.16 MT. The
Board also directed that a Revised Cost Estimate (RCE) reflecting the
notional approved capital cost vis-à-vis actual expenditure incurred against
the approved items be informed to the Board and the Govt. The RCE for Churi
UG was prepared in Jov.’06 and approved by CCL Board in Dec.’06 and sent
to Govt. of India for its approval. The existing capital expenditure approved by
CCL Board as on 31.3.06 for Churi UG project is Rs. 21.39 Crs.
Job No.:3507127
V/7
Head-wise Capital Investment Approved by CCL Board for De-rating
Sl.
Particulars
As per
Capital
Variance
No.
Feasibility
Investment
Report
(As on
(Feb.’82)
31.3.06)
1
Land
42.00
79.09
(-) 37.09
2
Buildings
144.59
248.16
(-) 103.57
3
Plant & Machinery
1019.94
1508.63
(-) 488.69
4
Furniture& Fittings
4.44
14.41
(-) 9.97
5
Railway siding
233.66
24.09
209.57
6
Vehicles
11.67
19.91
(-) 8.24
7
Prospecting&
4.10
60.60
(-) 56.50
Boring
8
Mine Development
8a
Capital outlay in
Mines
8b
Road & Culverts
8c
Water Supply
8d
SR & FR cost
8e
Revenue
expenditure
capitalized
Sub-Total
216.28
184.41
31.87
Total
1676.68
2139.30
(-) 462.62
Approval of RCE for Churi Under ground project from Govt of India is still
waiting.
Job No.:3507127
V/8
CHAPTER-VII
MINE BOUNDARY, RESERVES & MINE LIFE
7.1
SELECTION OF MINING AREA
Existing mine boundaries : The existing mine boundaries of Churi UG mine
covers area lying in Churi mine block and part of Benti block The present boundary
of the Churi UG is as under :
North/North-East :
Adjusted boundary between Ashok OCP (Piparwar
Area) & Churi UG in Benti block and Common
boundary with Ray Bachra UG along fault F17-F17
West
:
Arbitrary line beyond Fault F11A along the fault F11A
plane and Damodar river
South -East
:
Saphi river
South/South-West
:
Common Boundary Between Churi and Manki Colliery
Subsequently, alteration / addition has been done in the approved boundary
(on the northern side) within Churi block as boundary fault (F-13) was not
encountered. However, Ray Bachra UG had encountered a fault (F-17). Hence,
natural extension of the mine boundary of Churi UG was made by adjustment of
common boundary between Churi & Ray Bachra UG mines. Later, after exhaustion
of development reserves in Lower Bachra seam & non-availability of surface land for
depillaring, part of the virgin property lying in Benti block across Damodar river up to
fault F-11A (Sector-A) was also annexed into Churi UG.
While evaluating and finalizing the boundaries of proposed Churi-Benti UG
project, the mining area of existing Churi UG lying within Churi & Benti geological
blocks have been considered
The total area within mine boundary of Churi-Benti UG project is 7.68 Sq.kms
Out of the above Churi block has 5.89 sq. km. of area. Only 2.03 sq km has been
considered for this reporting in Churi Block.. Out of the 1.79 Sq.Kms of the area in
Benti Block ,0.41 sq.kms is considered for CM deployment in Benti block.. The total
area for the Churi -Benti Block for CM deployment is 2.44 sq.kms.
Criteria for selection of mining area for CM: It is now proposed for deployment of
Continuous Miner in the mine on similar specifications, as done in some other UG
mines of CIL. Accordingly, mining area having seam thickness more than 3.0m has
been identified for application of Continuous Miner. Similarly, extractable reserve has
been estimated for workable seam/section thickness up to 4.6m.
The present report has been prepared for augmentation of production by
deploying Continuous Miner (CM) in the Churi - Benti UG project. The area selected
for deployment of CM is the western section of CRO, where Upper Bachra Seam
(UBS) is not workable , few panels in Eastern section of CRO (E12 & E13) and part
of sector-A of the Benti Block having thickness greater than 3.0m. So the extent of
Job No: 3507127
VII-1
working for this report limits only to panels (W1 to W15) in western section of CRO
and few panels in Eastern section of CRO (E12 & E13) of Churi Block and part of
Benti Block only for CM.
The area having thickness less than 3.0 m in Benti Block have been proposed
to work with Low Height LHD in Churi-Benti project. Area having thickness greater
than 3.0m have been proposed to work with Continuous Miner.
Feasibility of extension of project boundary:
The possibility of extension of existing boundary was examined for adding more
reserves for deployment of Continuous Miner. It is not possible to extend the existing
boundary. The possibility of extension of existing boundary in Benti Block up to Fault
F-13 was also examined. Due to presence of link road for Ashok project and existing
Benti nala, the extension of the boundary up to fault F13 is not possible. The colliery
authority has also communicated this.
The existing mine boundary in Benti Block has been taken as project
boundary for the Churi-Benti project.
7.2
MINE BOUNDARIES
The proposed boundary for Churi-Benti UG project is same as existing
boundaries of Churi UG mine.
7.3
EXTRACTABLE RESERVES
The area under the Churi-Benti project falls under the Churi & Benti (partly)
blocks. While calculating the reserves for continuous miner, the following
considerations have been made:
 The area having thickness greater than 3.0m has been considered for CM
deployment. The remaining areas has been considered for conventional Bord
& Pillar development/ Depillaring.
 The virgin patches falling within the proposed CM panels shall be developed
and depillared by continuous miner itself. Its reserves are shown in the table
below.
 The thickness of extraction in development and depillaring for CM has been
considered as 4.6m
 The percentage of extraction has been taken as 65% of coal in standing
pillars
 The development height for B &P working has been considered as 2.4m or
less (actual thickness of the seam after leaving 0.3m-0.5m of coal in roof).
 The extractable thickness for the conventional B & P depillaring has been
taken as 4.0m or less (actual seam thickness).
 Roof coal beyond 2.40m in the developed galleries shall be taken while
depillaring.
Job No: 3507127
VII-2
 Out of total
11.079 M.Te of extractable reserves only 0.939 M.Te of
extractable reserves in Benti Block is considered for B &P development.
Table 7.1: Summary of Estimated Extractable Reserves
Seam / Section
Churi block
Benti block
Total
Dev.
Dep.
Dev.
Dep.
A. Continuous Miner
Lower Bachra seam (LBS)
0.224
2.979
---
---
3.203
Bottom Lower seam (BLB)
---
---
0.464
0.547
1.011
Sub-Total
0.224
2.979
0.464
0.547
4.214
B. Heightening District
Lower Bachra seam (LBS)
0.915
---
---
0.915
Sub-Total
0.915
---
---
0.915
C. Bord & Pillar
Upper Bachra seam (UBS)
0.755
2.928
---
---
3.683
Lower Bachra seam (LBS)
0.242
5.037
---
---
5.279
Bottom Lower Bachra (BLB)
---
---
0.521
0.748
1.269
Upper section of Top Lower
---
---
0.418
0.430
0.848
Bachra (UTLB)
Sub-Total
0.997
7.965
0.939
1.178
11.079
7.4
PRODUCTION TARGET & LIFE OF THE MINE
Considering an average productivity of the loading equipment over the life of
the mine, proposed production target from the mine is as under:
Existing production
-
0.16 MTY
Additional Production
Heightening District
-
0.15 MTY
(2 Remote Controlled LHDs - 2.7Cu.m.)
Continuous Miner Panel
-
0.50 MTY
TOTAL
-
0.81 MTY
Considering the extractable reserves in western section of Churi block, few
panels in Eastern section of CRO (E12 & E13) & part of Benti block and the
production schedule, the life of the mine is expected to be about 11years (including
production built-up & tapering periods).
Job No: 3507127
VII-3
CHAPTER-VIII
MINE ENTRIES
8.1
SELECTION OF MINE ENTRIES
Churi underground(Re-organization) is an on going project. It has been
approached through a pair of inclines (Inc.No-6 & Inc. No-7). Presently the mine is
operating in Bottom Lower Bachra seam in Benti block and Upper Bachra seam in
Churi block with above-mentioned entries. It is proposed to continue with same set of
mine entries for Churi-Benti project. The brief detail of the existing entries along with
their proposed utility is shown in Table 8.1.
For deployment of continuous miner in Benti block (including one of the
existing panel) to enhance production, it is proposed for additional drivages in coal
below Damodar River. It is necessary to make additional drivages at appropriate
location for optimal ventilation system, traveling/ man-riding route, provide approach
for transport of CM package equipment requiring tramming height of around 2.7m,
provide alternative escape route and to make optimal use of existing resources.
It is proposed for drivages in coal to connect panel W-11 (in Lower Bachra
seam, Churi block) along true dip and trunk roadway in Bottom Lower Bachra
seam/section (Benti block) at right angle up to fault F-11A. This will facilitate
formation of self-draining panels on either of the trunk roadway and optimal transport
& ventilation layout of the panels.
Justification for additional Drivages :
The proposed drivages will be second drivages below Damodar River. While
granting permission for the first drivages below Damodar River through W-6 panel,
DGMS has made observation for alternate means of access & egress on other side
of Damodar River. The approach to surface site in Benti block is long and difficult. It
will be difficult to maintain such isolated mine entry. Such isolated place is likely to
give way to illegal activities. Moreover, problem of extremists already exists in this
area. In view of the difficulty of maintaining isolated mine entry, it is better to provide
alternate means of access & egress from underground itself.
Besides, the drivages from the surface would take 3-4 years. Considering
limited reserves and life of mine in Benti block, the drivages may not be economic.
8.2
DIMENSION & PURPOSE OF MINE ENTRIES
The detail of the mine entries & other drivages area are shown in Table 8.1
along with dimension and purpose.
8.3
DETAILS OF STRATA BUNKERS
The brief description of mine entries, underground drivages and other
drivages/strata bunkers is given in Table 8.1.
Job No: 3507127
VIII-1
Table - 8.1: Brief Description of Mine Entries & Drivages
The details of existing entries and other mine drivages to be used for the
project are as follows:
Sl.
Mine entry
X-Section
Length/
Gradient
Approach
Purpose & mode of transport
No.
(Incline/shaft -
(Dia/WxH)
Depth
(From / To)
fitted, if any
No./Name)
(m/m x m)
(m)
Existing Entries & Underground Drivages
A.
CHURI OLD MINE AREA (MANUAL SECTION)
1
Incline No.1
4.8mx2.8m
200
-
Surface
Sealed off
toUBS
2
Incline No.1A
4.8mx2.8m
205
-
Surface to
Return of LBS
UBS/LBS
3
Incline No.2A
4.2mx1.8m
40
-
Surface
Haulage
toUBS/LBS
(Presently sealed off)
4
Incline No.3A
4.8mx2.8m
172
-
Surface
Traveling and intake
toUBS
(Presently sealed off)
5
Incline No.4A
4.8mx2.8m
167
-
Surface
Haulage (Coal/material)
toUBS
(Presently sealed off)
6
Air Shaft
1 (Near
4.26m dia
51.82
Vertical
Surface
Return airway (main fan) for UBS.
Incline No.4A
toLBS
B.
CHURI RE-ORGN. AREA (MECHANISED SECTION)
1
Incline No.6
4,8m x 2.8m
400
1 in 4
Surface to
Haulage (Material supply) & Intake.
LBS
2
Incline No.7
4.8m x 2.8m
450
1 in 4.5
Surface to
Coal transport (Belt conveyor),
LBS
Travelling & Intake.
3
Drivages below river
3.0m x 2.0m
-
-
Churi to Benti
Haulage and belt roadway,
Damodar, 3-headings
Block
intake/return airways
(Existing)
C.
CHURI OLD MINE AREA (DEVELOPED & SEALED OFF)
1
Incline No.2, 3, 4 & 5
Proposed Additional Other Drivages
1
Drivages below river
4.8m x 3.0m
-
-
Churi to Benti
Additional escape route &
Damodar, 3-headings
Block
Ventilation
2
Strata
Bunker
600t
-
Vertical
-
Strata Bunker
(SB1)/Staple Pit
3
Strata
Bunker
400t
-
Vertical
-
Strata Bunker
(SB2)/Staple Pit
Job No: 3507127
VIII-2
Job No: 511101
VIII-3/4
CHAPTER - IX
MINING STRATEGY
9.1
CONSTRAINTS IN MINING
The present constraints within the project boundary are summarized as under:
A.
Surface Constraints
(i)
Acquisition of land (Forest/ Jungle Jhari/Tenancy)
(ii)
Power trestles passing over the proposed mining area of Churi block.
(iii)
Rehabilitation of villages/ families.
(iv)
Roads, Damodar & Saphi rivers, nala and HFL over the mining area,
(v)
Existing mine boundary, diverted Benti nala & approach road to Ashok
OC project in Benti block
(vi)
Piparwar rehabilitation site over Benti block
(vii)
Other surface features, like Piparwar GM office, BOC quarters, DVC
sub-station, water filter plant, etc. over Churi block
B.
Underground Constraints
The proposed mining area of the project consists of area under Churi block
and part of area under Benti block (up to existing boundary in sector A). The details
of the underground constraints for the blocks are stated as under :
1.
Churi block
(i)
The development reserve in Lower Bachra seam (LBS) and Upper
Bachra seam (UBS) has almost exhausted.
(ii)
The thickness of Lower Bachra seam to the west has gradually
increased. The average thickness being
5.5 m. In one isolated
borehole NNKC-48 (in the south-west), the thickness has increased to
as much as 11.24m.
(iii)
LBS & UBS are contiguous in major part of the property except in a
small part to the east in Churi old, where the parting is more than 9m.
The parting reduces to as low as 0.47m.
(iv)
Analysis of seam structure of LBS shows presence of bands mostly in
the upper section. Extraction of full seam thickness of LBS may affect
the overall grade.
(viii)
Existing galleries of the developed panels of UBS & LBS has low
development height up to 2.4m.
(ix)
The system of support in the existing developed galleries of the panels
in UBS & LBS is roof bolting.
(x)
Low parting thickness between the seams in major part of mining area
(xi)
Narrow x-section (3.0m x 2.0m) of the approach to Benti block through
3-headings in W-6 panel of Lower Bachra seam (LBS) in Churi block to
Bottom Lower Bachra (BLB) in Benti block below Damodar river.
2.
Benti block
(i)
The upper Bachra seam has not developed over the entire proposed
mining area, except a small part near to Damodar River.
Job No: 3507127
IX/1
(ii)
Lower Bachra seam splits in two parts. Top (TLB) & Bottom (BLB)
sections. Top section further splits in two parts, i.e Upper (UTLB) &
Lower (LTLB) sections. The splits of Top section combines (CTLB) in
some part of the property.
Splitting / merging of the seam/section over the proposed mining area
is observed in Benti block. The property shows presence of irregular
banding of seam/sections. Therefore, it is essential to ensure exact
working over the entire property in the proposed mining area
(iii)
The parting between the seam/section mainly comprises of shale/ carb.
Shale/ sandy shale, which may not be self-supporting and may require
leaving of 0.3-0.5m of coal in roof.
(iv)
Grade of the coal for bottom split (BLB) varies from B - E and top
section (UTLB) varies from D-F.
(v)
The parting between BLB & LTLB/CTLB varies from 0.30-5.0m. In
major part of the area, it is generally less than 1.0m. The parting
between LTLB and UTLB in major part of the area is also less than
1.0m. Hence, entire middle section may be lost either in maintaining
statutory parting of 3.0m between two workable sections or due to its
unworkable thickness.
9.2
GEO-MINING CHARACTERISTICS
The geo-mining parameters of the workable seams/sections in Churi & Benti
block have been summarized in the tables below :
Table 9.1 : Geo-mining Characteristics of mining area under Churi block
Sl.
Parameters
Upper Bachra Seam (UBS)
Lower Bachra seam (LBS)
No.
1
Area within mine boundary
5.89 sq. km
2
Mining area considered for CM
2.03 sq. km
deployment
3
No. of borehole intersections
56
within mine boundary
4
Boreholes density (BHs/sq.km)
9.5
5
General Thickness range (m)
0.13-4.84
1.71-11.24
6
Depth range (m)
26.21 - 91.00
21.59 - 93.65
7
Parting (m)
0.47-20.27
8
Grade of Coal (inband)
C - E
B - E
9
Present declared grade
Grade ‘B’ Long Flame
10
Immediate roof
Grey shale, sandy shale,
Carb. Shale / grey shale /
conglomerate, medium to
fine to medium grained
coarse grained sand stone
sandstone
11
Immediate floor
Carbonaceous shale, grey
Grey shale, intercalations of
shale
shale & sandstone,
carbonaceous shale, sandy
shale
12
Present Status of mining
Manual B&P development being
Development almost
carried out
completed. Standing on
pillars
Job No: 3507127
IX/2
Table 9.2: Geo-mining Characteristics of mining area under Benti block
Sl.
Parameters
Upper section of Top Lower
Bottom Lower Bachra
No.
Bachra (UTLB) / Combined
(BLB)
Top Lower Bachra (CTLB)
1
Area within proposed mine boundary
2.1sq. km
Existing area
1.79sq. km
Additional area beyond existing
0.31sq. km
boundary ( not considered for this
report)
2
Mining area considered for CM
0.41 sq. km
deployment
3
No. of borehole intersections within
23
proposed mine boundary
4
Boreholes density (BHs /sq. km)
12.7
5
General Thickness range (m)
0.45 - 4.15 (UTLB)
0.24 - 4.25
1.10 - 5.10 (CTLB)
6
Depth range (m)
73.10 - 109.19 (UTLB)
76.27 - 121.68
74.06 - 106.75 (CTLB)
7
Parting (m)
0.30 - 5.17
(parting between BLB & CTLB/LTLB)
8
Grade of Coal (inband)
C - F (UTLB)
A - E
D - F (CTLB)
9
Present declared grade
Grade ‘B’ Long Flame (BLB)
10
Immediate roof
Medium to coarse grained
Coarse to very coarse
sandstone, carbonaceous
grained sandstone
shale grey shale &
carbonaceous shale, grey
conglomerate
shale & sandy shale
11
Immediate floor
Carbonaceous shale, sandy
Sandy shale, alternate
shale, grey shale, grey wacks,
bands of shale &
medium to coarse grained
sandstone, carbonaceous
sandstone & alternate band of
shale, grey wacks, coarse
shale & sandstone
to very coarse grained
sanstone
12
Present Status of mining
Virgin
Initial B&P development
by LHD being done
9.3
SELECTION OF MINING METHOD
Existing Mining Method
The entire property in Churi UG project is almost developed along the floor in
both Upper Bachra & Lower Bachra seams except few virgin patches in UBS.
The parting thickness over the entire property of Churi UG mine varies from
0.47m to 20.27m.
The property lying between the parting ranges of 0.47m to 9.0m falls under
the contiguous condition. Therefore, the entire property of the mine has been
classified into two categories i.e. contiguous property & Non-contiguous
property.
In the discussions held at CMPDI HQ, it was decided to deploy Continuous
Miner in the areas free from workable thickness of UBS and having parting
(between UBS and LBS) greater than 9 m. This area lies west to the main dip
in the CRO and few panels of eastern section of CRO.
Job No: 3507127
IX/3
Subsequently, in the review meeting, chaired by CMD, CCL on 16.09.2006 at
N.K area office, it was decided to deploy CM in the western section of CRO
only. The remaining area i.e. eastern section of CRO & Churi old section shall
be worked later on by any other suitable method. It was also advised that CM
should first be utilized for development in any virgin patch of the mine to gain
experience. Accordingly, the working strategy has been formulated.
PRESENT PROPOSAL
The property lying in the western section of CRO, panel E12 & E13 and part
of Benti Block has been considered for deployment of CM. The extractable
reserve for CM in the above mentioned area has been estimated 4.214 MT.
FUTURE POTENTIAL FOR CM DEPLOYMENT:
Eastern section of Churi Re-organization and Churi Old section.
Both the seams are almost developed and standing on pillars in the eastern
section of CRO and Churi old mine. The extractable reserves of about 8.9 MT
may be available for depillaring. The details of the reserve are given in
Chapter-IV. But this requires scientific investigation for parting stability to work
both the seams independently. The major portion of the above-mentioned part
is contiguous in nature.
9.4
SELECTION OF MINING METHOD
9.4.1
Introduction of Mass Production Technology
The various methods of Mass Production Technology are as follows:
(i)
Blasting Gallery Method
It is suitable for depillaring of thick coal seams. The optimum thickness
of seam for this method is at least 8.0m. The area having seam thickness
more than 8.0m in Churi UG is in a very small patch. Rest part of the area is
having thickness less than 8m and also has overlying Upper Bachra seam
having workable thickness with low parting. To work Upper Bachra seam, a
minimum parting of at least 3.0m has to be maintained. To maintain a parting
of 3.0m or more, the effective thickness of extraction in Lower Bachra seam
will further get reduced. If full thickness is extracted in Lower Bachra Seam,
the Upper Bachra Seam will not be extractable. Contiguity of seams exists in
a considerable part of the property. The average seam thickness of LBS is
around 5.5 m. Even if it is considered for extraction of reduced seam
thickness in LBS (<8m), it will not be suitable for the exploitation of both the
seams. Analysis of seam structure shows that seam/ section comprises of
multiple bands and generally band exists beyond 4.0 m. Therefore, if the
extraction will be done by Blasting gallery methods, the grade of the seam will
fall down at least by one grade due to presence of multiple bands in upper
section of the seam. The project may not be economically viable on reduction
Job No: 3507127
IX/4
of grade from the declared grade’B’. Hence, this method has not been
considered.
(ii)
Longwall Method
As both the seams are almost developed on Bord & Pillar method and
balance virgin reserve is not sufficient for longwall mining. So, this method
has not been considered.
(iii)
Working in Double Sections
Churi -Benti project is planned for the area where upper seam is not workable.
Only lower seam (LBS) is workable having average thickness of 5.5m. Double
section workings may be considered for the eastern section of CRO. Double
section workings may be considered later on.
(iv)
Depillaring with Continuous Miner
This method has been successfully used in Indian mining conditions.
Experience in zero seam of Anjan Hill Mine of SECL and Tandsi Underground
mine of WCL is encouraging. The geological conditions of both the mines are
almost similar to that of Churi UG. The only difference is that Churi
Underground project is developed along the floor of the seam having
development height of 2.4m.and bolted galleries. The proposed area for CM
deployment consists of Western section of CRO and part of the Benti block.
The proposed area for CM deployment shows overlying seam/ section
unworkable and is suitable for deployment of CM. The area proposed in Benti
is virgin. Development and depillaring of property in Benti will further help in
gaining confidence for CM operation. Hence, this method may be adopted for
depillaring of developed pillars of western section of Churi Reorganization and
for development and depillaring in Benti block.
9.4.2
Reasons for Selecting Continuous Miner
Continuous Miner has been selected for development of virgin property
in Benti block and depillaring of developed pillars in Churi UG project.
The reasons for selection of this method are as follows:
a)
Churi UG has been developed on Bord & Pillar method. It has a flat
gradient (2-3 degree) and the av. thickness of seam is 5.5m.
b)
Benti block is almost virgin. Seam thickness, gradient and declared
grade are favorable for CM deployment.
c)
Benti Block has been already approached through W-6 panel.
d)
The working panel can be isolated quickly from goaf area as the rate of
extraction is faster.
e)
The proposed method is flexible and does not require large
geologically undisturbed patches as in the case of longwall mining. In
Churi UG, the developed workings are almost free from any geological
disturbances.
Job No: 3507127
IX/5
f)
This method requires relatively low capital cost for high production and
productivity in comparison to longwall method.
g)
The rate of extraction of this method is high and the method has been
proved successful in Anjan Hill/ NCPH mines and Tandsi mines of
SECL and WCL respectively.
9.5
MINE DEVELOPMENT/DEPILLARING STRATEGY
9.5.2 PROPOSED MINE DEVELOPMENT STRATEGY
The broad mining strategy proposed for implementation is briefly described as
under :
a.
Delineation of Mining Area (for CM)
(i)
The mining area having seam thickness >3.0m and unworkable overlying
seam/sections and/or free from workable seam/sections shall be worked with
Continuous Miner.
Accordingly, virgin area in Bottom Lower Bachra seam/section of Benti block,
developed panels of western section of CRO (panels W1 -W15) and E12 &
E13 panels of eastern section of CRO have been considered for deployment
of Continuous Miner.
(ii)
Virgin patches falling within the developed panels in LBS in Churi-Benti
underground project are proposed to be developed and depillared by
Continuous Miner.
(iii)
No working has been proposed in the areas having thickness less than 2.0m.
If any doubt arises regarding the thickness of the seam in the proposed area
by different suggested method, the same may be verified by putting some
extra exploration boreholes. Provision for exploratory boreholes have been
made in this report.
IV.
The assessment of reserves for continuous miner panels has been done on
the basis of CM deployed in some of the mines CIL with operating height
limited to 4.6m, thereby leaving some coal in roof in western section of CRO.
Efforts should be made while finalizing the technology for implementation to
maximize the recovery/extraction.
b.
Heightening and Widening of Galleries
Existing galleries of developed panels in western section of CRO except W-16
panel is proposed for heightening. No heightening is proposed in Benti
section.
The existing Churi underground mine is developed along the floor in both the
seams having height of working 2.4m and width of gallery is 4.2m. The
Job No: 3507127
IX/6
approved and available Continuous Miner, presently operating in CIL mines,
is available for 4.6m heights. So the existing developed workings, wherever
feasible, are to be heightened up to 4.6m and it shall be re-supported with
roof bolting. The blasted coal will be loaded by Remote controlled LHDs.
Provision for the same has been made in this report.
The workings of heightening shall be kept sufficiently ahead of
Continuous Miner panels so that working of CM is not affected.
Adjustment of mine boundary.
As colliery authorities communicated us that further extension of boundary up
to fault F-13 is not possible and existing boundary in Benti should be
considered as the final boundary. So, property beyond the existing boundary
in Sector-A of Benti block has not been considered for this report
c.
Additional Approach to Benti block by crossing below Damodar River:
It is proposed to first deploy the CM in Benti block for development and
depillaring of BLB seam/section. This requires crossing of Damodar River by
driving 3 headings from panel W-11, to facilitate the transport of CM package
equipment and effective ventilation system of the project. The existing
headings for approach to Benti block through W-6 panel has effective x-
section of 3.0x2.0m, which may not be adequate for CM transportation
The heightening of existing headings below Damodar River from panel W-6
may not be practically feasible. Hence, it is proposed to re-cross Damodar
river from panel W-11 with limited number of headings of adequate x-cross
section after taking permission from DGMS.
d.
Strategy for remaining area
(i)
It is proposed to develop and depillar simultaneously the remaining area of
Benti block in two sections having thickness less than 3.0m by Bord &
Pillar method with low-height LHDs.
(ii)
It is also proposed to develop and depillar simultaneously the remaining
property in eastern section of CRO and Churi old in two sections by B & P
with LHD or any other suitable method.
e.
Sequence of operation for B & P working
 The existing LHD panel will continue in Benti Section for Bord and
Pillar development of trunk heading (T-2) up to dip most point.
 After development of trunk heading (T-2) , the development of BLB and
UTLB shall be done in those panels where CM cannot be deployed.
 The existing manual development in UBS will continue for development
of the remaining virgin reserves in UBS in CRO.
 The manual workings shall be phased out before arrival of CM
package.
Job No: 3507127
IX/7
 After exhaustion of development and depillaring reserves in Benti block
and heightening reserves in western section of CRO, the equipment
deployed there may be utilized for depillaring of the developed pillars in
remaining panels of eastern section of CRO and Churi old.
f.
Sequence of operation for Continuous Miner
 It is proposed to first deploy the CM in Benti block for development and
depillaring of BLB seam/section.
 After development and depillaring of proposed area by CM in Benti
block, the CM is proposed to be deployed in western section of CRO
for depillaring of standing pillars in W1-W15, except W6. Depillaring of
W6 panel is not proposed till complete exhaustion of reserves in Benti
block.
 Deployment of Continuous Miner may be done in the dip most panels
in western section of CRO (leaving W-6 & W-16 panels) and panel E-
12 & E-13 in eastern section of CRO. The sequence of deployment of
CM may be changed as per the operational requirement at that time of
the project to facilitate the safe operation.
 After exhaustion of reserves in Benti block and western & eastern
(panels E-12 & E-13) sections of CRO, the remaining property under
Churi block may be depillared simultaneously with LHD in both the
seams.
Depillaring of panel W6 is possible only after complete exhaustion of reserves
in Benti block.
g.
Phasing out of manual system of mining
The B&P development reserves for UBS are nearing exhaustion. Hence, it is
proposed to phase out the manual Bord & Pillar district for CM panel.
i.
Strategy for coal evacuation
 The existing belt lay out will be strengthened by replacing the existing
drive heads etc.
 For coal evacuation from Benti, the proposed evacuation route will be
through W-6 Panel. The trunk belt layout will be in Inc. no.7, W-6 panel,
T1, T2, T3 panel of Benti block. Gate belt layout shall be in panels
where CM and LHDs are proposed to be deployed.
 After exhaustion of reserves for the continuous miner in Benti block,
the trunk belt of T1, T2 & T3 panel may be re-utilized for laying beyond
W-6 panel to cater need of continuous miner in Churi CRO.
 The existing belt will cater the need of heightening districts in western
section of CRO till the life of CM in Benti block.
Job No: 3507127
IX/8
i.
Re-organization of Ventilation System
It is for re-organization of ventilation system considering the high resistance of
the existing mine. It is for opening of trunk roadways of old Churi section for
establishing return airway path. Further, the existing approach to Benti block through
W-6 panel is proposed to be used as intake airway while the additional approach
proposed through W-11 panel is to be used as return airway.
i.
Land acquisition for the project
The land acquisition for the project is proposed for one complete life cycle of
continuous miner as decided during presentation of Production Augmentation
report before the FDs of CCL on 5.12.06.The provision for the same has been
made in the report.
9.5.2
Utilization of Existing Resources
(i)
Presently, there are 5 nos. of LHDs. For heightening & widening of developed
galleries in the western section of CRO, 2 remote controlled LHDs has been
proposed. The existing LHDs may be gainfully utilized for development in
Benti Block. Low Height LHD will replace the existing LHDs.
(ii)
Existing transport layout and mine infrastructure shall be utilized after
modification as per Supplier’s requirement to suit Continuous Miner
technology.
(iii)
W-6 panel of LBS in western section of CRO shall be left intact and
maintained to facilitate the approach to Benti UG, which is presently being
developed after crossing the Damodar River from this panel.
(iv)
In addition to above, other existing resources may also be utilized as and
when required.
9.5.3
Prior Permission from DGMS
Prior permissions from DGMS is required for the following:
(i)
Heightening and widening of existing developed galleries in LBS for
deployment of Continuous Miner in CRO.
(ii)
Permission for development and depillaring of B&P panel with Continuous
Miner.
(iii)
Working below any surface features such as nalla, road, water reservoir, fire
etc. These surface features include all the features, which may endanger the
safety of mine.
(iv)
Permission for Continuous Miner deployment shall be sought in consultation
with the Supplier.
In addition to above, routine mining operations, which require prior permission
from DGMS and other permission for safe working has also to be obtained.
9.5.4 Scientific Study
The technology suggested for depillaring of Lower Bachra seams by
continuous miner in CRO is a new concept in CCL. It has been successfully
Job No: 3507127
IX/9
deployed and worked in SECL and WCL. It requires some scientific study in
consultation with the bidder for safe working of the mine.
This scientific study may be conducted to:
(i)
Ascertain the hydro-geological regime, since the property proposed for
working is bounded between two rivers namely, Saphi and Damodar.
(ii)
Ascertain the connectivity of Churi UG working with any potential source of
danger, which may endanger the safety of the mine.
(iii)
Ascertain the connectivity of fault etc. to rivers or any other water bodies.
(iv)
Ascertain the support requirement for depillaring with CM.
In addition to above, any activity, which requires verification and may
endanger the safety of the mine, shall further be confirmed by the scientific study as
and when it is required.
9.6
MINE DEVELOPMENT ACTIVITIES
9.6.1 Proposed Mine Development Activities:
The following other developmental activities have to be completed:
 Acquisition of surface land (forest/tenancy).
 Rehabilitation of villages & shifting of power line.
 Heightening of existing haulage roadway (Incline no:6) for underground
transportation of Continuous Miner package.
 Heightening/widening of existing developed galleries of the working
panels in western section of CRO.
 Strengthening of existing coal evacuation system by belt conveyors.
 Drifting required for construction of Underground Strata Bunkers of
adequate capacity.
 Arrangement for storage & supply of clean water for Continuous Miner
operation.
 Construction of main sump of adequate capacity with arrangement for
cleaning.
 Strengthening of existing electrical supply system at surface &
underground power supply arrangement for CM package.
 The existing 37 KW endless haulage for material transport is to be
replaced by 90 KW.
Job No: 3507127
IX/10
CHAPTER - X
METHOD OF WORK
10.1 METHOD OF DEVELOPMENT
The whole property of Churi Underground mine has been developed in stages
and their present status are as follows:
CHURI BLOCK:
*
Churi Old (Manual Section) : Developed fully by Conventional B&P
with drilling, blasting and manual loading into tubs with rope haulage transport
in both the seams. Presently workings are isolated except few headings for
return airway.
*
Churi Old (Sealed Off): In this part of the property only Lower Bachra
seam is worked which is developed and depillared in distant past by
Conventional Bord & Pillar method and presently sealed off. It falls beyond the
proposed mining area for Churi-Benti UG Project (greater than 150m from
proposed boundary). The presence of water / fire cannot be ruled out.
Churi Re-Organization(CRO) Section : Mechanized development of
Lower Bachra seam by LHD with LDCC/MDCC and Gate Belt Conveyor
transport system whereas Upper Bachra seam is developed manually.
Development of LBS in CRO section is almost complete except in patches,
which requires conformity of thickness by putting extra exploration boreholes.
Upper Bachra Seam is partly developed and partly virgin which has to be
developed by the Conventional Bord & Pillar method of mining. Depillaring of
seams in CRO and Churi Old has not been done in any of the seams due to
non-availability of land.
BENTI BLOCK:
Benti Section: Presently development with LHD is in progress in the Bottom
lower Bachra seam/section after crossing the Damodar River through W-6
panel in CRO.
10.1.1 PRESENT MINING METHOD & MINE DEVELOPMENT
The status of the seams being worked is as under:
(i)
Upper Bachra (UBS)
-B & P Development in progress.
(ii)
Lower Bachra (LBS)
-Almost fully developed by B&P.
(iii)
Bottom Lower Bachra (BLB) -B & P Dev. is in progress in Benti block
In Churi Block, both the seams namely lower Bachra & Upper Bachra are
almost fully developed by Bord & Pillar method of mining. Lower Bachra seam
Job No: 3507127
X/1
has been fully developed with LHD in CRO & manually in Churi old Section of
Churi block. Upper Bachra seam is being developed manually in CRO. The
UBS has also been developed manually by B & P method in Churi old mine.
Part of the property of Upper Bachra seam in CRO, is still to be developed,
which is in progress.
The Churi UG project is developed along the floor of the seam in both the
seams. The size of pillar is 25x25m centre-to-centre and size of gallery
4.2x2.4m (in LBS) & 4.2x1.5-2.0m. Depth of working for UBS and LBS varies
from 18-91m & 37-93m respectively. The dip of the coal bearing strata
generally varies from 1 in 20 to 1 in 40 (20-30), generally towards northwest.
In Benti Block, major part of the property is virgin. Development of Bottom
Lower Bachra seam/section is in progress by LHD along the floor of the seam.
The size of pillar is 25x25m centre-to-centre and size of gallery 4.2x2.4m (in
BLB).
10.1.2 Trunk Road Development
At present Churi Old and CRO have separate set of trunk roadways in each
section along the mine entries. The trunk roadways (in each section)
comprises of 4-6 headings. Trunk roadways have been driven up to the
adjusted boundary between CRO and Ray-Bachra underground mine in
Lower Bachra Seam.
Trunk headings development in Churi old mine has been done up to 47th
level. The present length along the trunk roadway up to extreme point in CRO
is more than 2.5km whereas in Churi Old mine is about one km. The method
of trunk roadway development in CRO is mechanized Bord & Pillar with LHD
whereas in Churi old mine it is manual Bord and Pillar. At present drivage of
trunk roadway is complete in both the seams and sections of workings (CRO
& Churi old). Benti block has been approached through W-6 panel in CRO
with 3 headings. Trunk heading development is in progress with LHD in
Bottom Lower Bachra seam/section.
10.1.3 Panel Development and Extraction
The panel layout in CRO and Churi Old consists of 5-6 headings, except few,
in both the seams/sections. The panels have gallery size of 4.2x2.4m & size
of pillar is 25x25m center-to-center. In few cases, the size of pillar may be of
lesser dimension. The seam thickness of Upper Bachra Seam varies from
1.2m to 4.0m whereas the seam thickness of Lower Bachra seam varies up to
11.24m (visual thickness) as in NNKC-48. The panels in Churi block are
generally developed up to the boundary of the mine but in some cases it has
not been developed up to the boundary due to thickness problem or practical
operational difficulties at that time. The panels are developed generally with
2.0-2.4m height of extraction leaving 0.5-0.6m solid coal in roof against
immediate shaly roof.
Job No: 3507127
X/2
10.1.4 Existing Transport
Presently the mode of transport of coal from face to surface is as follows :
(a)
SDL/LHD feeds coal to face conveyor/medium duty chain conveyor
and then to Gate Belt Conveyor and brought to surface by trunk belt
conveyor and then fed to CHP at Ray Siding.
(b)
Material transport from surface to underground is through incline No.6
by direct rope haulage and endless haulages.
(c)
Coal from manual district is directly loaded manually onto face
conveyors which feeds to the gate belt conveyor and finally to trunk
belt conveyor for transport up to surface.
10.1.5 Existing Ventilation
The mine is categorized as Degree-I in gassiness. The ventilation system
comprises of Incline 6 & 7 as intake and air -shaft and Incline 1A as the return
for the Upper Bachra, Lower Bachra and Bottom Lower Bachra seam/section.
One PV-200 type Fan is presently installed to serve the ventilation
requirement of the mine.
10.1.6 Existing Support System
The existing practices of roof support in the workings of Churi & Benti blocks
are roof bolts with W-strap as per approved SSR from DGMS. It is also
supplemented with conventional support as and when required.
10.1.7 Existing Production:
The present production from Churi UG is from Upper Bachra in CRO and from
Bottom Lower Bachra in Benti Section. The mine is presently producing
around 0.165MTY with mechanized as well as manual districts.
10.2 PROPOSED METHOD OF WORK
The suggested method of extraction for the Churi-Benti project comprises of:
 Bord & Pillar development & depillaring with Continuous Miner
 Bord & Pillar development & depillaring with low height LHD
 Heightening of existing galleries with remote controlled LHD.
10.2.1 BORD & PILLAR DEVELOPMENT & DEPILLARING WITH CONTINUOUS
MINER
The Continuous Miner will be deployed for development and depillaring of virgin
reserves in Benti block (Panel B-5 to B-9 & T-3). Subsequently, it will be shifted in
Churi Block for depillaring of panels W-1 to W-15 in the western section of CRO and
panel E12 & E13 of eastern section of CRO. The virgin patches within the panel are
also proposed to be developed and depillared by Continuous Miner.
A.
Geo-mining Parameters: The geo-mining parameters of the area proposed
for deployment of Continuous Miner is briefly stated below:
Job No: 3507127
X/3
Table 10.1 : Geo-mining Characteristics of mining area under Churi
block
Sl.
Parameters
Upper Bachra Seam (UBS)
Lower Bachra seam (LBS)
No.
1
Area within mine boundary
5.89 sq. km
2
Mining area considered for CM
2.03 sq. km
deployment
3
No. of borehole intersections
56
within mine boundary
4
Boreholes density (BHs/sq.km)
9.5
5
General Thickness range (m)
0.13-4.84
1.71-11.24
6
Depth range (m)
26.21 - 91.00
21.59 - 93.65
7
Parting (m)
0.47-20.27
8
Grade of Coal (inband)
C - E
B - E
9
Present declared grade
Grade „B‟ Long Flame
10
Immediate roof
Grey shale, sandy shale,
Carb. Shale / grey shale /
conglomerate, medium to
fine to medium grained
coarse grained sand stone
sandstone
11
Immediate floor
Carbonaceous shale, grey
Grey shale, intercalations of
shale
shale & sandstone,
carbonaceous shale, sandy
shale
12
R.M.R
47.3
41.72-61.0
10.2: Geo-mining Characteristics of mining area under Benti block
Sl.
Parameters
Upper section of Top Lower
Bottom Lower Bachra
No.
Bachra (UTLB) / Combined
seam (BLB)
Top Lower Bachra (CTLB)
1
Area within proposed mine boundary
2.1sq. km
Existing area
1.79sq. km
Additional area
0.31sq. km
2
Mining area considered for CM
0.41 sq. km
deployment
3
No. of borehole intersections within
23
proposed mine boundary
4
Boreholes density (BHs /sq. km)
12.7
5
General Thickness range (m)
0.45 - 4.15 (UTLB)
0.24 - 4.25
1.10 - 5.10 (CTLB)
6
Depth range (m)
73.10 - 109.19 (UTLB)
76.27 - 121.68
74.06 - 106.75 (CTLB)
7
Parting (m)
0.30 - 5.17
(parting between BLB & CTLB/LTLB)
8
Grade of Coal (inband)
C - F (UTLB)
A - E
D - F (CTLB)
9
Present declared grade
Grade „B‟ Long Flame (BLB)
10
Immediate roof
Medium to coarse grained
Coarse to very coarse
sandstone, carbonaceous
grained sandstone
shale grey shale &
carbonaceous shale, grey
conglomerate
shale & sandy shale
11
Immediate floor
Carbonaceous shale, sandy
Sandy shale, alternate
shale, grey shale, grey wacks,
bands of shale &
medium to coarse grained
sandstone, carbonaceous
sandstone & alternate band of
shale, grey wacks, coarse
shale & sandstone
to very coarse grained
sanstone
12
Present Status of mining
Virgin
Initial B&P development
by LHD being done
Job No: 3507127
X/4
B.
Mining Parameters for CM Panel
No. of Headings
-
4-8
Gallery width
-
4.2m
Development height
-
2.4m(Already developed)
-
4.6m(where heightening proposed)
Pillar Extraction height
-
2.7m - 4.6m
Av. Pillar size
-
25 x 25m center to center in UBS & LBS.
(Size varies within the panels)
Panel width
-
79.2m - 179.2m (In Churi Block)
125m - 150m (In Benti Block)
Panel length
-
Up to 1000m in both blocks
Cut out distance for CM
-
15m in split
(assumed)
-
10m in Slices
Cutting width
-
3.3m
C.
Panel Development
CHURI BLOCK
Most of the panels in Churi block are almost developed. Panel formation has been
done by considering existing panel barriers, which shows panels of 4 to 8 headings.
The av. pillar size is 25m x 25m centre to centre with a gallery width of 4.2m. The
virgin patches falling within the panels are proposed to be developed and depillared
by CM itself.
BENTI BLOCK
Major part of the Benti block is virgin. Five headings panel has been proposed for
development and depillaring. The proposed pillar size is 25m x 25m centre to centre
with a gallery width of 4.2m or 4.8 m. The proposed development height for Low
Height LHD panels is 2.4 m or actual seam thickness after leaving 0.3m to 0.50m
coal in roof and 4.6m for CM development district. Proposed width of galleries for
CM development panels are 4.8m.
Development height and Horizon - The existing average height of development in
Upper Bachra, Lower Bachra, Bottom Lower Bachra and Upper Section of Top
Lower Bachra seam/section proposed to 2.4m or seam thickness leaving 0.3 to 0.5m
coal in the roof to provide additional support to the immediate shaly roof. The seam
has been proposed to develop along the floor of the seam.
LOW HEIGHT LHD PANEL
Pillar Size
: 25m x 25m ( center to center)
Gallery Size
: 4.2m
Development Ht
: 2.4m or actual seam thickness after leaving
0.3m to 0.5m coal in roof
Depillaring Ht
: Actual seam thickness
Job No: 3507127
X/5
CONTINUOUS MINER PANEL b
Pillar Size
: 25m x 25m ( center to center)
Gallery Size
: 4.8m
Development Ht
: 4.6 m or actual seam thickness after leaving
0.3m to 0.5m coal in roof
Depillaring Ht
: 4.6m or Actual seam thickness
D.
Method of Pillar Extraction
Method of extraction would be depillaring with caving. There are many
methods of pillar extraction by continuous miner like:
 NAVID METHOD
 CHRISMAS TREE METHOD
 POCKET AND FENDER METHOD and
 Other methods
The sketches of the above methods are enclosed in this chapter. However the
method of work will be finalized after scientific study for the project .Out of the
above-mentioned methods POCKET AND FENDER METHOD has been
successfully tried in some other mines of CIL .The brief description of the
above method is as under.
The method of extraction of pillars comprises of the following:
Splitting and Slicing of the pillar.
Line of extraction.
Extraction height and horizon.
Manner of extraction.
Sequence of operation in Pillar extraction.
Splitting and Slicing: The existing developed pillar shall be splitted into two
parts by driving a roadway of 6.6m width parallel to pre developed rises and
perpendicular to the face line at the centre of pillar. The height of the splitted
gallery may be 4.6m.
The existing size of pillar is 25m x 25m in which two slices in each fender may
be possible. The width of one slice may be 6.6m and the width of other slice
may be 3.3m. The height of extraction in slices may be 4.6m.
As the method suggested for depillaring is totally new for CCL, so the width
and height of split and slices may change depending upon the method of
extraction. The above width & height of splits and slices are proposed as per
the method being practiced in SECL.
Line of Extraction: The pillars in a depillaring panel will be extracted while
retreating from boundary, maintaining a straight line of extraction. The
straight-line method with fully mechanized equipment has several advantages
over the diagonal line of extraction as it reduces both the tramming distance
and cable length.
Job No: 3507127
X/6
Extraction Height and Horizon: The extraction height in pillar shall be up to
4.6m and it shall be worked along the floor of the seam.
Manner of Extraction: It is proposed to introduce one fully mechanized Bord
& Pillar district using Continuous Miner and Ancillary equipments in Churi -
Benti Project for development and depillaring of Lower Bachra and Bottom
Lower Bachra seam/section. The Continuous Miner will develop virgin
property in Benti block (Thickness >3m) with pillar size 25mx25m and gallery
size 4.8mx4.6m. The developed pillars of the Churi-Benti Project will be
depillared by the CM up to 4.6m height or actual seam thickness.
The manner of extraction would be splitting and slicing, which is common in
the mines of CIL. The mine management and the work force are familiar with
the method and the subsequent strata behaviour. The pillars in a depillaring
panel will be extracted while retreating from boundary, maintaining a straight
line of extraction. There may be several methods/layout for depillaring in a
panel. A tentative layout for depillaring by C.M. is indicated in sketches 1 to 4.
Keeping in view the extraction system/layout being followed in other mines of
CIL with CM, one of the suggested method may be “Pocket and Fender
Method”. In this method, the sequence of extraction may be as under:
A split roadway of suitable width is to be developed parallel to pre-developed
rises and perpendicular to the face line at the center of the pillar. It will form
two fenders and the fenders so formed shall be extracted by making inclined
pockets into that fender at an angle of 600 to the horizontal. These inclined
pockets are made at a particular distance from the side of the pillar to form a
snook that will provide temporary stability to the workings and later on it will
get crushed and helps in regular caving of the roof. While making fenders, the
roadway shall be supported with bolts in a manner specified in the approved
systematic support plan.
The coal cut by the Continuous Miner shall be collected by the gathering arm
of the machine and discharged into Shuttle Cars. The shuttle car feeds the
coal by a Chain Conveyor installed in its body, to a self-propelled Feeder
Breaker. Coal is then discharged to the surface through a series of gate &
trunk belt conveyors.
It is proposed to shift the surface features like villages, roads, power trestles,
private/company quarters, sub-station etc.
Before going for development/depillaring of panels with CM in Churi-Benti
Project, prior permission under Reg. 100 of CMR, 1957 have to be obtained.
Similarly, various public works like road, high tension line etc. passes over the
lease hold property of Churi Block. So before going for depillaring, the
permission under regulation 105 of CMR, 1957 would also have to be
obtained and should be complied effectively.
Job No: 3507127
X/7
Sequence of Operation : The sequence of operation of Continuous Miner for
“Pocket and Fender Method” has been shown in Sketch-2. The details of
sequence of operation of the seams shall be as below :
-
Cut 1 is driven in a split up to a maximum distance of 15m or as
permitted by DGMS.
-
The Continuous Miner is trammed to Cut-2 in second split of a pillar
and commences cutting while the Roof Bolter Machine supports Cut-1.
-
Once the CM completes Cut-2 and Roof bolting is completed in Cut-1,
CM commences Cut-3 (in first split) operation.
-
When Cut-3 in 1st split shall be in progress, the roof bolter shall support
the Cut-2.
-
As the Cut-3 is completed and roof bolter supports Cut-2, CM will again
be trammed to 2nd split for Cut.4.
-
When Cut-4 in 2nd split shall be in progress, the roof bolter shall
support the Cut-3.
-
When Cut-4 is complete and Cut-3 is supported by the roof bolter, then
CM shall be trammed to first split to take the slice-5 in the fender and
Cut-4 shall be supported by the roof bolter.
-
This process shall be repeated as shown in sketch.
In addition to above, other method of extraction like Navid method, Christmas
tree method are also available. Final method of extraction may be finalized
after detailed scientific study for deployment of CM.
E.
Support System
Support system shall be of roof bolting supplemented by conventional support
as and when required.
Support System during panel development
: At the time of panel
development, the roadways are proposed to be supported with roof bolts. The
roof bolting may be quick setting resin roof bolt or fixed column-grouted bolt
using cement, sand mortar. Development galleries will be supported by 2-3
rows of roof bolts 1.8m in length. The distance between two adjacent rows of
bolt and between two adjacent bolts in a row should be around 1.2m. The
above specification may change depending upon the results of the scientific
study. In addition to above, the provisions of Reg. 108 of CMR, 1957 together
with related circulars are to be complied. The support system for the
development galleries shall be as per the approved Systemic Support Rules.
Support System in Split and Slice : The tentative support system in split
galleries may be with quick setting type resin bolts at an interval of 1.2m
between the rows and between bolts.
Slices may not be required to be supported as it is to be extracted with remote
operated Continuous Miner.
Job No: 3507127
X/8
Support of Goaf Edges :
(i)
All the goaf edges shall be supported by rows of quick setting type
resin bolts at 0.80m interval in between the two bolts and between two
rows and 0.5m from either sides of the pillar. The length of such bolts
shall not be less than 1.8m or 2.4m. Such goaf edge support shall be
provided in the split/original gallery, as the case may be, at the start of
the slice cut by the Continuous Miner.
(ii)
Each such goaf edge support shall have three parallel rows of bolts
across the original/split gallery.
(iii)
At least two wooden props shall be installed near the goaf edge on the
rib side as indicator type.
Support System at other places: The trunk roadways and other working
places shall be adequately supported and secured by roof bolting system or
other suitable means of support.
Support System for Geologically disturbed area : All dykes, visible slips
and breaks in roof shall be supported by cogs at an interval of 2.4m on either
sides of such disturbances and with cross-bars across them at an interval of
not exceeding 1.2m.
Smaller geological disturbances, wherever feasible, shall be kept supported
by roof bolts on both sides of the disturbances along with W-strap as suitable
intervals. The length of such roof bolts shall be appropriate to the extent of the
disturbances but in no case less than 1.8m. The spacing between the bolts
shall be approximately chosen on the extent of the geological disturbance but
in no case shall be more than 1.0m.
Additional supports shall be erected as and when required.
Monitoring of Roof Bolts : All the recommendations of DGMS Technical
Circular No.3 of 1996 and other applicable regulations and circulars regarding
roof bolting/floor bolting shall be effectively complied whenever applicable in
this mine for safe working.
Support Material : The specifications of the support materials are as follows:
Roof Bolts : (Tor steel/MS IS:1786-1985/IS:226-1975/IS:1570)
Type : Steel/Mild steel
Lenth of rod -
1.8m/2.4m
Dia of rod
-
20-22mm
Length of thread -
125-150mm
Bearing Plate (IS:226-1975)
Material
=
MS
Thickness
=
6mm
Job No: 3507127
X/9
Size
=
150 x 150 mm2
Nut
: (IS: 1363, Part-3, 1984)
Shape
=
Hexagonal
Height =
20mm
Cement Capsule
Length
=
Not exceeding 400mm
Dia
=
30-32mm
Type
=
Quick setting (the grout should provide a minimum
anchorage of 3 Te after 30 min and 5 Te after two hours of setting.
While doing the bolting operation in any roadways/workings of the mine, the
provisions of CMR 1957 and various DGMS Circular (Viz Cir Tech 3/1996)
shall be effectively complied for safe working of the mine.
F.
Coal Evacuation From CM Panel
The Continuous Miner would cut and simultaneously load the coal by its
inbuilt stage conveyor into the shuttle car directly. The loaded shuttle car
would discharge coal on to Feeder Breaker. Crushed (-100mm size) coal will
be uniformly discharged on to gate belt conveyor, which is installed in the
Central gallery of the panel. This gate belt conveyor will in turn discharge the
coal on the trunk belt conveyor. The gate belt conveyor would be installed in
the gallery so that loading distance and cable length on each side of the
loading point is minimal. The panel width of the CM panel varies from 79.2m
to 179.2m and length of the panel is up to 1000m. 2x200Te strata bunker is
proposed in the Benti block in T-2 panel and 3x200Te strata bunker is
proposed in the Churi block in the trunk heading near to W-6 panel.
G.
Material Transport
The material transport in the panel is proposed to be carried out by endless
and direct haulages.
H.
Ventilation System in Panel
The CM panel in Churi block comprises of 4 to 8 Headings in a panel where
as in Benti block 5 heading panels are proposed. In a 5 heading CM panel,
three galleries on the dip side of the panel would preferably be used as intake
airway while two galleries on the rise side is to be used as return airways. In
case of other panels, the manager of the mine may accordingly decide the no.
of galleries for intake and return airway for adequate ventilation of the panel.
In no condition, the ventilation of the panel should be neglected.
The faces would be ventilated by auxiliary fan using ventilation ducting. Other
measures, which may improve the ventilation of the mine, may also be
adopted as and when required.
Job No: 3507127
X/10
I.
FACE EQUIPMENT OF CONTINUOUS MINER PANEL
It is proposed that CM panel may have the following list of equipments:
1.
Continuous Miner
-
One
(Suitable to prevailing geo-mining condition)
2.
Shuttle Car
-
Three*
3.
Roof Bolter
-
One
4.
Portable Bolter
-
One
5.
Load Haul Dumper
-
One
6.
Feeder Breaker
-
One
7.
Set of Electrical Distribution equipment
-
One
8.
Communication equipment
-
One
* The no of shuttle cars has been taken as per suggestions made vide letter
no. SECL:BSP: DT(O):26/82 dated 28.02.07 of DT(O), SECL addressed to
Dir.(T), CIL.
The details of the equipment as proposed is as below :
Continuous Miner : One suitable Continuous Miner suited to prevailing
condition is proposed. The machine is equipped with radio cord remote
control, dust scrubber and methane monitor. It cuts and loads the coal in
single operation.
Operational Parameters of Continuous Miner (As per CM working in
SECL)
Cutting head width
-
3.3m
Cutting height
-
2.2m(Min.) to 4.6m (Max.)
Length of the machine
-
11.02m
Gallery width required
-
4.8m
Length of Cut in a single pose -
15m
Actual specification of machine may change depending upon the method of
extraction.
Shuttle Car : It transports the extracted coal from the Continuous Miner
loading conveyor to a self propelled stammer Feeder Breaker. From the
feeder breaker, coal is discharged to the gate belt and gate belt fed to the
trunk belt conveyor. The rated load capacity of low to medium capacity shuttle
car varies from 9-15 Te.
Roof Bolter : Since the development height of the panel is 2.4m, so the roof
bolter which can successfully work in a gallery height of 2.2m-4.6m is
proposed. The size and other specification of bolting material shall be of
approved type.
Load Haul Dumper (LHD): LHD may either be diesel or battery operated. It
has the following operations to perform in the Continuous Miner district.
(a)
Cleaning the spillage coal from Shuttle Car.
Job No: 3507127
X/11
(b)
Cleaning and sweeping up the heading of Continuous Miner after it has
completed cutting and thereby reducing time.
(c)
Transport materials and consumable goods.
(d)
Moving switchgear and transformer and also assisting installation of
main HT feeder cables.
Feeder Breaker: It receives the coal from Shuttle Cars and after crushing it to
the desired size of (-) 100mm, feeds it to the conveyor at consistent controlled
rate. It is mounted on tracks. The Feeder Breaker is having hopper sufficient
to hold a complete shuttle car.
J.
Production Proposed
The production proposed from the Continuous Miner panel is 0.50
MTY.
All the mining operations in Continuous Miner panel should be in accordance
with the various regulations of CMR 1957 and various circulars issued by
DGMS for safe working of the mine.
10.2.2 HEIGHTENING OF EXISTING GALLERIES WITH REMOTE CONTROLLED
LHD
The gallery width required for CM is 4.8m and it can cut coal up to a height of
4.6m but the existing workings have the width and height of galleries as 2.4m
and 4.2m, so heightening and widening of gallery may be required. Widening
of gallery will be done as and where required.
I.
Proposal for Heightening of Galleries
There would be separate remote controlled LHD panel for heightening of
existing galleries in the western section of CRO (W-1 to W-15 panels). Other
than these panels, no heightening of panels is proposed in this report. The
heightening of developed galleries is proposed up to 4.6m only leaving at
least 0.3-0.5m in the roof.
II.
Proposal for Widening of Galleries
Proposal for widening in those galleries is envisaged which shall be required
for the movement of Continuous Miner. All the galleries of the C.M. panels
may not be required for widening. The gallery through which Continuous
Miner (i.e. haulage roadway) is to be driven down would be widened up to
4.8m for lowering of the machine (CM) into the panel. Widening of the
galleries shall be applicable as per the requirement of CM package.
A.
Layout of Panels
The mine is almost developed by Bord & Pillar method of mining in both the
seams along the floor of the seam by LHD or manually in a panel form. So,
the existing panel lay out or lay out proposed in the working plan shall be
taken as the lay out of the panel for heightening of galleries.
Job No: 3507127
X/12
B.
Manner of Heightening
Heightening of galleries may be done by conventional roof blasting up to 4.6m
height. Blasted coal will be loaded by remote controlled LHD.
E.
Manner of Widening
Manner of widening of galleries may be by side blasting with permitted
explosives only and loading of blasted coal by LHD onto Chain Conveyor.
F.
Face Equipment
The coal obtained due to heightening/ widening of coal shall be loaded by
remote controlled LHD. Two numbers of remote controlled LHDs shall be
deployed in Heightening panel.
G.
Coal Evacuation from Panel
The coal shall be loaded on to Chain Conveyor by remote controlled LHD.
Chain Conveyor will feed coal to gate belt conveyor for coal evacuation from
panels.
H.
Ventilation of Panels
Heightening panels comprise of 4 to 8 headings, which is already developed.
In five headings panel, three headings in the dip side of the panel shall act as
the intake air and two headings on the rise side shall act as the return airway
of the panels. In other cases, the manager of the mine may arrange the intake
and return accordingly for safe working.
I.
Face Ventilation
The Auxiliary Fan with ducting shall do face Ventilation.
H.
Support System
The RMR of LBS varies between 41.7-61. It indicates that the immediate roof
of LBS is of fair category.
As remote controlled LHD is envisaged for loading of coal in the panels, it is
necessary that supports should be so designed that clear space is available
for movement of the machineries. At present, the panel is developed up to
2.4m and is supported as per the approved SSR. Now it is to be heightened
up to 4.6m. So, fresh SSR should be prepared and approved by the DGMS
and should be effectively complied.
The bolt density for three types of roof classified on the basis of RMR value as
recommended is as below:
Poor roof
-
1.2 to 1.5 bolts/m2
Fair roof
-
1.0 bolt/sq.m.
Good roof
-
0.7 bolt/m2
Job No: 3507127
X/13
As per the RMR value, the roof of UBS and LBS falls in fair category of roof.
So, the density of roof bolts in the Heightening panels should be 1.0 bolt/sq.m.
The bolt angle should generally be normal to the bedding plane in the
roadways/galleries. This also holds good for other panels of the mine.
Support materials should be as per DGMS Cir, no. 3/1996.
Support of Heightened Gallery (Within 9m of face) :
Area within 9m of the working face should be treated as the green roof. The
green roof support should be done as per Reg. 108 of CMR, 1957.
Support of Heightened Gallery:
*
After heightening of galleries up to 4.6m, the roof shall be re-supported
with roof bolts by roof bolter.
*
Four bolts in a row shall be installed. The spacing between the bolts in
a row and between the rows shall be 1.2m.
*
Some additional roof bolts shall be installed to increase the density of
roof bolts, as and when required.
*
The spacing between the sides of the pillar and the bolts in a row shall
be 0.6m on the both sides of the pillar corner.
*
Bolts shall not be less than 1.8m/2.4m in length and 22mm in diameter.
Support at Junction: The bolt density should be at least 25% more than the
bolt density of heightened gallery.
Support at Disturbed Places: In addition to the roof bolts, the geological
disturbed area of the Heightening panel shall be supported by cross-bars,
cogs W-straps and other suitable means as and when required.
Supports on Loose Floor: Props shall be set on solid floor and not on loose
packing material. The support shall be kept tight against the roof. Wherever
the props are to be set on sand a flat base piece not less than 5 cm thick, 25
cm wide and 75 cm long shall be used.
For legged steel cogs of 1.2m x 1.2m piece shall be set on solid floor and not
on loose material. They shall be kept tight with timber sleepers against the
roof to ensure maximum contact between the timber and the roof. The
provisions for support on loose floor shall also hold for other working panels of
the mine.
Support Material: The support material shall be as proposed in DGMS Gr
Tech. 3/1996.
I.
Production Proposed
The production proposed from Heightening panel is 0.15 MT i.e. 500 TPD.
Job No: 3507127
X/14
Before going for heightening or widening of galleries in a panel in any of the
seams or section, prior permission from DGMS should be obtained for that. All
the mining operations in the Heightening panel should be in accordance with
the various regulations of CMR 1957 and circulars issued by DGMS for safe
working of the mine.
10.2.3 B & P DEVELOPMENT & DEPILLARING WITH LOW HEIGHT LHD
Bord & Pillar development & depillaring is proposed in Upper Section of Top
Lower Bachra seam and Bottom Lower Bachra seam/section in Benti block.
The proposed pillar size in both the seam/section is 25m x 25m, in both the
seams/sections, width of gallery is 4.2m and height of gallery is 2.4m or the
actual seam thickness leaving 0.3-0.5m of coal in the roof. The development
is proposed in the virgin area of Upper section of Top Lower Bachra along the
roof of the seam & Bottom Lower Bachra seams along the floor of the
seam/section. It is proposed to leave at least 0.3-0.5m of coal in the roof,
since the immediate roof of both the UTLB & BLB comprises of carb. shale,
grey shale, grey wake, alternating bands of shale and sandstone. The reason
to develop the UTLB along the roof is to maintain the parting thickness of
3.0m between the seams/sections for safe working.
A.
Proposal for B & P Development / Depillaring panels with low
height LHD
Bottom Lower Bachra Seam (BLB)
Panels B-1 to B-4, B-13 to B-15, T-1 to T-2 and B-18-B-19.
Upper Section of Top Lower Bachra Seam (UTLB)
Panels B-1 to B-4, and B-13 to B-16.
B.
Layout of Panels
Since both the sections are contiguous, so layout of panels for UTLB & BLB is
proposed in such a way that pillars in both the sections are vertically
coincident. Generally, five headings panels for both the sections have been
proposed for the development of virgin property in Benti block. Vertical
coincident of pillars should be checked by putting boreholes at the alternate
junctions of the development galleries from either of the workings.
C.
Method of work
Development:
Bord and Pillar method with Conventional Solid
blasting. Low height LHD loading on to face
conveyor.
Depillaring: Conventional Bord & Pillar method with caving in both the
seams/sections.(simultaneous)
D.
Manner of Extraction
Development: The virgin property of BLB seam would be developed along
the floor of the seam leaving at least 0.3-0.5m of coal in the roof. Similarly,
Job No: 3507127
X/15
UTLB seam would be developed along the roof leaving at least 0.3-0.5m of
coal in the roof. The details regarding the development of BLB & UTLB seam
s/sections are as below :
Size of Pillar
= 25m x 25m (Centre to centre)
Width of gallery
= 4.2m
Height of gallery
= 2.4m or actual seam thickness
The parting between two sections should be maintained at least 3.0m.
Depillaring: Simultaneous Bord & Pillar depillaring with Caving in UTLB &
BLB has been envisaged. The developed Pillars would be extracted by
splitting and slicing. Each pillar would be splitted into two equal parts by one
dip split of 4.2m wide. There after level slices of 4.2m wide would be driven
leaving 1.8 m (minimum) rib against the goaf so that the area of roof exposure
at any one working place should not exceed 60 m2 at any time. On retreat, the
ribs would be reduced judiciously. Driving of a slice would commence only
when the extraction in the immediate in bye slice is completed and goaf edge
support as per approved SSR is erected. Only one slice in a pillar would be
driven at a time and extraction of a half of a pillar shall not be commenced
until extraction of the adjoining in bye half of the pillar has been completed.
Diagonal line of extraction would be maintained. The order of slicing should
be strictly followed to maintain the stipulated area of exposure of 60m2 (max.).
In no condition, except with the permission of DGMS, the area of exposure
should be more than 60m2.
E.
Coal Evacuation from Panel
It is proposed that the blasted coal shall be loaded by the low height LHD on
to chain conveyors and chain conveyor fed it to the gate belt conveyor for
transportation of coal from panel. This system will be applicable for
development and depillaring panels of both UTLB & BLB. Since the working is
contiguous, simultaneous working is to be done in both the seams/sections.
F.
Panel Ventilation
Two or three headings in the dip side of panel (depending upon the size of
panel) shall be used as intake airway and two or three headings on the rise
side of the panel shall be used as the return airway of the panel. The face
ventilation of the panels in both the conditions while development and
depillaring shall be done with the auxiliary fans as and when required. This
will be applicable for both the UTLB & BLB seams/sections.
G.
Face Equipment and Transport
Electric coal drill, Auxiliary fan, face pump may be the face equipment in
UTLB & BLB workings. Blasted coal would be loaded by low height LHD on to
chain conveyor and chain conveyor will fed to gate belt conveyor.
Job No: 3507127
X/16
H.
Support System
The immediate roof of Lower Bachra seam in the adjoining Churi block is of
fair category. The RMR study for Benti has not been done, so RMR of LBS in
Churi block has been taken for the support design for UTLB & BLB in Benti
block. The support system for the low height LHD working comprises of :
(a)
Support for development.
(b)
Support for depillaring.
Support for Development
There should be a systematic support plan for development workings duly
approved by DGMS in the mine. This shall be effectively complied for all
workings of Churi -Benti Project:
(i)
Support of working face within 9m
All working faces shall be supported by quick setting type full column grouted
bolts. The first row of support shall be at a distance of 1.8m from the face. The
spacing between the rows may be 1.2m. The means of support for the
working faces shall be roof bolts supplemented with conventional support as
and when required.
(ii)
Support of Tramming level
Where required tramming levels shall be supported by cross bars on safari
clamps or in duggis at an interval of
1.2m. In general, roof bolting
supplemented with conventional support as and when required shall support
it. Chocks/cogs shall be set as and when required.
(iii)
Support at Junction
The density of roof bolts at the junction of galleries should be 25% more than
those general galleries. Cross bars, cogs, chocks or other suitable type of
conventional support may also be erected as and when required.
(iv)
Support of Travelling Roadway
In addition to roof bolts, traveling roadway shall be supported by rope stitching
or steel girders or cross bars or vertical props or chocks/cogs at suitable
intervals.
(v)
Support of Airways
In addition to roof bolts, airways may be supported by rope stitching or steel
girders or cross-bars or vertical props or chocks/cogs.
(vi)
Support of geologically disturbed places
Geological disturbed places shall be supported by cross-bars or vertical props
or steel bolts or rope stitching or with chocks/cogs in addition to roof bolts as
and when required.
Job No: 3507127
X/17
Support for Depillaring
While going for depillaring, the systematic support plan should be prepared for
depillaring districts/panels and get approved by the DGMS. It should be
complied effectively for safe working of the mine. The envisaged support for
depillaring panels is as below:
(i)
Support within two pillars of extraction
The support within two pillars length of extraction would be done by roof bolts
at 1.2m spacing in a row and the distance between two rows of such bolts
would be 1.2m. It would be supplemented with the conventional support as
and when required.
(ii)
Split galleries shall be supported with roof bolts at an interval of 1.2m
between the rows and 1.2m between the bolts. Additional roof bolts may also
be provided to increase the density of roof bolts as and when required. It shall
also be supplemented with conventional support as and when required for
safe working of the time.
(iii)
Junction support
Junction will be supported by roof bolts with w-strap chocks/cogs may also be
erected as and when required.
(iv)
Slice support
Goaf side slice will be supported by cogs at 1.5m interval and rib side by roof
bolts with w-strap.
(v)
Goaf Edge Support
Goaf edges will be supported by cogs placed skin to skin with corner props.
Support Material
The specification of support material regarding roof bolts shall be in
accordance with the Cir. Tech 3/1996 of DGMS circulars.
Regarding the conventional support, the specification support material should
be as per the provisions of CMR 1957 and DGMS circulars.
Production Proposed
Production from the B & P development/depillaring with low height LHD is
proposed to be 0.10MTY.
10.3 PRODUCTION PARAMETERS
The production parameters as envisaged in the Churi-Benti Project Report is
as under:
CM Panel
-
0.50 MTY
Low height LHD panel
-
0.16MTY
Job No: 3507127
X/18
Heightening Panel
-
0.15 MTY
TOTAL
-
0.81 MTY
10.3
SUBSIDENCE
The Project Report for Churi-Benti Project covers area of Churi Re-
organization (CRO) and Benti block. Total area under this project comes to
about 7.68sq. km. For deployment of Continuous Miner, the proposed mining
area is 2.44sq. km. The proposed method of depillaring with CM is by caving..
Earlier, a subsidence study was carried out for the Churi UG mine. However,
the part of mining area for CM under Benti block was not considered. Hence,
It is proposed to undertake fresh subsidence study for assessment of damage
to surface for Churi-Benti project.
10.7
EXPLOSIVES & MAGAZINE
The explosives will be used only for B&P districts with LHDs including remote
controlled LHDs panel. The powder factor presently obtained is around
2.0tonne/kg of explosive. Efforts should be made to improve powder factor to
around 2.5tonne/kg. Blasting study may be undertaken for suitable blasting
pattern.
An explosive magazine of 400 kg explosives and 2000 detonators already
exists in the mine. The magazine would be used for the project. It should be
maintained in accordance with Indian Explosive Act & rules there under. The
adequate arrangement should be made for the safety of the magazine.
10.8
SCHEDULE OF EQUIPMENT PROCUREMENT
The year-wise phasing of P&M is given in appendix-A.3.
10.9
GENERAL PRECAUTION WHILE DEPILLARING
a. The extraction or reduction of pillars should be conducted in such a
way as to avoid the extension of collapse or subsidence of the goaf
over unextracted pillars.
b. During the extraction of pillars, no splitting or reduction of pillars or
heightening of galleries should be carried out for a distance greater
than the length of two pillars ahead of the pillar under extraction. While
starting of pillar extraction, it may be extended up to 4 pillars only.
c. Attempts should be made to allow the roof to cave regularly so as to
avoid the presence of large area uncollapsed. So that danger from air
blast or weighting on pillars could be avoided. If needed, suitable
means should be adopted to bring down the goaf at regular interval.
Adequate number of convergence recorder / load cell should be
installed to predict the roof fall.
d. Rib of not less than 1.8 m should not be left against the adjacent goaf.
Some times, this may also be required in split galleries. So if needed, it
must be left in split galleries also and may be judiciously reduced on
Job No: 3507127
X/19
retreat after setting strong breaker line of cogs or other means of
artificial support adjacent to it.
e.
Adequate precautions against „Air Blast‟ as per Cir. Tech.2/1988
should be taken.
f.
The area of exposure at any depillaring slice should not be more than
60m2 at any time.
g.
In case of contiguous working, where the depillaring with caving is
proposed, the extraction in both the seams or sections should be in
such a manner that the line of extraction in both the seams/sections
should be vertically coincident up to each other and in case of any
trouble in one section, persons from both the sections should be
immediately withdrawn.
h.
In case of contiguous workings, the pillars in one seam/ section, should
be vertically above and below the pillars in the other seam or section
unless the strata are inclined at an angle of more than 300 from
horizontal. The partings between two seams/sections should not be
less than 3.0m at any place.
i.
While working in any of the seam/sections, use of CO detector,
methanometer and other safety apparatus must be ensured for safe
working of the mine. The provision for safety apparatus has been made
in this report. Telemonitoring system may also be used at the mine.
j.
Water spraying arrangement to suppress the dust in continuous miner
is an integral part of the machine, so availability of clean water to CM
must be ensured throughout the shift.
k.
The total no. of working panels may be three, and the production
envisaged is 0.81 MTY. So, the ventilation of the mine should be as per
statute and adequacy of ventilation in each panel should ensured. To
check the adequacy of ventilation, ventilation survey for the panels/
mine should be conducted by a scientific body. The provision for
ventilation survey has been made in this report.
l.
As per the geological plan of the blocks, there are too many faults. But
in actual mine operation such no. of faults has not be encountered. But
some minor faults have been encountered as reported by the colliery
management. So, adequate precautions should be taken while working
near the fault. The presence of minor slips cannot be ruled out. So
adequate precautions should be taken while working.
m. Over the leasehold property of Churi-Benti Block, too many important
surface features like nala connected to Damodar River, public road
power line, power trestles, Piparwar rehabilitation site, Piparwar GM
office, DVC substation, etc exists over it. Before working below it, either
it should be shifted/diverted from the proposed mining area or
protective pillars of adequate size considering the angle of draw of 450
of the area to be depillared should be left against such surface features
so that the line of fracture due to caving should not reach to the nala or
other surface features lying over the property and may not affect the
surface features which needs to be protected or may cause danger for
Job No: 3507127
X/20
the person employed there in. Provision of filling of seasonal nala
above the HFL, shifting of trestles has been made in this report.
n.
No working should be conducted within 60m of HFL line without taking
permission from DGMS.
o.
At present, Churi Old mine has the disused isolated working. So
adequate precautions should be taken while restoring the workings in
Churi Old mine in both the seams.
p.
The mine is surrounded by Damodar river, Saphi river, workings of
Ray-Bachra colliery and old abandoned working of Churi which had
been worked in distant past through incline No.2,3,4 & 5. So, adequate
precautions should be taken while working approaches towards these
old workings.
q.
While working both the sections/seams simultaneously, both the
seams/sections shall be under the supervision of same over-man and
one experienced officer should be given for safe working of the mine.
The above provisions will also be applicable for other working panels of
the Churi-Benti project. Provisions for the same have been made in this
report.
r.
In case of any apprehension of danger felt by the supervisor or by any
other official of the mine/project, in any of the panels, the manpower
should be withdrawn for the safety of the workers.
s.
Adequate precautions should be taken to avoid the danger of air blast
and the provision of escape route should be made and kept maintained
in the mine for safety of the mine. The persons should be trained to
deal with any emergency situation, which may endanger the safety of
the mine.
t.
Incubation period of coal for Churi u/g is not known. It should be freshly
determined so that the size of sub-panels can be decided as per the
incubation period. The panel size has been envisaged in this report
considering the incubation period of 9 months.
u.
As soon as the panels are exhausted it should be sealed with the
approved type of isolation stoppings. The competent person to ensure
any leakage from goaved out workings should conduct periodic
inspection of isolation stopping as per Coal Mines Regulation, 1957.
The provision of water seal should be made in these isolation stopping
to prevent the accumulation of water behind the stoppings. The type of
water seal should be of such type that will not allow the leakage of
gases from the goaved out workings.
v.
The earlier subsidence study of Churi underground project clearly
spelled out that the subsidence would reach to the surface so adequate
precaution should be taken to avoid the accumulation of water over the
subsided areas and any surface cracks formed due to subsidence
should be effectively filled with non-combustible material.
w.
Intrinsically safe and flameproof apparatus should be used below
ground. The hydraulic fluid used by the various machines below ground
should be of approved type.
Job No: 3507127
X/21
x. Where blasting is to be done, only permitted explosives should be used
and all precautions as per CMR 1957 with various DGMS Circular
should be effectively complied with for the safe operation of the mine.
y. The working faces in each panel should be supported as per the
approved SSR and if roof bolting is to be done, then full column
grouting should be ensured.
z. Wearing of safety appliance by the workers should be ensured for the
safety of the workers.
aa. The Incline No.1 falls within the HFL line. It is proposed to construct
embankment above 3m HFL to prevent surface inrush of water.
bb. All the safety provisions mentioned together with statutes shall also be
applicable while working in Benti Block.
cc. In addition to above all, such provisions of CMR 1957 and related
DGMS circulars, which attracts attention while carrying out the mining
operation, should be effectively complied for the safety of the mine as
well as the safety of the persons employed therein.
Job No: 3507127
X/22
CHAPTER - XI
MINING SCHEDULE
11.1
PRODUCTION SCHEDULE
A.
Extractable Reserves
The following points have been considered for estimation of extractable
reserves for the project:
 In the Churi block, it has been decided to deploy Continuous Miner in the
western section of CRO & panel E12 & E13, which is free from workable
thickness of UBS.
 In Benti block, the Continuous Miner is proposed to be deployed in Bottom
Lower Bachra seam/section having seam thickness >3.0m, leaving 0.3-0.5m
coal against shale roof, wherever upper seam/sections are not workable.
 The western section of CRO is mostly developed in Lower Bachra seam along
the floor up to 2.4m. It is proposed that the virgin patches falling within the
panels are to be developed and then depillared by Continuous Miner.
 The developed panels in the western section of CRO are proposed to be
heightened up to maximum operating height of roof bolter for deployment of
Continuous Miner.
 It has been considered that the surface features (like GM office, DVC sub-
station, Pvt./Company quarters, trestles, road, etc.) will be shifted to maximize
extraction from the panels.
 Villages are proposed to be rehabilitated.
 No depillaring is proposed below the Piparwar rehabilitation site.
 The pillar size in developed panels has been considered as 25m x 25m and
gallery size 4.2m x 2.4m. The extractable reserves for CM panels have been
estimated considering percentage of extraction as 65% of the in situ coal in
pillars.
 For virgin panels in Benti block, the 5-headings panel with pillar size of 25m x
25m and gallery width of 4.8m has been considered. For virgin area falling
within existing mine boundary & fault F13, has been not been considered.
 The existing connecting panel between Churi & Benti block, i.e panel W6 has
not been proposed for depillaring till completion of extraction in Benti block.
 Provision for protective pillars below the nala flowing over the panels in the
western section of CRO and Piparwar rehabilitation site has been made and
reserve blocked in protective pillars has not been considered in extractable
reserve.
 The reserves for Bord & Pillar in contiguous seams in Churi & Benti block has
been estimated considering leaving parting of 3.0m in from the floor of upper
including actual parting. It includes the reserves in virgin patches in the panels
and in existing developed galleries (i.e, heightening while depillaring) up to
4.0m or the actual seam thickness, whichever is more. Depillaring reserves
has been calculated assuming that the surface features over the panels shall
be shifted. Pillar size has been taken as 25mx25m and gallery width of 4.2m.
Job No: 3507127
XI/1
The summary of extractable reserves in different seams/sections is shown in
Table 11.1. The panel-wise extractable reserves is given in Annexure-A.
Table 11.1 : Summary of Extractable Reserves (MT)
Seam / Section
Churi block
Benti block
Total
Dev.
Dep.
Dev.
Dep.
A. Continuous Miner
Lower Bachra seam (LBS)
0.224
2.979
---
---
3.203
Bottom Lower seam (BLB)
---
---
0.464
0.547
1.011
Sub-Total
0.224
2.979
0.464
0.547
4.214
B. Heightening District
Lower Bachra seam (LBS)
0.915
---
---
0.915
Sub-Total
0.915
---
---
0.915
C. Bord & Pillar
Upper Bachra seam (UBS)
0.755
2.928
---
---
3.683
Lower Bachra seam (LBS)
0.242
5.037
---
---
5.279
Bottom Lower Bachra (BLB)
---
---
0.521
0.748
1.269
Upper section of Top Lower
---
---
0.418
0.430
0.848
Bachra (UTLB)
Sub-Total
0.997
7.965
0.939
1.178
11.079
From the above table, the reserves considered for the proposed Churi-Benti project
is as under:
a)
Continuous Miner
(LBS & BLB)
4.214Mt
b)
Heightening District
(LBS)
0.915Mt
c)
B&P development
(UBS, BLB & UTLB)
1.059Mt
It was decided in the FD`s meeting while presenting augmentation report to make
provision of land acquisition for deployment of Continuous Miner only. Hence, B&P
depillaring has not been considered, as surface land is not acquired.
Additional Extractable Reserves:
(i)
Benti block: If the working is extended up to the Fault F13, after statutory
boundary adjustment between Churi-Benti and Ashok project, additional extractable
reserves of 0.784 Mt will be available which may provide longer span of life for the
continuous miner.
(ii)
Additional Extractable Reserves in seam thickness beyond proposed
extraction thickness of 4.6m
In western section of CRO, reserves are blocked in LBS beyond proposed
extraction thickness of 4.6m. It is expected that about 1.0Mt of extractable reserve is
blocked in thickness above 4.6m. While finalizing the specifications of Continuous
Miner, care may be for maximization of extraction thickness.
Job No: 3507127
XI/2
Reserves in panel lying in the eastern section of CRO & Old Churi in UBS &
LBS may be considered for deployment of CM after scientific studies.
B.
Mining Schedule
The following points has been considered for mining schedule of Churi-Benti
UG project:
 It is proposed to deploy Continuous Miner initially in virgin area of Benti block
for B&P development to generate confidence and facilitate learning of the
technical know-how.
 Simultaneously, heightening of existing galleries of the panels proposed for
extraction with Continuous Miner will be undertaken.
 After initial development & depillaring by Continuous Miner in Benti block, the
Continuous Miner would be deployed for depillaring of standing pillars in Churi
block. The depillaring is proposed to commence from the extreme panel / dip
most side of western section of CRO.
 At present two B&P development panels/districts are working. The B&P panel
with LHDs is working in Bottom Lower Bachra seam/section in Benti block
while the manual B&P district is working in Upper Bachra seam in Churi block.
 It is proposed that the B&P district with LHDs will continue with development
in Benti block (Bottom Lower Bachra-BLB & Upper section of Top Lower
Bachra- UTLB seam/sections). The manual B&P district is proposed to
phased-out with introduction of Continuous Miner & Heightening districts.
 It is proposed for shifting of surface features (power trestles, road, etc.) and
rehabilitation of villages overlying the proposed panels for Continuous Miner.
The surface features should be shifted well ahead of the mining schedule for
CM production to facilitate extraction. The provision for the same has been
made in this report.
 Panel W-6, considering the entry to Benti section is not proposed for
extraction till completion of final extraction in Benti block.
 Prior to deployment of CM in Churi block, existing panels are to be heightened
as proposed. Heightening of the panels should be sufficiently advanced for
timely deployment of Continuous Miner.
 The Continuous Miner is proposed for introduction in the third year from the
zero date. In the first two years, before commencement of operation of
Continuous Miner, initial preparatory work would be undertaken.
 It has been assumed that all the preparatory work in the including land
acquisition, EMP approval, etc. and procurement & commissioning of
equipment would be completed in two years.
 The existing LHDs in the mine should be replaced with low-height LHDs to
continue with B&P development in low seam /section thickness horizons.
 Available working days in a year has been taken as 300days.
 After completion of heightening district, for the balance life the equipment may
be deployed for depillaring of the reserves standing on pillar in the mine.
Job No: 3507127
XI/3
 In case, reserves considered for Continuous Miner exhausts early, alternative
place of deployment may be suitably identified and arranged for shifting for its
gainful utilization.
 The depillaring of B&P panels of Benti Block in Churi-Benti project has not
been considered, as it would require acquisition of land. As decided in the
FD’s meeting provision for land acquisition is to be made only for Continuous
Miner.
 While working with Continuous Miner in the proposed area of Churi-Benti
project, scientific studies may be conducted for depillaring of standing pillars
in remaining areas of the Churi block by Continuous Miner. If the results of
scientific studies permit, CM may be deployed in the remaining areas after
exhaustion of reserves in Churi-Benti project.
C.
Construction Period
The first two years will be construction period. During this construction period,
the following activities should be completed:
 NIT and Tendering.
 Finalization of contract for supply of CM package
 Scientific studies for selection of appropriate support and method of
work for deployment of CM.
 Permission from DGMS to work with CM
 Permission for heightening of existing panels
 Acquisition of land for depillaring.
 Shifting of Power trestles, road and other surface features .
 Rehabilitation of villages.
 Heightening of existing roadways including inclines for marching of CM
package to underground
 Strengthening of transport system as per requirement of CM
 Construction of UG strata bunker and drifting
 Construction of water reservoir and water filter plant
 Strengthening of workshop as per requirement of CM.
 Strengthening of ventilation system by opening of Churi old workings
and establishing main return through LBS.
 Drivages of roadways below Damodar River to provide additional
approach to Benti block.
The next two years will be production built-up period. Production from
Continuous Miner and Heightening district will commence from 3rd year
and target production of 0.81 MTY will be achieved in the 4th year.
Based on above, production schedule from the Churi-Benti project is
proposed as under:
Job No: 3507127
XI/4
Technology
Production from Working Districts/ Technology (Mt)
/
Continuous
Heightening panel
B&P with low-
Manual
TOTAL
Year
Miner
with remote
height LHDs/
B&P
controlled LHDs
Normal ht LHD
Year 0 /
---
---
0.10
0.06
0.16
Existing
Year 1
---
---
0.10
0.06
0.16
Year 2
---
---
0.10
0.06
0.16
Year 3
0.40
0.10
0.16
---
0.66
Year 4
0.50
0.15
0.16
---
0.81
Year 5
0.50
0.15
0.16
---
0.81
Year 6
0.50
0.15
0.159
---
0.81
Year 7
0.50
0.15
---
---
0.65
Year 8
0.50
0.15
---
0.65
Year 9
0.50
0.07
---
0.57
Year 10
0.50
--
---
0.50
Year 11
0.31
--
--
---
0.31
11.2 COAL QUALITY
The grade of coal in Lower Bachra seam (LBS) in Churi block varies from ‘A’
to ‘E’. In the panels proposed extraction with Continuous Miner (and heightening
district for CM panels) with seam section of 4.6m, the grade of coal generally is from
‘B’ to ‘C’ (long flame). In Benti block, grade of coal of Bottom Lower Bachra seam
(BLB) in proposed panels for Continuous Miner varies from ‘A’ to ‘C’ (long flame),
generally ‘B’ grade (long flame).
In Benti block, the development reserves for B&P panels with LHDs in Bottom
Lower Bachra (BLB) & Upper section of Top Lower Bachra (UTLB) varies ‘B’ to ‘D’
and ‘D’ to ‘E’, respectively.
The declared grade for Churi UG during past several years of its mine
operation has been grade ‘B’ (long lame), however the geological grade is ‘C’.
Almost entire Churi UG mine has been developed and presently B&P development is
being continued in Benti block. The present declared grade of coal is ‘B’ (long flame).
After discussion in FD’s meeting on 5.12.06 and 22.3.07 at CCL, it has been decided
that declared grade of the mine should be taken for planning purpose instead of
geological grade ‘C’.
Considering the extractable reserves and variation of grade in the property for
CM, B&P & heightening panels, the average grade of coal is expected to be of grade
‘B’ (L/F). Accordingly, grade of coal for financial evaluation has been considered as
Grade ‘B’ (L/F).
11.3 ZERO DATE
Job No: 3507127
XI/5
Zero date of the project has been considered as the date of land acquisition,
EMP approval and/or sanction of report, whichever is later.
Job No: 3507127
XI/6
CHAPTER - XIII
MINE VENTILATION
13.1 DEGREE OF GASINESS
Churi UG is an existing mine in North Karanpura coalfield presently working
Upper Bachra seam & Bottom Lower Bachra seam. The mine has been categorized
as degree-I gassy mine. No active emission of inflammable gas has been noticed
during development in Upper & Lower Bachra seams and in Bottom Lower Bachra
seam in Benti block. Further, it is proposed to continue work in Bottom Lower Bachre
& Upper section of Top Lower Bachra in Benti block and Lower Bachra seam in
Churi block. Hence, gassiness of the mine has been taken as degree-I, for the
purpose of assessment of ventilation requirement & planning.
In conformity with Coal Mines Regulation, 1957 & related circulars issued by
DGMS & standards of ventilation, following criteria have been used:
a)
Restrictions on the maximum velocity in a drivage or mine entries
Fan drift or Ventilation shaft
-
15m/s
Man winding shaft or haulage roadways
-
8m/s
Other roadways
-
6m/s
Conveyor roadways
-
4m/s
Face
-
4m/s
b)
Minimum air quantity requirement in a panel at LVC
Based on the production from a ventilation district
-
2.5m3/min./t
Based on the manpower deployed in the largest shift
- 6m3/min./person,
Which ever is more.
c)
Requirements of minimum velocity at the working faces in the mine
Immediate out bye of ventilation connection from face
-
30m/min.
4.5m from face on intake side of brattice/partition
-
30 m/min.
7.5m out bye of the discharge end of an air pipe
-
15 m/min.
d)
Estimation of aerodynamic resistance of a path/mine
R = k x P x L / A3 R - Aerodynamic resistance in kg sec2 m-8
Where,
k - Coefficient of aerodynamic resistance
P - Perimeter of the path in metre
L - length of airway in m
A - area of x-section in m2
e)
Estimation of pressure requirement for a path/fan
P = R x Q2
Where, P - pressure drop in Pa
Q - air flow through a path in m3/s
f)
Estimation of motor power requirement for the main fan
Q = 1.1 x P x Q/(nf x nt)
P - main fan pressure in Pa
Where,
Q - air flow through the main fan in m3/s
nf & nt - fan & transmission efficiencies
g)
Standards of Ventilation Efficiency in a mine
Ventilation Efficiency Quotient (VEQ) of a mine
-
60% or more
Operating Efficiency of Main fan (nf)
-
60%
Transmission Efficiency (nt)
-
95%
Job No: 3507127
XIII/1
13.2 AIR QUANTITY REQUIREMENT
The estimated air quantity requirement at the working panels' last ventilation
connections (LVCs) during different stages (refer para 13.3.3) of mine operation as
described above is given in Table 13.1.
Table 13.1 : Estimation of Air Quantity Requirement (in m3) at Panel LVCs
Parameter
Air requirement (m3/s) forProposed Operating panels’ LVC
Continuous Miner Panel
B&P Panel
B&P with remote
with LHDs
controlled LHDs
Production (TPD)
1700
534
500
Manpower (largest shift)
70
120
100
On the basis of production
22.0
22.5
20.8
(@@2.5m3/min/t
Considering production, air
quantity & velocity in panel
would be very high. Hence, air
requirement at velocity of
1.0m/s has been considered.
On the basis of manpower
7.0
12.0
10.0
@6.0m3/min/ person
On the basis of velocity
11.0
5.8
5.8
@0.50m/s (assuming x-
section of 4.8x2.4m/4.6m
On the basis of Temperature
22.0
11.6
11.6
(assuming
temprature
exceeds
30.5oC, taking
velocity of 1.0m/s)
Max. of Air requirement
22.0
22.5
20.8
TOTAL
65.3
On the basis of above, the total air quantity requirement at the panel last
ventilation connection is expected to be about 65.3m3/s. The air quantity would,
therefore, be accordingly regulated so that all the working places / districts get the
required quantity of air as per statute for safe operation of the mine and safety of the
persons employed therein.
One fan (PV-200 type, sec., 79 mm wg) is operating in Churi old section and
catering the existing requirement of the mine. The discharge through the existing fan
is about 50m3/s. Existing fan capacity may not be sufficient to cater the ventilation
requirement of the Churi-Benti Project. However, detailed ventilation survey (
keeping in view that 3 districts would be operated at a time in the Project), should be
carried out to ascertain the actual ventilation requirement for the Project.
For better ventilation in the mine, choking of return, leakage through fan
drifts/shafts, air locks, setting of fan, maintenance of stoppings, etc. should be
examined carefully and adequate steps should be taken for any rise in temperature
Job No: 3507127
XIII/2
and humidity. For better conditions at the working faces, it is desirable to maintain
that the air velocity of air 1.0m/s.
There will be three numbers of panels working at a time. It is suggested that
the colliery management should prepare a ventilation management plan clearly
stating the code of practices and implemented for proper ventilation management in
the mine. In addition to above, various provisions of CMR, 1957 together with
different circulars issued by DGMS should be complied effectively to maintain the
adequacy of ventilation in the working places.
13.3 VENTILATION SYSTEM DESIGN
13.3.1 Present Ventilation Arrangement
9.2
Present Ventilation System
At present, exhaust system of ventilation is being followed for ventilating the
workings of mine. Presently, Churi UG mine is operating mine with two incline entries
(Inc. 6 & 7) on the rise side working as main intake airways and an air shaft serves
as main return airway with a main mechanical ventilator (PV200 make) installed in
the air shaft. The present air discharge through the main fan is about 50.0m3/s at an
operating fan pressure of about 58mm of WG. The details of main intake & return
airways is as under :
Intake airway
Inc. 6
4.8 x 2.8 m2
Inc. 7
4.8 x 2.8 m2
Return airway
Air shaft 1
4.26 dia. (Fan - PV200 make)
Two standby fans exist, one a Model AF-80 fan in the fan drift parallel to the
existing fan drift and other a Model PV-160 fan in 1A incline. Only the main fan
PV200 make is in operation.
Problems in the existing ventilation arrangement / system: The present
VEQ and the system efficiency of the mine is about 39%. The mine resistance is
about 0.2272gaul, which is very high. Besides, there are several bottlenecks in
ventilation system of the mine. A ventilation study has been conducted for the Churi
UG with the existing extent of workings in October 2006. The deficiencies in the
existing system have been indicated. Further, proposals have been suggested for
improvement in the existing system of ventilation. The recommendations of the
report on ventilation system design for the mine submitted in October 2006 should
be complied.
Presently, working panels in Benti block is being ventilated by the existing
approach through W6 panel. It is proposed to operate two districts in Benti block
including Continuous Miner district. It has been proposed for additional approach for
Benti block through W-11 panel. This would facilitate in improving the ventilation for
the panels in Benti block.
Job No: 3507127
XIII/3
13.3.2 Proposed Ventilation Arrangement
It is proposed to utilize the existing ventilation system. Certain modifications in
the underground ventilating paths is suggested to reduce the mine resistance as well
as improvement in ventilation efficiency as mentioned under :
 It has been proposed for additional approach for Benti block through W11
panel.
 The zig-zag return is proposed to streamlined by directing the return air
through trunk roadways of Churi old section in Lower Bachra seam.
Besides, the suggestions made in the report ‘Ventilation System Design’, for
Churi colliery should be implemented.
13.3.3 Ventilation Simulation
From the ventilation study carried out for the mine, it appears that the single
existing main fan may not be adequate as the present discharge is about 50m3/s at
wg of about 58mm. Total air quantity required at panels’ LVC is about 65.3m3/s.
Considering VEQ of 60%, air discharge required through the fan is about 108.83
m3/s. The required pressure at the main fan considering present mine resistance of
0.2272gaul works out to 196mm of water gauge, which is very high. Hence, the mine
resistance needs to be significantly reduced.
Ventilation study has been undertaken for the mine. Several deficiencies have
been indicated in the report. By implementing the suggestions, it has been shown
that the mine resistance is likely to reduce to about 0.14gaul. It is further proposed
for modification in ventilating paths as suggested in Para 13.3.2. It involves opening
of old Churi section and drivages of additional approach to Benti block for additional
return paths. This may reduce the mine resistance further and the mine resistance is
likely to be less than 0.1gaul.
Considering mine resistance of 0.10gaul and air requirement at panels’ LVC
and main fan, the required fan pressure will be about 86mm of wg. To meet the
above required ventilation parameters, the existing main fan along with one of the
standby fan or a new main fan with the suitable parameters (higher volume &
increased discharged pressure) would be required. It is proposed to utilize the
existing resources (main fans).
Hence, it is proposed for operating existing main fan along with another
standby fan in parallel. Simply operating two fans in parallel will not meet the
ventilation requirement of the Churi-Benti Project, unless resistance of the ventilating
path is reduced to less than 0.10 Gaul. Hence, it is necessary to reduce the
resistance by implementing the suggestions mentioned above. The proposed
ventilation arrangement is expected to be adequate for the project after incorporation
of suggestions made above and the ventilation study report. Hence, ventilation
simulation for different stages of the mine has not been carried out.
Job No: 3507127
XIII/4
It is expected that depending upon the layout of ventilating paths, sequence &
extent of working panels and leakages, VEQ of the mine can be improved further,
thereby reducing the required air discharge through the main fan.
13.3.4 Proposed Ventilation Layout
Ventilation layout of the main/trunk headings: The fresh air taken into the
mine through mine entries would be taken to the working panels along the
main/auxiliary trunk roadways. These trunk roadways comprises of 4-7headings.
Generally, 2-3 central headings have been considered as main intake airways while
the flank headings on either side have been taken as main return airways, where
working panels lies on either side to trunk headings. Where the working panels lies
on one side of the trunk roadways, the three headings along/adjacent to the working
panels have been taken as intake airways while the remaining headings will work as
return airways. In the auxiliary trunk roadways, the intake and return airways have
been considered based on minimum requirement of air crossing.
While crossing the Damodar river, the existing trunk headings are limited to 3
headings only. In this situation, 2 headings works as intake and 1 heading as return
airway for the existing workings in the Benti section. It is proposed to re-cross the
Damodar river with limited no. of headings through Panel W-11 of western section of
CRO. It will help in improving the ventilation for the workings in Benti section with CM
and low height LHD.
Ventilation layout of the panels: The existing B&P panels comprises of 4-8
headings in Churi block. For the proposed B&P panels in Bottom Lower Bachra and
Upper Section of Top Lower Bachra seams/sections, 5 headings layout has been
envisaged, wherever possible. In all these panels, it is generally proposed for
ascensional system of ventilation, as far as practicable, with 2-3 headings on the dip
side to work as panel intake airways while 2 headings on the rise side to work as
panel return airways.
13.4 FAN SPECIFICATIONS
The existing main fan (along with standby fans) is proposed to be utilized for
the project. The specifications of the present operating main fan is as under :
Paticulars
Fan & its motor
Model
PV200
Make
VOLTAS
Fan type
Exhaust
Impeller diameter (mm)
2000
No. of V-belt grooves
4
No. of V-belts
4
Fan pulley diameter (mm)
275
Motor pulley diameter (mm)
440
Fan RPM
880
Installed motor power (kW)
90
Motor RPM
1440
Total Current drawn (Amperes)
85
Voltage (V)
550
Job No: 3507127
XIII/5
13.5 AUXILIARY VENTILATION
In the panels, auxiliary fans are proposed to be installed for ventilating the
working faces. Provisions of auxiliary fans and ventilation ducting have been made in
the report for proper face ventilation.
Job No: 3507127
XIII/6
CHAPTER - XIX
MANPOWER, PRODUCTIVITY & TRAINING
19.1 MANPOWER REQUIREMENT
The manpower for the proposed Churi-Benti UG project has been assessed
keeping in view the existing deployment at surface as well as underground. At
present, total of 905 (nos.) manpower is working at the mine (as on 01.01.2007).
The break-up of the existing manpower is given in Table 19.1.
The manpower requirement for has been estimated for the target
production of 0.81Mty, including existing production of 0.16Mty and incremental
production of 0.65Mty. The total manpower has been as 863 (nos.). Out of this
total manpower, underground manpower has been estimated as 651 (nos.) while
the surface manpower has been estimated as 212 (nos.). For the incremental
production of 0.65Mty, the incremental manpower has been taken 293 (nos.).
For surface manpower, all the existing places of deployment have been
taken into consideration. The same may be continued based on requirement.
Additionally, new places of deployment have been identified. For underground
manpower, manpower assessment is based on the requirement of re-organized
trunk transport, re-organized panels & equipment. The underground manpower
requirement has been worked out keeping in view the mine layout, number of
equipment and statutory requirement. Provision for manpower has been made
considering authorized absence of workers.
The detail of job-wise and category/scale-wise requirement of manpower
has been given in Appendix-B. The break-up of total manpower (group-wise) viz.,
Daily rated workers, Monthly paid staff and Executives proposed project is given
in Table 19.1.
Table 19.1 : Summary of Group-wise Manpower
Sl.
Particulars
Existing Manpower
Proposed Manpower
No.
1
Piece Rated Workers
177
---
2
Daily Rated Workers
576
697
3
Monthly Paid Staff
130
138
4
Executives
22
28
TOTAL
905
863
It may be noted that number and category/scale of persons employed may
be changed in actual practice within overall provision of manpower requirement.
Job No: 3507127
XIX/1
Summary of manpower requirement category/scale-wise along with
wages/scales & annual benefits has been provided in Appendix B.1. Phasing of
manpower during initial stages of mine is given in Table 19.2.
Table 19.2 : Year-wise Phasing of Manpower
Year
Existing
Y1
Y2
Y3
Y4
Y5
(2006-07)
Manpower
905
905
905
863
863
863
The retirement profile shows reduction of manpower to the tune of about 150nos.
in the next 2 years and about 235nos. in next 4 years. However, the existing
manpower of 905nos. has been considered during the initial years for the
purpose of present evaluation.
19.2
PRODUCTIVITY & OMS
The target production from the project is 0.75Mty including existing production of
0.10Mty and incremental production of 0.65Mty. The project is likely to achieve
the target production during the year 4. Considering total manpower of 950, the
overall OMS is estimated as 3.32tonnes and EMS is Rs 847.93. Considering
incremental production of 0.65Mty and incremental manpower of 293 (nos.), the
incremental OMS is estimated as 8.5tonnes.
19.3
TRANSPORT OF PERSONNEL
It is proposed for man-riding arrangement for transportation of workmen to the
nearby working places in the mine as the distance of travel is likely to increase
due to increase in the extent of the mine. The same is proposed along the
alignment of trunk roadways. It is suggested for haulage based mine cars for
man riding. However, arrangement / layout and type of man-riding system to be
provided in the mine may be finalized considering the suitability to mine at a later
stage. Lump sum provision for the same has been made in the report.
19.4
TRAINING
The success of Continuous Miner system relies as much on the training
programme and motivation of the management and operators as on the
machinery and methodology. Prior to deployment of CM at Churi-Benti UG
project, a team consisting of executives, supervisors from the mine and Planners
should visit the mines of SECL/WCL where Continuous Miner is in operation. The
supplier should arrange a workshop on operation and maintenance of CM.
Skilled manpower would be required for safe operations of the
machines/equipment and to make the mine a highly productive. The manpower
may be suitably identified and utilized for mine operations. The workers will be
Job No: 3507127
XIX/2
imparted safety & work related training at the V.T.C. Besides, regular refresher
training may be organized for the existing manpower at the V.T.C.
The actual manpower deployment in the mine is generally on the basis specific
job/work requirement. The work-load of the specific job is generally non-
continuous and actual working hours is very low for certain category of jobs. This
requires larger manpower deployment. It is now proposed for deployment of
multi-skilled crew for general services and maintenance purposes (during general
shift) and other works, which are non-continuous and can be clubbed together to
increase the actual working hours and minimise the total manpower. Such multi-
skilled crew is proposed to be developed by in-house training at the area level.
Supplier’s expert should give adequate training on operation of Continuous Miner
and its ancillary equipment to the workers. The education and training for the
electrical & mechanical personnel and operators should be conducted at the mine
site. The operators should be given "on the job" training by skilled, experienced
operator of supplier who will work alongside them for sufficient period until the
trainee is fully conversant with the safe and efficient operation of the controls and
method of work. It is suggested that all persons to be involved in this new
technology should be given a prior general and specific exposure to method of
mining & equipment to be used through theoretical lecture and visual aids, which
may be procured along with equipment.
The operators involved with Mass Production Technology, Belt conveyor,
Haulages etc. and electricians and mechanics would be imparted training by
trained staff for operation of the respective equipments as well as to ensure
safety of equipment. The refresher training will also be imparted to supervisory
staff in the Area Training Center as per the requirement and needs.
Depillaring will be introduced & practiced in the mine for the first time. Strata
control, monitoring as well as management, is likely to critical. It is desirable that
a strata monitoring cell may be established under a senior official at the mine with
appropriate instrumentation for monitoring of the strata and caving. The
executives, supervisory staff as well workers involved with the depillaring / strata
control may be given appropriate training for technicalities of strata management.
Strata control, monitoring as well as management, is likely to critical to the
success of the Mass Production Technology in view of proposed method. It is
desirable that a strata-monitoring cell may be established under a senior official
at the mine with appropriate instrumentation for monitoring of the strata and
caving. The executives, supervisory staff as well as workers involved with the
Mass Production Technology may be given appropriate training for technicalities
of strata management.
Job No: 3507127
XIX/3
It is proposed for operating man-riding system in the mine with a view to
minimise the travel distance. It is necessary that the system works efficiently and
safely. It is therefore proposed for appropriate training of the man-riding operators
and maintenance personnel for man-riding system.
Job No: 3507127
XIX/4
CHAPTER - XX
SAFETY AND CONSERVATION
20.1
Safety Measures
All precautions stipulated under CMR, 1957 and circulars issued by DGMS
from time to time shall be strictly complied with, for the maintenance of safe
working condition in the mine. Some major identified sources of danger and
their preventive measures have been described in the paragraphs given
below.
20.2
Major sources of Danger
The following are identified as the major sources of dangers:
1.
Surface inrush of water from Damodar River, Saphi River, Benti Nala and
other seasonal Nala passing over the leasehold property.
2
Workings of Ray-Bachra colliery and old abandoned workings of lower Bachra
seam which have been worked in distant past through incline no. 2, 3, 4 & 5.
along with old and abandoned workings of adjacent Manki colliery
3.
Strata problem
4.
Fire, spontaneous heating, dust and other inflammable gas.
5.
Geological disturbances.
6.
Blasting in roof of already developed galleries for Heightening of existing
galleries and side blasting for widening of existing galleries to facilitate the CM
operation.
20.3
Preventive Measures
The suggested preventive measures are as under:
A
Surface Inrush of Water: The sources for water inrush into the underground
workings are anticipated from the following sources: -
(a)
Damodar river
(b)
Saphi river
(c)
Benti Nala
(d)
Seasonal Nala passing over the leasehold property.
(e)
Surface cracks due to caving operation.
(f)
Geological disturbances.
(g)
Unplugged exploration Boreholes.
(h)
Potholes created due to caving of the overlying seams at surface.
To guard against the above-mentioned causes, the following measures have
been envisaged.
1.
A solid barrier of 60m has been left against the Damodar & Saphi Rivers.
2.
No working has been proposed within 60m of HFL line, except with the
permission of DGMS.
3.
No depillaring is proposed below Piparwar Rehabilitation site, Seasonal Nala,
Benti Nala. Provisions for protective pillars to protect the important surface
features have been made in the report.
Job No: 3507127
XX/1
4.
The filling of seasonal nala and low-lying area above H.F.L should be done
before going for depillaring operation. If possible, nala may be shifted/diverted
from the existing working. The existing topography compels that nala and low
lying area which comes under HFL line, is to be filled up with OB or other
suitable material above HFL. Since the construction of embankment against
the river Damodar may cause the creation of water reservoir over the
workings, therefore filling of seasonal nala and low lying area above H.F.L
have been proposed. If all the above is not possible, no depillaring operation
should be commenced below this area except with the permission of DGMS.
5.
As subsidence progresses, surface cracks should be filled up effectively with
earth and the ground should be given adequate slope towards the water
bodies for natural drainage, so that surface cracks may not provide the way
for surface water to percolate below ground.
6.
Garland drains should be made around the caved out area to prevent water
accumulation over the caved area.
7.
The surface position of all the faults and geological features should be clearly
marked on the working plan and adequate precautions should be taken
against them.
8.
The HFL line of Damodar River and Saphi River has been drawn as per
survey of 1976. The HFL of these rivers may have changed. So fresh survey
should be conducted to draw the correct HFL line as on date. While
approaching the workings below or near HFL, adequate precautions should
be taken to avoid any danger to the mine.
9.
Effective protective measures should be taken against danger from
accumulation of rainwater, particularly over silted subsidence cracks, shallow
workings etc. as well as against the embankment if any.
10.
Effective measures should be taken against any obstruction in the normal
drainage of the area.
11.
Exploration boreholes, which are unplugged due to any reason, should be
effectively plugged.
12.
Potholes should be effectively filled up.
13.
Constant vigilance to be exercised during rainy season by the competent
person (Manager/ safety officer with senior most mine official & surveyors) to
check vulnerable points and effectiveness of safety measures. In case of any
doubt, persons should be withdrawn safely.
In addition to above, the provisions of Reg. 126 of CMR 1957 together with
circulars issued by the DGMS time to time should be complied effectively for
safe operation of the mine.
B
Underground Inundation: The sources of irruption of water from
underground to the workings are anticipated from the following sources:
(a)
Adjoining Ray-Bachra mine and old abandoned workings of inclines 2,
3, 4 & 5.
(b)
Workings approaching towards geological disturbances (faults, slips
etc).
(c)
Working below goaved out workings.
(d)
Unknown/ hidden water bodies in the overlying strata
Job No: 3507127
XX/2
To guard against the above-mentioned causes, the following measures have
been envisaged -
1.
The provisions of Reg. 107 of CMR 1957 (Working near mine Boundaries)
should be effectively complied with.
2.
Sequence of panel extraction should be such as to avoid working below water
bodies.
3.
The worked out panels isolated with stopping should be provided with water-
seals to prevent accumulation of water under high hydrostatic head behind
the stoppings, without leakage of the noxious gases from the goaved out
area.
4.
Before commencement of extraction of pillars in a seam, the workings/ goaf of
overlying seams should be dewatered and made dry.
5.
Hydro-geological studies should be conducted to locate the unknown/ hidden
water bodies, which might become potential source of inundation in future and
for safe drivages below Damodar River.
6.
While approaching towards river and/ or any accumulated water bodies
advance boreholes should be made by the safety-boring machine. The
provision of the safety-boring machine has been made in this report.
7.
Adequate parting should be left against the fault plane or any other geological
disturbances, if encountered.
8.
All exploration boreholes drilled from the surface should be correlated and
plotted accurately on the working plan and all other plans. The boreholes
should be plugged with cement from bottom to top (full column) wherever
possible, to prevent direct inrush of water through such boreholes.
9.
Any UG workings approaching within 60m of the water bodies, adequate
precautions should be taken as per the statute.
In addition to above, the provisions of Reg. 127 of CMR 1957 together with
circulars issued by the DGMS from time to time should be complied effectively
for safe operation of the mine
C
Precautions Against Spontaneous Heating
(a)
Underground Measures
i)
Where development has been done without giving due consideration to
formation of panels, Isolation stoppings should be constructed to create
artificial panel.
ii)
Caving of seams should be done only in descending order. The crossing point
temperature should be freshly determined (if it is not known) for deciding the
size of the panels/ sub-panels.
iii)
Wherever possible, extracting of the pillars should be done soon after the
development of galleries, to prevent the crushing of pillars. Hence, there will
be minimum time gap between formation and extraction of pillars in each
panel.
Job No: 3507127
XX/3
iv)
Regular and rapid advance of coalfaces should be maintained to ensure rapid
consolidation of the goaf.
v)
Method of mining should be selected in such a manner that the minimum
coal is left in the goaf.
vi)
After completion of depillaring operation, the panel should be sealed off by
construction of approved type isolation stopping.
vii)
Ventilation pressure on the stopping should be kept balanced to prevent
inward leakage of air, which may cause spontaneous heating in the goaf.
viii)
Approved type Hydraulic fluid and fire resistant materials should be used in
the underground.
ix)
The roof coal is bound to left in the panels proposed for CM deployment in
CRO, since only 4.60m is to be extracted. There may be the chances of
spontaneous heating of coal in the goaved out panels. So isolation of panels
should be done with approved type of isolation stopping and regular
monitoring should be done to avoid any dangers in the mine.
(b)
Surface Measures
i)
Surface cracks propagated up to the surface due to depillaring of the
seams should be filled with non-combustible material to prevent the air
leakage into the goaved out areas, which may cause spontaneous heating
in goaf.
ii)
The filling of cracks may be done with earth, clay and non-combustible
material of 1.5m thick nesses. The mutti (earth clay) should be placed in
thee layers of 50 cm each in succession, with proper consolidation. The
mutti seal should be kept moist for a period of 5 years.
iii)
It is observed that fireclay bands exist in the strata overlying the coal
seams in Churi mining block. The fire clay material, being plastic in nature,
may form a natural seal to the cracks caused due to mining. This will
provide additional support in filling the cracks. Hence it is proposed that
fire clay mining should not be permitted in that area.
iv)
In no condition, any combustible material or sand should be used for filling
up the cracks.
In addition to above, the provisions of Reg 117 and Reg 118A of CMR 1957
along with DGMS circulars should be strictly complied for safe operation of
the mine.
D
Precaution against fire
The sources of fire in the mine may be as under:
The spontaneous heating of goaved out panels in both the seams.
The existing fire in the same seams or section.
The existing fire in the near by mine which is connected with the working of
Churi UG by any means.
Due to presence of any source of ignition.
Job No: 3507127
XX/4
Adequate precautions should be taken to prevent the spontaneous heating of
coal. When the UG working approaches to any old working or adjacent
workings, which is under fire, then adequate precautions should be taken as
per statutes for safe working of the mine.
In addition to the above, the provisions of Reg. 118, 119, 120, 121 & 122
together with various circulars of DGMS should be effectively complied with
for safe working of the mine.
E
Precautions due to contiguity of the seams:
Although, this Production augmentation report doesn’t envisages the workings
in the contiguous part but it may have to be done in future. The following
precautions may be adopted in the contiguous part :
(i)
Working in both the seams should be vertically coincident.
(ii)
Vertically should be checked by putting holes at the alternate junctions
of the gallery.
(iii)
The thickness of parting should be not be less than 3.0m in any case.
(iv)
If working is to be done in both the seams independently, prior
permission should be obtained from DGMS and upper seam to be
depillared first.
(v)
For working both the seams simultaneously, the line of extraction in
both the seams should be vertically coincident.
(vi)
In addition to above, the provisions of Reg. 104 of CMR, 1957 and
circulars issued by DGMS should be strictly complied with.
F
Precautions against Noxious gases and Inflammable gases
The Churi UG mine has its underground workings in both the seams namely
Lower Bachra and Upper Bachra and is almost fully developed by Bord and
Pillar method of mining with SDL/LHD loading and manual loading of coal.
During development of both the seams, no incidence of abnormal make-up of
gas was noticed and the mine is declared Degree-I mine. Two main
mechanical ventilators of adequate capacity to cater to the ventilation
requirement as well as for dilution of various gases including inflammable
gases of the mine has been installed at the mine. Presently one fan PV-200 in
air-shaft is operating in Churi Old mine area and is catering to the ventilation
requirement of whole mine. Continuous Miner have in-built methane indicator
along with the other safety instruments, so as to warn in advance before any
apprehended danger. The other following precautions should also be taken:
(i)
Churi underground is degree-I gassy mine. Adequate provisions have
been made in the report towards building up and maintenance of
standards of ventilation as per Reg 130 of CMR-1957.
(ii)
Regular monitoring of atmosphere i.e the presence of noxious and
inflammable gases in the goaf of UBS should be made.
(iii)
The auxiliary fans should effect brisk ventilation of headings/workings.
(iv)
The provisions of Reg 124, 142 and various circulars issued by the
DGMS should be effectively complied with.
Job No: 3507127
XX/5
In addition to that other provisions of CMR 1957 related to gas and ventilation
shall also be complied effectively for safe working
G
Precaution against Dust
Due to operation of Continuous Miner, coal dust may be formed in
appreciable quantity at the face, which may cause health hazards. In order to
prevent it to be air bone, the Continuous Miner cutter head is equipped with
powerful water sprays. An optional integral dust collector is also available with
the machine, which controls the dust in the machine vicinity. The adequate
provision for water arrangement is made in the report. The adequate
precautions should also be taken for preventions of accumulations of dust
particles for safe operation at face. The provision of stone dust barrier should
also be implemented in the gate belt in in bye ends and out bye end. The
other following precautions should also be taken:
(i)
Adequate provisions have been made in this report for supply of water from
surface for dust suppression in CM-panel, LHD panel. Provisions have been
made in this report for adequate ventilation of the workings. Steps should be
taken for effective compliance of the various provisions.
(ii)
It is suggested that regular and systematic sampling of air-borne dust is to be
made for control of air bore dust to safe concentration level.
(iii)
In addition to above, the provisions of regulation 123, 123A and 123B together
with various circulars issued by the DGMS from time to time should be
effectively complied with for safe working of the mine.
H
Precautions for strata control
(i)
While development or depillaring of the panel, the supporting should be done
as per the approved SSR.
(ii)
Since the immediate roof predominantly comprises of carb shale, shaly coal
shale, alternate bands of shale and sand stone, so while development in any
of the seam a coal of 0.3-0.5m thickness should be left against the roof.
(iii)
In case of roof bolting, it must be supplemented with the conventional support
as and when required.
(iv)
The scientific body should conduct the fresh cavability study of the strata for
Churi UG mine.
(v)
Adequate no. of convergence recorder, load cells etc. should be installed
while depillaring in any panel to protect from danger of air blast.
(vi)
Record of local fall and main fall should be properly maintained and analyzed
in the safety committee meeting, so that the general awareness regarding
local fall and main fall can be created among the workers and officials.
(vii)
All other steps as needed by the situation in accordance with the provisions of
regulations and circulars should be taken to avoid any mishaps due to roof
fall.
(viii)
In addition to above, all other provisions of CMR, 1957 which is attracted by
strata problems together with various related circulars should be effectively
complied for safe working of the mine.
Job No: 3507127
XX/6
(ix)
As and when required, induced blasting may also be used to bring down the
roof regularly.
The provisions of Reg 108 of CMR, 1957 and various circulars related with it
should be effectively complied.
I.
Working below PWD road and Power trestles
The PWD road between Bijupara & Hazaribagh together with other roads and
many power trestles are passing almost through the Churi mining area and it
has to be shifted to facilitate depillaring operation in the proposed area. The
provisions for shifting of trestles, road, basti, filling of low lying areas and other
infrastructure belonging to company have been made in this report
Development under these roads and power trestles has already been done. In
case of non shifting of power trestles and the roads, two nos of pillars or
distance considering angle of draw of 45 deg. of the workings (which ever is
more) should be left un-extracted on both sides of the roads and power
trestles to protect it. This should also be applicable for all those surface
features like nala, DVC Sub station, and any other important surface features
which is to be protected and may cause any danger in future.
While working below surface features, the various provisions of CMR
1957 related to that together with various circulars should be effectively
complied with for safe operation.
J.
Signalling & Lighting
Sufficient lighting as per standards will be provided at all the required places
i.e. at coal transfer points, loading points, working faces, along trunk and gate
belts, feeder breaker, switch gear and maintenance area. Adequate lighting
provision has to be made at underground workings, workshop and coal
dispatch area to avoid accidents and to maintain safe working condition. Good
communication between face, conveyor drives, key points in underground,
surface control rooms, offices, workshop etc., is essential for efficient
operations. Intrinsically safe signaling equipment of audio- visual type should
be installed in underground for smooth and efficient communication between
various points. In addition to above, the provisions of CMR, 1957 together
with related circulars should be complied.
K.
Precautions against subsidence due to depillaring by caving
The following control measures have been suggested.
(i)
As subsidence progresses, surface cracks should be filled up effectively with
earth and the ground should be given adequate slope towards the water
bodies for natural drainage, so that surface cracks may not provide the way
for surface water to percolate below ground.
(ii)
Garland drains should be made around the caved out area to prevent water
accumulation over the caved area.
(iii)
It is suggested that mine management should form a team that will be
responsible for the proper and regular filling of surface cracks developed due
to subsidence. The team will also maintain record of the development and
Job No: 3507127
XX/7
filling surface cracks. Mine management at the site should arrange adequate
supply of filling materials.
(iv)
Surface drains should be made outside the subsidence area to prevent the
surface water of adjoining area to come into active subsidence area.
(v)
The topography of the mining area is uneven and the ground elevation varies
from 402 to 468m, i.e. a difference of elevation of 66m. For such terrain, the
maximum anticipated subsidence of 3.655m (for both seam working) is
unlikely to extensively affect the drainage pattern in the area. However,
subsidence may result in the formation of depressions over the center of the
panels where water may accumulate during rains. So, adequate precautions
against accumulation of water may be taken..
(vi)
The surface features, such as rivers, surface structures and PWD road,
existing over the mining area are likely to be affected by subsidence. So either
it should be shifted or adequate precautions to protect surface features may
be taken.
(vii)
The nala flowing over the mining area are likely to be affected by subsidence.
It is to be protected by leaving coal pillars un-extracted vertically below and
within the subsidence influence area. Tenancy land over the mining area is
likely to be affected by subsidence. Thus, if any cultivation is being done in
such land, crop compensation to be paid to the tenancy land owners during
the year when depillaring operation will be carried out in the panels below it
and subsequent reclamation by filling and consolidation of the land.
(viii)
The HT lines over the mining area are likely to be affected by a maximum
amount of 1.908m subsidence. Thus, pylons of HT lines need to be protected
by leaving coal pillars un-extracted vertically below it or HT lines should be
shifted from the subsidence zone.
(ix)
An abandoned quarry on the northern side of the mine boundary is unlikely to
be affected by subsidence as it is away from the subsidence area. It is
recommended that while carrying out extraction in the panels of Upper Bachra
seam, close subsidence monitoring should be done and their impacts and
effectiveness of the mitigative measures should be reviewed before starting
depillaring in lower seam.
L
Precautions against Blasting in Heightening District.
Since the entire mine is developed up to 2.4m only and it is to be heightened
up to 4.60mto facilitate the CM operation for depillaring of standing pillars.
This type of heightening experiences will be totally new for the project. So,
before going for heightening, the permission from DGMS for Blasting,
Support, Ventilation and other workings should be obtained. The entire mining
operation should be in accordance with the provisions mentioned in the
permission. In addition to above, other provisions as per statute should be
strictly complied with.
M.
Environmental Monitoring
To ensure the safe operation of the mine, the following aspects should be
measured periodically and adequate precautions as per statutes should be
taken.
ii)
Fire damp (CH4)
Job No: 3507127
XX/8
iii)
Carbon-Monoxide (CO)
iv)
Temperature
v)
Humidity
vi)
Coal dust concentration
The various provisions regarding monitoring and remedial measures for each
of the above as per CMR, 1957 and other related circulars should be
complied with effectively.
N.
Conservation
In Churi Block, two coal seams namely Lower Bachra and Upper Bachra exist
with a parting ranging from about 0.47-18m. The thickness of Lower Bachra
seam generally varies from 3 to 5m and gradually increases to 9m in the
western part. The thickness of Upper Bachra varies from 2 to 3m in the major
part of the area.
In Benti block, the Lower Bachra seam is splitted in two parts Bottom Lower
Bachra & Top Lower Bachra. Top Lower Bachra further splits into two parts
Upper section of Top Lower Bachra & Lower section of Top Lower Bachra. In
part of the areas these two section merges and forms combined Top Lower
Bachra. Two sections namely, Bottom Lower Bachra & Upper Section of Top
Lower Bachra / Combined Top Lower Bachra is workable through out the
property in Sector-A of Benti Block.
The mine is developed up to 2.4m in most part of the property in Churi
Block. Presently development is in progress in bottom lower Bachra seam in
Benti Block. The development height is 2.4m.
The maximum cutting range of the proposed Continuous Miner (which
has been successfully deployed at Anjan Hill Mine, SECL) is about 4.6m.
Continuous Miner having cutting height more than 4.6m. is also available. But
it requires gallery width of 5.5m. But LBS has been developed with gallery
width 4.2m. So, it limits the choice of the machine. The percentage of
extraction achieved may be about 65% of the coal in standing pillars,
considering the average thickness of coal in the area proposed for mining. In
general, coal seams exhibit variable thickness. The seams having thickness
greater than 3.0m has been proposed for continuous miner working. The use
of continuous miner will increase the percentage of recovery as compared to
conventional Bord and Pillar Method. The layout of panels and the extraction
of pillars have been envisaged in such a manner to result minimal losses of
coal in the goaf.
O.
General
All underground workers will be provided with self-rescuers and all such
resources will be examined and maintained by competent person. Where
formation of coal dust is more than permissible limit, approved type of dust
respirator will be provided to the workers. The various provisions of CMR,
1957 related with the safety of the mines and persons employed there in
Job No: 3507127
XX/9
should be strictly complied with. Adequate precaution should be taken in
operation of haulage & conveyor roadways.
Job No: 3507127
XX/10
CHAPTER-XXI
ENVIRONMENT MANAGEMENT
21.1 GENERAL
The present report covers part of area under Churi & Benti (partly) blocks.
Upper & Lower Bachra seams are presently being worked at the mine. Presently
development is in progress in Bottom lower Bachra seam of Benti block (Sector-A)
and upper Bachra seam of Churi Block. It is proposed to introduce Continuous Miner
technology in the mine. The method of mining proposed is Bord & Pillar with caving.
The average seam thickness within proposed mining area of the workable seams is
about 5.5m. The range of extraction height in the seams will be restricted to 4.6m.
The maximum depth of mine workings in the mining area is likely to vary from about
21m to 121.68 m.
A study for subsidence prediction and management for Churi U/G was carried
out at CMPDI (HQ) considering 4.6m of extraction and extraction for both the seams.
It has been estimated that the maximum possible subsidence over the mining is
3.784m. The estimated tensile strain values in the forest area due to extraction of
Upper and Lower Bachra seams individually and after extraction of both the seams
are exceeding the limit prescribed by MOEF, i.e. 20mm/m. In the forest area such
amount of tensile strain is likely to develop surface cracks more than 300mm wide.
Part of the Benti block was beyond the scope of the study for subsidence. Churi-
Benti project consists of part of Churi Block and part of Benti Block.
The method of extraction proposed for Churi-Benti Project is B & P with
caving. Previously, no depillaring activities have been undertaken within the mining
area. Major area under the project lies at moderate depth of cover. It is expected that
caving in underground may cause subsidence at surface. Hence, it is proposed to
undertake fresh subsidence study for appropriate evaluation.
The surface topography of the mining area is uneven. The ground elevation varies
from 402 to 468m above MSL. The general slope of the area is towards east and
west sides. Damodar and Saphi rivers flowing on the western and eastern boundary
of the Churi block respectively and control the surface drainage of the existing mine
area. Major portion of the surface over the proposed mining area is under forest and
remaining is tenancy land. PWD road, few kutcha, Power trestles & forest roads are
passing over the mining area. Accordingly, these surface features are proposed to
be shifted and villages are proposed to be rehabilitated / resettled
Provision has also been made for compensatory afforestation, anti-pollution
measures, base line data generation, and for earth filling over subsidence area
caused by depillaring with caving
Job No. - 3507127
XXI-1/2
Sufficient storage capacity has also been provided in the main underground
sump, so that the suspended dust particles generated due to underground mining
operations settle down and comparatively cleaner water is discharged on the
surface. Capital provision for settling tank has also been made in this report. Oil &
grease trap would be constructed near workshop to treat effluents.
The solid waste debris due to excavation of inclines/drifting, etc. would
be utilised for making the haulage embankment and surface levelling. So, any
adverse effect on environment is not expected. Plantation at industrial site may be
done for aesthetic look.
The noise level at the transfer points of coal in the underground workings as
well as at the face and on surface, would be kept within the permissible/
recommended level of 85dBA. The general ecology comprising flora/fauna/general
environmental and air, water, noise etc will be protected and improved.
21.2 COMMUNITY DEVELOPMENT
For better relation with the neighboring villages and as corporate social
responsibility, it is required that community work like play ground, park, drinking
water, road etc. may be provided. Churi UG mine is an existing mine and several
works have been undertaken in the past for community development. However,
provision of lump sum additional capital for community development has been
envisaged.
21.3 EMP CAPITAL
The total additional capital under EMP head has been estimated and is shown
in appendices. Further, provision has been made for EMP related activities from
revenue account @Rs. 4.0/tonne, as ‘Environmental Protection Cost’.
EMP of Churi UG Project was prepared in the past considering the technology and
production target of approved Feasibility Report. Since the technology and mining
area has changed and boundary has also been re-adjusted, there is a need for
preparation of a new EMP considering all the aspects of the Churi-Benti Project.
A comprehensive EMP report dealing with the impact of mining on
environmental attributes & various mitigative measures will be prepared separately.
Job No. - 3507127
XXI-2/2
CHAPTER-XXII
MINE CLOSURE PLANNING
22.1 PREAMBLE
Mining is a hazardous operation as it offsets the equilibrium of natural
depositional environment viz. in-situ stress field, ground water, surface drainage
system as well as the socio-economic condition. Although mining activities are
usually short-term phenomena, they are liable to leave long lasting impacts on
landscape, ecology and on the mind set of local inhabitants. Thus, it is imperative
that any mining venture should have adequate closure plan addressing issues viz.
reclamation and environmental protection, rehabilitation of disturbed area.
Community implementation of mine closure plan will incur some extra cost,
neglecting this aspect will lead to future problems of attending compensation or
expensive socio-economic problems.
Hence, efforts have been made to identify the likely impacts on geo-
environmental and socio-political set-up due to closure of the proposed Churi-Benti
UG project during the planning stage itself, so that it will offer an opportunity to
generate resources for mitigative measures during closure of the mine.
22.2 LIFE CYCLE CONCEPTS
Mining Projects have a definite life cycle. All the mines have to eventually
close their operation. The reasons for the closure may be many including economic
conditions, depletion of mineable resource or any other unforeseen safety reasons.
In the present project proposal the mine life cycle planning is governed by the
reserves content in the proposed mining area. Here, it is planned to exploit Lower
Bachra seam in Churi block and Bottom Lower Bachra seam & UTLB in Benti
section. As per mining schedule, the project life is estimated as 11 years. It is
suggested that the activities for closure will be initiated at an early stage of project
life in a gradual/planned manner.
22.3 MINE CLOSURE PHASE
The mine closure phase is supposed to be closed when the mine is de-
commissioned, facilities at site are removed, the mine entries are sealed / fenced off,
the management of waste dump/tailing is completed and the site is released in
ecologically sustainable suitable for proposed land use.
The likely impacts due to closure of the mine in so far as the geo-technical/
safety/ environment and socio-political aspects are concerned and the suggested
mitigative measures are elaborated as under:-
A) Technical aspects:-
i) Mine Entries : It is suggested that mine openings & workings will be
properly closed & sealed so as to prevent any danger to post-mining uses of area.
ii) Service Buildings : The service buildings/structures will be removed/
demolished or may be used for some offices and the land covered under them
restored for productive uses.
Job No. - 3507127
XXII-1/3
iii) Hazardous substances : Prior to surface demolition/restoration, a surface
audit will be undertaken on all surface structures, spoil heaps, lagoons etc. to assess
whether there are any hazardous materials that could cause problem i.e. explosive,
asbestos, chemical oil etc.
iv) Disposal of assets : A list of surface and UG assets (P&M) will be
prepared and made available to potential purchasers or transferred to other
new/working mines of the company. This will ensure that the assets perform till its
economic life and have better utilisation of assets.
B) Environmental aspects
i) Post closure Env. monitoring : It is suggested that the air & water quality
parameters in the mined out area is monitored by some agency even after closure of
the mine.
ii) Land reclamation and rehabilitation : The area on surface is mainly
covered by forest, tenancy, cultivable & Govt. land. The method of mining is
depillaring by caving under low to moderate depth of cover. The degradation of
surface is expected due to caving. If any cracks / voids are created due to
underground mining activities, it will be restored to original profile by filling up cracks
/ voids. The post-mining surface profile should ensure no accumulation of water and
to maintain the general drainage pattern. It is suggested that the site restoration is
progressive so that the restoration is more or less similar to the rate of mining.
The objective of restoration of post-mining area will be determined through
consultation with local community and the govt. authority, so that the potential/
required end use of the mined out land is determined in advance. Such usage may
be agriculture, forestry, amenity development or nature reserve. Necessary capital
provision in the revenue account is indicated in the report.
C. Socio-political aspects
i) Mining Community : Due to closure of mining operation persons directly
employed in the mine will be surplus. It is suggested that suitable manpower plan
may be formulated by the mining company sufficiently before closure of mine for re-
deployment of the work force in other units of the company.
The community in the region is highly dependent on agriculture, forest and
other activities. The existence of mine is providing employment or other indirect
benefits to the community. The mine closure is likely to create negative impact on
the socio-economic condition of the region. It is suggested that the mine owner will
interact with the local govt. to establish strategy for supporting the project affected
community of the region by promoting investment in non-mining related enterprises.
ii) Mining Township and Water supply : It is suggested that the civic
facilities developed during the mining phase will be transferred to the local
govt./municipality so that, the region transforms smoothly into post mining phase.
The plan of closure shall be implemented in consultation with all
stakeholders including state government.
Job No. - 3507127
XXII-2/3
22.4 FINANCIAL ASPECT
A corpus fund is proposed to be created by deducting @Rs.0.50/t from
revenue account & will be released at the time of undertaking mine closure activity. It
may include cost of all closure activities, post-mining land use, organisation for
executing closure activities, post-project monitoring activities, etc.
Job No. - 3507127
XXII-3/3
CHAPTER XXIII
LAND & PROJECT IMPLEMENTATION SCHEDULE
23.1 LAND ACQUISITION
23.1.1 Mining Area
The distribution total area within mine boundary is as under:
Existing area within mine boundary
-
7.68 sq. km
Churi block
-
5.89 sq. km
Benti block
-
1.79 sq. km
Area where CM is proposed
-
2.44 sq. km
Churi block
-
2.03 sq. km
Benti block
-
0.41 sq. km
23.1.1 Quantum & Type of Land
Land-use within mine boundary: The proposed mining area under the project
covers area of existing Churi reorganization (CRO) mine and part of Benti Block. The
northern limit of the mining area in Benti block is up to the existing adjusted
boundary with Ashoka OCP of Piparwar Area. The limits of developed pillars in Churi
block and adjoining virgin area in Benti block up to existing mine boundary
constitutes the mining area for the project. Major part of the area within the proposed
mine boundary is forest land. Power trestles and roads are passing over the
property, which needs to be shifted. Many villages like Pahan Tongari, Sakhuwa
Tola, Jobia Sarna, Manu -Tand, Barwatand, Amba-gram, etc. are situated over the
proposed property. Villages & other surface features falling over the mining area
needs to be shifted / rehabilitated. The quantum and type wise land use of the area
within the proposed mine boundary is shown in Table 23.1. This detail of land is as
per the land use plan supplied by the project.
Table 23.1: Summary of Land-use over Total Area within mine boundary
Usage of
Existing Land Area (Ha)
Total
Land
Churi block
Benti block
(Ha)
Forest
443.48
49.98
493.46
Non-Forest
145.38
129.14
274.52
Total
588.86
179.12
767.98
Within the existing mine boundary, the land over the mining area is to be acquired for
extraction of coal (development & depillaring). The area lying on south of fault F10
has been excluded as extent of mining is not known. Only the area lying on the north
of fault F10 in Churi & Benti block (within existing mine boundary) is available for
extraction and is about 6.04 sq. km. The land use for the above area considered for
mining is shown in Table 23.2.
Table 23.2 Details of actual mining area are as under
Job No: 3507127
XXIII-1/4
Usage of
Existing Land Area (Ha)
Total
Land
(Ha)
Churi block
Benti block
Forest
382.34
49.98
432.32
Non-Forest
58.42
113.56
171.98
Total
430.76
171.98
604.30
If the total area is to be depillared then surface land of 604.3 Ha of land is to be
acquired. It comprises of 432.32.Ha forestland and 171.98 Ha non-forest land. Total
amount of rupees required for the acquisition of this total land will be around 5533.22
lakhs (i.e. 55.33 Crores). As decided in the FD’s of CCL, it was directed to make
provision for land acquisition only for CM deployment.
Land-use for CM Deployment: Out of the total mining area as mentioned above,
only part of the area is proposed for CM deployment. Area of the western section of
CRO (up to W-15 panel) including panels E12 & E13 and part of the Benti block up
to its existing boundary in Benti block. Major part of the area proposed for CM
deployment is forest. The quantum and type wise details of land for the proposed
area for CM deployment are as shown in table 23.2.
So, out of the above 604.3 Ha, only 229.10 Ha of forest land & 15.5 Ha of non-forest
land will be required for CM deployment and provision for the same has been made
in the report which amounts to 28.94 Crores.
Table 23.2 : Summary of Land-use for CM Deployment over Mining Area
Type of Land
Within Existing Boundary
Total Land
Churi
Benti
(Ha)
Forest
203.5
25.6
229.1
Non-Forest
15.5
15.5
Total
203.5
41.10
244.6
The above delineation of land is based on the land use plan supplied by the
colliery authority. Considering possibility of subsidence, it is proposed to acquire land
on surface taking into account the NPV of forestland and compensation of
private/govt./other type of lands.
If CCL management makes boundary adjustment up to Fault F-13 in Benti
block, the additional 31 Ha of land will have to be acquired. Presently, diverted
Benti nala, haul road of Ashoka project & other important road are passing over this
additional property. This 31 Ha land comprises of 24.2 Ha of forestland and 6.7 Ha
of non-forest land. The boundary adjustment can provide a longer development life
for CM. Since Area officials have not agreed for boundary adjustment, this extended
part is beyond the scope of this project report.
Land requirement for other infrastructure of the mine: Major infrastructure
for the project / mine already exists on surface including residential colony & other
welfare measures. The surface land other than the mining has not been proposed for
Job No: 3507127
XXIII-2/4
acquisition. The land acquisition for the project has not been done till today. It has to
be acquired for the project for the exploitation of the developed and virgin reserves.
As directed by FDs, it is proposed to acquire land (all rights / surface rights) only for
the purpose connected with introduction (development & depillaring) of Continuous
Miner only. Accordingly the provision has been made in this report.
23.1.2 Status of Notification & acquisition
The entire area within the proposed mining area is already notified under
section 9 of CBA Act. The details of the land acquisition (as provided by the CCL
authorities) status for Churi-Benti UG project is as below:
a) The revised forest application in new format was submitted to the DFO,
Ranchi (East) on 13.7.05.
b) DFO has forwarded to CF on 27.10.05.
c) Latest development in the process of acquisition of land as communicated by
CCL management is that the proposal for land acquisition is pending with
RCCF.
The actual status for the land acquisition for CM deployment in Churi-Benti
project has been assumed that it is not acquired till today, so the provision for its
acquisition has been made in this report.
The cost of forest land has been taken as Rs 12.60 lakhs/Ha and non-forest land
has been taken as Rs 0.50 Lakhs per Ha. Forest land includes GMK (jungle-
jhari).
23.1.2 Time-frame for acquisition with capital provision
The phasing of the quantity of land and its capital provision is shown in
Appendix-A.1.
23.2 PROJECT IMPLEMENTATION SCHEDULE
The activity for project / mine development will commence only after the
acceptance of De-rating cum completion report (foreclosure) report of Churi UG
project and sanction of the present report. As most of the surface infrastructure
exists, initially efforts would be made to commence the trunk roadway development
in Bottom Lower Bachra seam and undertaking various activities required facilitating
introduction of Continuous Miner. Simultaneously, efforts would be made for timely
procurement & commissioning of the Continuous Miner. Efforts would be made for
consolidation of existing coal evacuation system, man-riding arrangement, pumping
& ventilation re-organization, etc. The schedule for procurement of additional Plant &
Machinery (P&M) & other infrastructure along with their capital phasing have been
detailed in appendices
Zero Date: The zero date for the project has been considered as the date of
sanction of PR and/or EMP approval, which ever is later. The project construction
activities would start from Year 1. It has been assumed that the activity of PR/EMP
approval and land acquisition for CM deployment would be completed in the first two
(2) years, i.e. by the end of Year 2.
Job No: 3507127
XXIII-3/4
For timely implementation of project, it is essential that all activities related to
construction of the project are properly scheduled, closely monitored and effectively
supervised. All departments will have their own implementation schedule to get the
project constructed within the time frame. The resources should be made available in
time as soon as the project report gets sanctioned to prevent time & cost overrun.
The construction activities are required to be identified in detail for appropriate
monitoring and timely implementation of the proposed project so that the project
achieves its target output within time frame.
Construction Team: It is proposed to appoint a Project Officer (mining) of M-
1 rank and Colliery Manager of E-5 level along with a group of Asstt. Managers of E-
4/E-3 level for the mine. It is proposed that each of the units will have a dedicated
team of electrical and mechanical engineers to take up the project development
activities for timely execution of the work.
23.3 YEAR OF COMMENCEMENT OF PRODUCTION
The existing production from the Churi-Benti project is about 0.16Mty. It is
proposed to enhance the production level of the project to 0.81Mty. The target year
to achieve the rated production is Year 4. Year-wise production schedule during
initial years in shown in the Table 23.3.
Table 23.3 : Production Schedule during Initial years
Technology / Year
Year 1
Year 2
Year 3
Year 4
Year 5
Manual B&P district
0.06
0.06
---
---
---
B&P with low-height LHDs
0.10
0.10
0.16
0.16
0.16
B&P heightening district with
---
---
0.10
0.15
0.15
remote controlled LHDs
Continuous Miner
---
---
0.40
0.50
0.50
Total Production (Mt)
0.16
0.16
0.66
0.81
0.81
Job No: 3507127
XXIII-4/4
CHAPTER- XXIV
FINANCIAL EVALUATION
24.1
TOTAL CAPITAL INVESTMENT
Churi UG is an ongoing project in CCL. With the aim of CCL to augment coal
production this PR has been envisaged with production augmentation of
Churi-Benti UG to 0.75 MTY. Accordingly the economics has been worked out
considering introduction of Continuous Miner Technology (for the first time in
CCL). The estimated economics have been discussed in the subsequent
paragraphs.
Initial capital investment has been provided in the report till the year of
achieving rated coal production i.e 4th year. The capital requirement both
Initial as well as beyond target year, has been proposed from the own
resources of the Company. The estimated capital requirement is given below:
Rs.Crores
Sl.
Particulars
1
Initial Capital (Up to target year)
163.41
2
Additional Capital (upto target year)
145.44
3
Existing Expenditure upto 31.3.06
17.97
considered in this PR
4
Capital beyond target year.
2.39
5
Specific Investment Rs./t
2178.81
Foreign Exchange: Foreign Capital will be involved in this project. The
estimated foreign exchange requirement is shown in Appendix-A.3.5.
The details of capital investment under various heads viz. Land (A.1),
Buildings (A.2), Vehicles (A.6), Prospecting & Boring (A.7) and Development
(A.8), are given in the appendices mentioned against each of them.
24.2
CAPITAL INVESTMENT ON P&M
Capital investment on P&M is given in Appendix-A.3. The detailed break-up
for P&M, Electrical, Pump & Pipes, Workshop and Other P&M etc. are given
in Appendix-A.3.1 to A.3.5. The estimated capital investment on P&M is given
below:
Rs. Crores
Sl.
Particulars
1
Additional P&M (up to target year)
111.59
P&M (beyond target year)
-
2
CMT Package (up to target year)
66.80
CMT Package (beyond target year)
-
Job No: 3507127
XXIV/1
a.
Method of Estimation of Capital Cost
The method of estimation of capital investment for P&M, Civil estimates,
Development Capital, Revenue expenditure capitalised etc. is as follows.
b.
Prices of Plant & Machinery
For the plant and machinery, as far as possible, the prices have been taken
from the Standard Price List of Mining Equipment published by CMPDI and
whenever information regarding price was not available, a broad estimate was
made. Price of Continuous Miner has been based on the price of equipment in
a recently concluded agreement between ECL & supplier for CMT introduction
at Jhanjra mine, ECL. The 100% payment to the supplier will be on the basis
of outright purchase.
c.
Estimated Cost of Civil Construction
The basis for the estimation of the cost of civil construction viz. residential
buildings, service buildings, roads etc. has been given in Appendices - A.2.1,
A.2.2 & A.8.2.
d.
Capital Investment on Vehicles
The additional capital investment on vehicles is estimated as Rs. 10.00 Lakhs.
The details are given in Appendix- A.6.
e.
Development
Under this head, estimated investment is given for (a) capital outlay in mines
(Appendix A.8.1), (b) Roads and culverts, including haul roads (A.8.2), (c)
Water Supply & Sewerage (A.8.3). The details of each item are given in the
respective Appendix indicated in bracket.
f.
Opening of Revenue Account
Churi UG project is an existing ongoing project.
24.3 COST OF PRODUCTION
The overall estimated average cost of production of this proposed Project
comes to Rs.1261.01/t and Rs. 1404.94/t at 100% and at 85% operation
levels respectively. The break-up of different cost elements is shown in
Appendix-C1 & C2. Salient points regarding estimation of revenue costs are
mentioned below:-
a)
Salary/Wages : There is no additional requirement of manpower.
However for the purpose of its impact on CPT, the requirement of
manpower is estimated category wise/ scale wise and details of
manpower are given in Appendix - B1.
Prevalent pay scales for executives and non- executives (NCWA-VII)
are adopted. Mid points of the relevant pay scales of executives & non-
executives have been considered in estimating the salary and wages
cost. EMS works out to be Rs. 847.93. The average wages cost per
tonne works out to Rs. 346.40.
Job No: 3507127
XXIV/2
b)
Store :
i)
Repair and Maintenance : As per standard norms formulated by
CMPDI for underground mine.
ii)
Explosive and Timber/Roof Bolting : Based on approximate
consumption pattern of underground mines in the Area.
iii)
POL & Miscellaneous store cost : As per CMPDI norms.
iv)
Spares & Maintenance (for the life of project) for CM (refer to
Appendix A.3.5 for details), has been considered as per the
agreement for Jhanra mine, ECL. These are however subject to
change upon finalisation of agreement with supplier during
implementation.
The average store cost including all the above works out to Rs.
309.61/t.
c)
Power : Detailed calculation of specific energy consumption per tonne
of output is given in the chapter for power supply, illumination, etc.
Power cost per unit kWh is considered as average Rs.3.20/unit. The
average power cost per tonne works out to Rs. 56.84.
c)
Misc.expenses including workshop debit : This covers the expenditure
on printing & stationery, postages, telephone, repairs and maintenance
of assets other than P&M, workshop debits for annual servicing and
overhauling of major equipment, insurance and taxes for vehicles,
normative contractual cost of major maintenance. The average misc.
cost at 100% capacity level works out to be Rs. 64.08 /t.
d)
Supervision Charges for CM : This cost is for a period of five years of
initial operation of CMT package and has been considered as per the
agreement for Jhanra mine, ECL. These are however subject to
change upon finalisation of agreement with supplier during
implementation. This works out to Rs. 138.24/t.
This would involve operational supervision by suppliers’ personnel with
other overheads. The incidence of income tax on salary of such
personnel and service tax on services provided has been included in
these charges.
e)
Depreciation: Depreciation on assets is computed as per the prevalent
norms. The straight-line method of charging depreciation has been
adopted. The average depreciation cost per tonne at 100% level works
out to Rs. 246.29 /t.
e)
Administration charges: It is taken as Rs. 54.46 per tonne of annual
output based on average cost per tonne of CCL .
f)
Interest on Working capital @ 12.5% works out to Rs. 40.59/t.
24.4 GRADE OF COAL SELLING PRICE & PROFITABILITY
The present declared grade is ‘Gr. B’. The same has been considered for the
purpose of present economic evaluation. Considering the above and overall
estimated average cost of production of Rs.1261.01/t and Rs. 1404.94/t at
Job No: 3507127
XXIV/3
100% and at 85% operation levels respectively, the project is likely to earn a
profit of Rs. 179.99/t and Rs. 36.06/t, respectively. The profitability at different
level of operation is presented in Appendix-C.1&2.
24.5 BREAK-EVEN PRODUCTION
It is estimated that the project would break-even at 36.86% of production
capacity.
24.6 INTERNAL RATE OF RETURN
The overall financial Internal Rate of Return (FIRR) of the Project works out to
9.33% and 0.08 % at 100% and at 85% level of production respectively. The
year-wise production and present declared grade ‘B’ selling price of Rs.
1441.00/t has been considered for IRR calculation. However, with a slippage
of grade by one stage i.e Grade C, the IRR will not be positive.
24.7 SENSITIVITY ANALYSIS
The following parameters have been identified for assessing their impact on
the profitability of the project.
a)
Capital investment
b)
Operating cost
c)
Capacity utilisation
d)
Selling price of coal
The above parameters have been increased / decreased in Steps of 5% to a
maximum of 25% over the base case and the IRR have been computed. The
following table summarises the results of sensitivity analysis:
Variable Parameter
IRR at different stages of
5%
10%
15%
20%
25%
1
Increase in Capital
9.33
8.34
7.40
6.51
5.66
4.85
-
2
Increase in Cost of Prodn.
9.33
6.24
3.10
tive
-
3
Decrease in Capacity
9.33
9.12
4.73
0.08
tive
-
4
Decrease in Selling Price
9.33
5.00
0.42
tive
24.8 INCREMENTAL SCENARIO
An option has been included, which shows the incremental impact of the
introduction of CMT in Churi-Benti for an incremental production of 0.65 MTY.
The salient features of the incremental analysis is tabled below:
Sl.
Particulars
1
Incremental Capital (Up to target year) Rs.Crores
145.44
2
Incremental Average cost of production Rs./t
827.16
3
Incremental IRR at 100% of incremental Prodn. %
21.17
4
Incremental IRR at 85% of incremental Prodn. %
13.35
5
Incremental Specific Investment Rs./t
2237.55
Job No: 3507127
XXIV/4

 

 

 

 

 

 

 

 

 

 

//////////////////////////////////////////